Timeline Bar

Registered22 Jun 2026
Today3 Aug 2026
Promised29 Oct 2030

Timeline

Promised completion29 Oct 2030
Revised completion29 Oct 2030
Actual completion
Possession delayOn time

Registration & Cost Details

Registration fee (in ₹)₹39,000
Project cost (in ₹ Lakhs)₹7,135 Lakhs
Project duration60 months
Project categoryResidential
LocalitySunrakh Bangar,
Original start date
Proposed start date1 Nov 2025

Inventory

Total units268
Unit TypeUnitsCarpet Area (sqm)
1 BHK16042.06–52.01
2 BHK3666.86
STUDIO7025.91–30.41
OTHER215.94

Promoters & Contact

Contact Details

Applicant TypePartnership Firm
Mobile8449076666
Emailarihantinfratech222@gmail.com
Coordinator8449076666
Helpline9639222253
Address9, CIVIL LINES, MATHURA-281001

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2025-Q38.0%
2025-Q414.0%
2026-Q118.0%

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
Group Housing/07478/MVDA/BP/24-25/1392/1410202530 Oct 202529 Oct 203029 Oct 203029 Oct 2033

Land Parcels

Khasra No.AreaPlot Type
Khasra N0.-1186 MI, 1194 and 1196, Mauza- Sunrakh Banger, Vrindavan, Mathura ( Land Area as per Deed )8020.62Khasra
Khasra No.- 1186 MI, 1194 and 1196, Mauza- Sunrakh Banger, Vrindavan, Mathura ( Land Area as per Site)7488.60Khasra

Approved Unit Plan

Unit plan rows on file268
Total flats (sum of rows)268
BlocksBlock A, Block B, Block C
Floor types1 BHK, 2 BHK, STUDIO, OTHER

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of Krishna Galaxy?

The RERA registration number of Krishna Galaxy is UPRERAPRJ325884, as recorded on the UP-RERA portal.

What is the RERA status of Krishna Galaxy?

As reported by UP-RERA, the status of Krishna Galaxy is "Registered".

Where is Krishna Galaxy located?

As reported to UP-RERA, Krishna Galaxy is located at Khasra No. 1186MI, 1194, 1196, Mauza- Sunrakh Bangar, Mathura, Uttar Pradesh, PIN-281121, Sunrakh Bangar,, Mathura, Mathura, Uttar Pradesh.

When will Krishna Galaxy be completed?

The latest completion date reported to UP-RERA for Krishna Galaxy is 29 Oct 2030.

Is Krishna Galaxy delayed?

Measured against the latest completion date reported to UP-RERA, Krishna Galaxy is on time.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026