Krishna Galaxy

UPRERARegistered

Krishna Galaxy is a RERA-registered residential project by ARIHANT INFRATECH in Sunrakh Bangar,, Mathura (RERA ID UPRERAPRJ325884). Registered with a completion deadline of 29 Oct 2030.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
8%Q4'25
14%Q1'26
18%Q2'26
—Q3'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ325884
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryMathura-Vrindavan Development Authority
Proposed start1 Nov 2025
Project duration60 months
AddressKhasra No. 1186MI, 1194, 1196, Mauza- Sunrakh Bangar, Mathura, Uttar Pradesh, PIN-281121, Sunrakh Bangar,, Mathura, Mathura
TehsilMathura
Applicant typePartnership Firm
Applicant address9, CIVIL LINES, MATHURA-281001
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    Group Housing/07478/MVDA/BP/24-25/1392/14102025

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered22 Jun 2026
Original completion29 Oct 2030
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹39,000
Sanctioning authorityMathura-Vrindavan Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors268 · 3 · 10 (units from plan)
  • 1 BHK160 60%
  • STUDIO70 26%
  • 2 BHK36 13%
  • OTHER2 1%
ConfigurationUnitsCarpet area
1 BHK16042-52
2 BHK3667
OTHER216
STUDIO7026-30
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
Block A · 1 BHK, 2 BHK108042-67
Block B · 1 BHK, 2 BHK108042-67
Block C · OTHER, STUDIO, 1 BHK910816-43
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Kanchana Agrawal
License CA/2016/78675
BBC Company, Near New Bus Stand, B.S.A. College Road, Mathura, Uttar Pradesh
Engineer
Kumar Iquwal Bahadur - Space Innovative Design Associates
3rd Floor, Vimal Tower, Sanjay Place, Agra - 282002
Contractor
B. S. TECHNO CONSTRUCT PVT. LTD.
5 Manas Nagar, Opp. Gouri Plaza, Mathura
Sr.Development work declared to RERA
1Demarcation of Plots
Plot area is Sq. Mtrs. 6726.92 of Krishna Galaxy project , out of Total Land area 7,488.60 Sq. Mtrs.
2Boundary Wall
230 mm wall in brick masonry with first class bricks along with RCC footing and Column structure.
3Road Work
Laying of pavers over well compacted subgrade with GSB layers.
4Footpaths
Footpaths will be constructed using interlocking as per sanctioned plans.
5Water Supply Including Drinking Water Facilities
Laying of PVC / CPVC pipes of required dia as per MEP designs and making of manholes of required size and Water Supply to be collected form pumps size 7.5 HP (2 working +1 standby ) to Under Ground Tanks (Total capacity 340 KL) and Over-Head Tanks (total capacity 80 KL) as per Plans.
6Sewer System
Proper Sewerage system will be constructed using DWC/RCC pipes as per drawings and sewerage will be treated with STP having capacity of 150 KLD and its treated water will be used in flushing gardening and residual will be disposed of in government sewerage system.
7Drain
Laying of DWC/PVC pipes having 150-200 mm dia and making of Manholes by Civil masonry Work.
8Parks
Landscaping work, Horticulture work and Plantation as per sanctioned Plans.
9Tree Planting
Total 35 no. of trees of various categories will be planted in the project as per sanctioned plans like - Neem (Azadirachta indica) , Banyan (Ficus benghalensis), Peepal (Ficus religiosa), Amaltas (Cassia fistula), Mango ( Mangifera indica), Jamun (Syzygium cumini), Ashoka (Polyalthia longifolia), Gulmohar (Delonix regia), Bottlebrush (Callistemon spp.), Shrubs/ Under-growth (Optional), Hibiscus, Bougainvillea, Indian lilac (Lagerstroemia indica)
10Design For Electric Supply Including Street Lighting
Laying of underground HT and LT cables, Erection of poles with provision of 2 nos. of transformers ( capacity 500 KVA X 2 nos. ) , control panels and meter rooms as per UPPCL Guidelines. DG Set (capacity 200 to 250 KVA ) will be installed for the using in back-up of common utilities.
11Community Buildings
Multipurpose hall (235 sq. mtr.) having facility of yoga, meditation, gym and table tennis.
12Treatment and Disposal System of Sewage and Sullage water
Construction of STP collection tank along with modular treatment system, as per MEP drawings and Sewerage Treatment Plant (Capacity 150 KLD) will be installed / constructed as per approved drawings. All sewerage will be treated and treated water will be used in flushing gardening.
13Solid Waste Management And Disposal System
Solid Waste will be collected manually and disposal will be done.
14Water Conservation System
Making of required Rain Water Harvesting pits to filter rainwater of required capacity as per MEP designs.
15Energy Management System Including Use of Renewable Energy
Good quality and approved brand equipment will be used in substation to minimize energy loss as per norms and approved drawings.
16Fire Protection And Fire Safety System
Proper Fire Fighting system will be installed including Fire tanks having capacity of 120 KL, Fire pump 2 nos. 2280 LPM 40-60m head, Jockey Pump 180 LPM 60m, hydrant, sprinkler system, fire alarms, fire extinguishers and fire hose reels as per drawings.
17Social Infrastructure And Other Public Amenities Including Public Health Services
Proper Water supply, sanitary facilities and first-aid box will be provided on ground floor of every tower.
18Emergency Evacuation Services
N.A.
19Other Miscellaneous Work
Proper Security system including Security Guard, CCTV Cameras and controlled access will be made available.
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 29 Oct 2030.

