Estanzo

Timeline Bar

Promised31 Dec 2015
Registered11 Aug 2017
Today4 Aug 2026

Timeline

Promised completion31 Dec 2015
Revised completion31 Dec 2015
Actual completion
Possession delay127 mo delay

Registration & Cost Details

Registration fee (in ₹)₹4,59,000
Project cost (in ₹ Lakhs)₹1,668 Lakhs
Project duration38 months
Project categoryResidential
Locality
Original start date11 Dec 2012
Proposed start date12 Nov 2012

Inventory

Total units

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9927737788
Emailkpsinfrabuild@rediffmail.com
Coordinator9927737788
AddressC 1/203 Lajpat Nagar, Delhi

No promoter data available.

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
17348B

Revalidated: Plotted Resi development/ Plotted Housing/07289/ADA/LD/24-25/0372/11032025 (1 Jan 2013)

1 Feb 200831 Jan 2013

Revalidated upto: 31 Dec 2015

31 Dec 201531 Dec 2015

Land Parcels

Khasra No.AreaPlot Type
91726480
918, 9196390
92412117
925, 926, 928, 92915665
9301316
9311316
9273631
91726480Khasra
918,9196390Khasra
92412117Khasra
925,926,928,92915665Khasra
9301316Khasra
9311316Khasra
9273631Khasra

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
262 Jan 2006
360516 Jul 2005
484126 Sept 2005
1328221 Dec 2012
46098 Aug 2007
51525 Jan 2008
47226 Dec 2005
104616 Feb 2008

Frequently Asked Questions

What is the RERA registration number of KPS Town Phase - I?

The RERA registration number of KPS Town Phase - I is UPRERAPRJ8995, as recorded on the UP-RERA portal.

What is the RERA status of KPS Town Phase - I?

As reported by UP-RERA, the status of KPS Town Phase - I is "Registered".

Where is KPS Town Phase - I located?

As reported to UP-RERA, KPS Town Phase - I is located at Agra, Agra, Uttar Pradesh.

When will KPS Town Phase - I be completed?

The latest completion date reported to UP-RERA for KPS Town Phase - I is 31 Dec 2015.

Is KPS Town Phase - I delayed?

Measured against the latest completion date reported to UP-RERA, KPS Town Phase - I is 127 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026