Timeline Bar

Registered9 Aug 2022
Promised20 Feb 2025
Today4 Aug 2026

Timeline

Promised completion20 Feb 2025
Revised completion20 Feb 2025
Actual completion
Possession delay17 mo delay

Registration & Cost Details

Registration fee (in ₹)₹49,500
Project cost (in ₹ Lakhs)₹7,141 Lakhs
Project duration32 months
Project categoryResidential
Locality
Original start date
Proposed start date1 Jul 2022

Inventory

Total units142
Unit TypeUnitsCarpet Area (sqm)
3 BHK142923–1105

Promoters & Contact

Contact Details

Applicant TypePartnership Firm
Mobile8595000455
Emailrera@niralaglobal.com
Coordinator9582868291
Helpline9311440079
Address975, JANTA FLATS, NAND NAGARI, SHAHDARA, EAST DELHI, DELHI-110093

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2022-Q2
2022-Q3
2022-Q4
2023-Q1
2023-Q2
2023-Q3
2023-Q4
2024-Q1
2024-Q2
2024-Q3
2024-Q4

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
PLG/(BP)-3091-S/122420 Feb 202020 Feb 202520 Feb 202520 Feb 2025

Land Parcels

Khasra No.AreaPlot Type
GH-03, SECTOR-16, GNIDA78021.19Plot

Approved Unit Plan

Unit plan rows on file82
Total flats (sum of rows)142
BlocksB1, B10, B12, B14, B2, B3, B4, B5, B6, B7, B8, B9
Floor types3 BHK

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of NIRALA ASPIRE PHASE-II (B1 TO B10, B12 , B14)?

The RERA registration number of NIRALA ASPIRE PHASE-II (B1 TO B10, B12 , B14) is UPRERAPRJ783018, as recorded on the UP-RERA portal.

What is the RERA status of NIRALA ASPIRE PHASE-II (B1 TO B10, B12 , B14)?

As reported by UP-RERA, the status of NIRALA ASPIRE PHASE-II (B1 TO B10, B12 , B14) is "Registered".

Where is NIRALA ASPIRE PHASE-II (B1 TO B10, B12 , B14) located?

As reported to UP-RERA, NIRALA ASPIRE PHASE-II (B1 TO B10, B12 , B14) is located at 311, Gautam Budh Nagar, Uttar Pradesh.

When will NIRALA ASPIRE PHASE-II (B1 TO B10, B12 , B14) be completed?

The latest completion date reported to UP-RERA for NIRALA ASPIRE PHASE-II (B1 TO B10, B12 , B14) is 20 Feb 2025.

Is NIRALA ASPIRE PHASE-II (B1 TO B10, B12 , B14) delayed?

Measured against the latest completion date reported to UP-RERA, NIRALA ASPIRE PHASE-II (B1 TO B10, B12 , B14) is 17 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026