Sanctioned by Mathura-Vrindavan Development Authority · 6,727 sqm of land · an approved plan of 3 blocks and 268 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
Group Housing/07478/MVDA/BP/24-25/1392/1410202530 Oct 202529 Oct 203029 Oct 203329 Oct 2030
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗

Land & documents

18 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
Khasra N0.-1186 MI, 1194 and 1196, Mauza- Sunrakh Banger, Vrindavan, Mathura ( Land Area as per Deed )8020.62Khasra
Khasra No.- 1186 MI, 1194 and 1196, Mauza- Sunrakh Banger, Vrindavan, Mathura ( Land Area as per Site)7488.60Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Sale deed · 21295
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 7224
The registered deed by which the promoter bought the land.
PDF ↗
Khatauni extract · 1428-1433 (Khasra No. 1196)
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1428-1433 (Khasra No. 1194)
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1428-1433 ( Khasra No. 1186)
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · Land area Details Khasra wise of Krishna Galaxy Project
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Allotment letter from the authority · Reply Letter for Krishna Galaxy Project Registration
The development authority’s letter allotting the plot - usually the step before a lease deed is executed.
PDF ↗
Khatauni extract · Khatauni Order Khasra No. 1196 Land Area 510.62 Sq. Mtrs.
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Allotment letter from the authority · Affidavit for Chak Road Krishna Galaxy
The development authority’s letter allotting the plot - usually the step before a lease deed is executed.
PDF ↗
Allotment letter from the authority · Affidavit for Chak Road Khasra No. 1195 no daviation
The development authority’s letter allotting the plot - usually the step before a lease deed is executed.
PDF ↗
Document checklist
DocumentStatusUploaded
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
not reported—
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New28 May 2026 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New28 May 2026 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New28 May 2026 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New28 May 2026 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New29 Dec 2025 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New29 Dec 2025 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New29 Dec 2025 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New28 May 2026 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New27 May 2026 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New29 Apr 2026 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New29 Apr 2026 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New29 Apr 2026 ↗
Agreement for sale (proforma)
The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind.
New9 Jun 2026 ↗

Quarterly progress reports

4 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

4 quarterly progress reports are on file with UPRERA, covering 2025-Q3 to 2026-Q2.

QuarterConstructionCertificates
2025-Q38%CA ↗ · Arch ↗ · Eng ↗
2025-Q414%CA ↗ · Arch ↗ · Eng ↗
2026-Q118%CA ↗ · Arch ↗ · Eng ↗
2026-Q2—CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameARIHANT INFRATECH
RolePromoter · current
RERA IDUPRERAPRM421710
PANABZFA5534B
CIN / TANAGRA16394A
Registered address9, CIVIL LINES, MATHURA-281001
RERA contact
Registered since2025
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Mathura

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
Arihant Infratech Collection Account for Krishna GalaxyBankCanara BankBranchMathura Dhauli PyauBranch addressMathura Dhauli Pyau Branch, In Front of Raman Sweets, Mathura, Uttar Pradesh, Pin-281001Branch districtMathura, Uttar PradeshA/C no.IFSCCNRB0007853Branch emailCb7853@canarabank.com
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
Arihant Infratech Separate Bank Account for Krishna GalaxyBankCanara BankBranchMathura Dhauli PyauBranch addressMathura Dhauli Pyau Branch, In front of Raman Sweets, Mathura ,Uttar Pradesh, Pin -281001Branch districtMathura, Uttar PradeshA/C no.IFSCCNRB0007853
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
Arihant Infratech RERA Transaction Account for Krishna GalaxyBankCanara BankBranchMathura Dhauli PyauBranch addressMathura Dhauli Pyau Branch, In front of Raman Sweets, Mathura, Uttar Pradesh, Pin-281001Branch districtMathura, Uttar PradeshA/C no.IFSCCNRB0007853
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

1 movement

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Quarterly progress report
2026-Q2
QPR 2026-Q2
newly filed with RERA
18 Oct 2026
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about Krishna Galaxy

Is Krishna Galaxy RERA registered?

Yes. Krishna Galaxy is registered with UPRERA under registration number UPRERAPRJ325884, registered on 22 Jun 2026. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for Krishna Galaxy?

The completion date filed with UPRERA is 29 Oct 2030. No completion certificate is on record yet.

Who is the builder of Krishna Galaxy?

ARIHANT INFRATECH is the promoter entity that filed Krishna Galaxy with UPRERA (promoter RERA ID UPRERAPRM421710). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does Krishna Galaxy have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is Krishna Galaxy located?

Krishna Galaxy is registered in Sunrakh Bangar,, Mathura, as filed with UPRERA.

What configurations are available in Krishna Galaxy?

The unit plan filed with UPRERA lists 1 BHK, 2 BHK, OTHER and STUDIO. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in Krishna Galaxy?

The approved unit plan filed with UPRERA runs from 16 to 67 m² of carpet area (about 172 to 720 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in Krishna Galaxy?

The approved unit plan describes 3 blocks and 268 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is Krishna Galaxy?

About 161 units per acre: 268 planned units across 1.66 acres (6,727 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