Registered29 Jul 2017
Promised31 Dec 2022
Completed15 Jul 2024

Timeline

Promised completion31 Dec 2022
Revised completion31 Dec 2022
Actual completion15 Jul 2024
Possession delay18 mo delay

Registration & Cost Details

Registration fee (in ₹)₹42,500
Project cost (in ₹ Lakhs)₹10,558 Lakhs
Project duration69 months
Project categoryResidential
Locality
Original start date1 Oct 2017
Proposed start date1 Oct 2017

Inventory

Total units358
Unit TypeUnitsCarpet Area (sqm)
2 BHK16855.06
3 BHK16875.05
SHOP2213.57–16.57

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9810281941
Emailinfo@emenox.com
Coordinator9810479545
AddressCorporate Office : B-48, Sector-67, Gautam Budh Nagar, Noida-201301, U.P.

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q2
2021-Q3
2021-Q4
2022-Q1
2022-Q2
2022-Q3
2022-Q4
2023-Q1

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
BP3117FTS769131 Dec 201530 Dec 202031 Dec 202230 Dec 2025

Land Parcels

Khasra No.AreaPlot Type
GH 04B7500 Sq. mtr.
GH-04B7500Plot

Approved Unit Plan

Unit plan rows on file92
Total flats (sum of rows)358
Total shops22
BlocksA, D
Floor types2 BHK, 3 BHK, SHOP, OTHER

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
840212 May 2011
840212 May 2011
840212 May 2011

Frequently Asked Questions

What is the RERA registration number of La Solara,Phase-2 (Tower A & D)?

The RERA registration number of La Solara,Phase-2 (Tower A & D) is UPRERAPRJ4460, as recorded on the UP-RERA portal.

What is the RERA status of La Solara,Phase-2 (Tower A & D)?

As reported by UP-RERA, the status of La Solara,Phase-2 (Tower A & D) is "Registered".

Where is La Solara,Phase-2 (Tower A & D) located?

As reported to UP-RERA, La Solara,Phase-2 (Tower A & D) is located at Dadri, Gautam Budh Nagar, Uttar Pradesh.

Is La Solara,Phase-2 (Tower A & D) completed?

As reported to UP-RERA, La Solara,Phase-2 (Tower A & D) was completed on 15 Jul 2024.

Is La Solara,Phase-2 (Tower A & D) delayed?

Measured against the latest completion date reported to UP-RERA, La Solara,Phase-2 (Tower A & D) is 18 months beyond that date.