Timeline Bar

Registered9 Aug 2022
Promised31 Dec 2024
Today4 Aug 2026

Timeline

Promised completion31 Dec 2024
Revised completion31 Dec 2024
Actual completion
Possession delay19 mo delay

Registration & Cost Details

Registration fee (in ₹)₹55,500
Project cost (in ₹ Lakhs)₹8,825 Lakhs
Project duration30 months
Project categoryResidential
Locality
Original start date
Proposed start date1 Jul 2022

Inventory

Total units175
Unit TypeUnitsCarpet Area (sqm)
3 BHK175923

Promoters & Contact

Contact Details

Applicant TypePartnership Firm
Mobile9910965333
Emailiresh-rera@niralaindiaparivar.com
Coordinator9810690076
Address201, 2nd Floor, F-8A, Aruna Park, Vijay Block, Shakarpur, East Delhi - 110092

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2022-Q2
2022-Q3
2022-Q4
2023-Q1
2023-Q2
2023-Q3
2023-Q4
2024-Q1
2024-Q2
2024-Q3

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
PLG/(BP)-3091-S/122420 Feb 202020 Feb 202531 Dec 202420 Feb 2025

Land Parcels

Khasra No.AreaPlot Type
GH-03, SECTOR-16, GNIDA78021.19Plot

Approved Unit Plan

Unit plan rows on file99
Total flats (sum of rows)175
BlocksB11, B15, B16, B17, B18, B19, B20, B21, B22, B23
Floor types3 BHK

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of NIRALA ASPIRE PH-IV (B11, B15 to B23)?

The RERA registration number of NIRALA ASPIRE PH-IV (B11, B15 to B23) is UPRERAPRJ508551, as recorded on the UP-RERA portal.

What is the RERA status of NIRALA ASPIRE PH-IV (B11, B15 to B23)?

As reported by UP-RERA, the status of NIRALA ASPIRE PH-IV (B11, B15 to B23) is "Registered".

Where is NIRALA ASPIRE PH-IV (B11, B15 to B23) located?

As reported to UP-RERA, NIRALA ASPIRE PH-IV (B11, B15 to B23) is located at Dadri, Gautam Budh Nagar, Uttar Pradesh.

When will NIRALA ASPIRE PH-IV (B11, B15 to B23) be completed?

The latest completion date reported to UP-RERA for NIRALA ASPIRE PH-IV (B11, B15 to B23) is 31 Dec 2024.

Is NIRALA ASPIRE PH-IV (B11, B15 to B23) delayed?

Measured against the latest completion date reported to UP-RERA, NIRALA ASPIRE PH-IV (B11, B15 to B23) is 19 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026