LANDMARK is a RERA-registered residential project by Balaji Enterprises in Lucknow (RERA ID UPRERAPRJ5016). Registered with a completion deadline of 17 Jan 2023.
RERA status as reported: Registered.Basic details
The promoter’s own descriptions, published as filed. UP-RERA does not certify them.
| RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossary | UPRERAPRJ5016 |
| Project category | Residential |
| Registration type | Ongoing |
| RERA status | Registered |
| Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossary | Lucknow Development Authority |
| Proposed start | 1 Jun 2017 |
| Original start | 1 Jun 2017 |
| Project duration | 68 months |
| Address | Lucknow, Lucknow |
| Tehsil | Lucknow |
| Applicant type | Partnership Firm |
| Applicant address | 3/271 VISHWASH KHAND GOMTI NAGAR LUCKNOW |
| Applicant contact |
Project timeline
Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.
2 building permits sanctioned
Construction start, as declared
A date on the record, not a filing — what was planned as of this entry.
Registered with RERA
- to
Extension granted
“Six months extension in view of force majeure caused by covid-19 pandemic”
Completion promised at registration
A date on the record, not a filing — what was planned as of this entry.
- to
Extension granted
Revised completion deadline
A date on the record, not a filing — what was planned as of this entry.
Completion certificate filed
A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.
Registration & timeline
Dates on the registration itself, not on construction - the quarterly reports carry that.
| RERA registered | 2 Aug 2017 |
| Original completion | 19 Jul 2021 |
| Revised completion | 17 Jan 2023 |
| First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary | 6 Jan 2024 |
| Registration fee | ₹47,500 |
| Sanctioning authority | Lucknow Development Authority |
Inventory
derived from unit plan
The approved unit plan, not an availability list: nothing here says what is unsold.
- 2 BHK36 46%
- 3 BHK36 46%
- 4 BHK6 8%
| Configuration | Units | Carpet area |
|---|---|---|
| 4 BHK | 6 | 203-235 |
| 2 BHK | 36 | 71-84 |
| 3 BHK | 36 | 96-116 |
| Tower | Floors | Units | Carpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary |
|---|---|---|---|
| landmark · 4 BHK, 2 BHK, 3 BHK | 14 | 78 | 71-235 |
Project team & development works
Who was engaged and what was promised. No status is filed against any of it.
| Sr. | Development work declared to RERA |
|---|---|
| 1 | Demarcation of Plots NA |
| 2 | Boundary Wall NA |
| 3 | Road Work NA |
| 4 | Footpaths NA |
| 5 | Water Supply Including Drinking Water Facilities YES |
| 6 | Sewer System YES |
| 7 | Drain YES |
| 8 | Parks NA |
| 9 | Tree Planting YES |
| 10 | Design For Electric Supply Including Street Lighting YES |
| 11 | Community Buildings YES |
| 12 | Treatment and Disposal System of Sewage and Sullage water YES |
| 13 | Solid Waste Management And Disposal System YES |
| 14 | Water Conservation System YES |
| 15 | Energy Management System Including Use of Renewable Energy NA |
| 16 | Fire Protection And Fire Safety System YES |
| 17 | Social Infrastructure And Other Public Amenities Including Public Health Services NA |
| 18 | Emergency Evacuation Services YES |
| 19 | Other Miscellaneous Work NA |
Registered agents
1 agent
Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.
| Sr. | Agent | RERA registration |
|---|---|---|
| 1 | SQUARE YARDS CONSULTING PRIVATE LIMITED | UPRERAAGT10119 |
Permits & extensions
2 permits
An approval and the date it runs to - not proof the work matching it was done.
2 sanctioning permits are on record with UPRERA, the latest valid to 19 Jul 2021.
Sanctioned by Lucknow Development Authority · 8,439 sqm of land · an approved plan of 1 block and 78 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan
| Permit no. | Date | Valid upto | Extendable upto | Revised end | Documents filed |
|---|---|---|---|---|---|
| 41052 | 20 Jul 2016 | 19 Jul 2021 | 19 Jul 2024 | 19 Jul 2021 | |
| 41052 | 20 Jul 2016 | 19 Jul 2021 | 19 Jul 2024 | 18 Jan 2022 |
UPRERA’s record carries 2 completion extensions for this project, the latest running to 17 Jan 2023.
| # | Granted from | Extended upto | Note |
|---|---|---|---|
| 1 | 19 Jul 2021 | 18 Jan 2022 | Six months extension in view of force majeure caused by covid-19 pandemic |
| 2 | 18 Jan 2022 | 17 Jan 2023 | — |
Land & documents
2 filings
How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.
| KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossary | Area | Type |
|---|---|---|
| 147, 149 | 2861.18 SQMTR | — |
| 147 & 149 | 2861.18 | Khasra |
1 registry or lease-deed filing is on this project’s record with UPRERA, dated 14 Dec 2015.
| Registry no. | Date | Type | Area |
|---|---|---|---|
| 19310 | 14 Dec 2015 | self | — |
| Registry document · 19310 The deed as registered with the sub-registrar, which is what proves the transfer took place. | PDF ↗ |
Facilities
as declared to RERA
Mostly reference numbers for filings made elsewhere, such as a fire NOC. Not live certifications, and verified by neither RERA nor Estanzo.
| Drinking water | YES IN DESIGN |
| Fire safety (as filed with RERA) | YES IN DESIGN |
| Renewable energy | YES IN DESIGN |
| Other facilities | YES |
The fire-safety value above is the filing reference UPRERA published for this project, not a live safety certification.
Quarterly progress reports
11 filed reports
The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.
11 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2022-Q3.
| Quarter | Construction | Certificates |
|---|---|---|
| 2020-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2020-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2020-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2020-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
Promoter (SPV) details
The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.
| Legal name | Balaji Enterprises |
| Role | Promoter · current |
| RERA ID | UPRERAPRM4003 |
| PAN | AAIFB6051C |
| CIN / TAN | NA |
| Registered address | 3/271 VISHWASH KHAND GOMTI NAGAR LUCKNOW |
| RERA contact | |
| Registered since | 2017 |
Nearby projects
Lucknow
Straight-line distance between filed coordinates. Not a comparison and not a travel time.
Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.
RERA bank accounts
verify before payment
Not confirmation that money is in these accounts, and details change - verify at the source before paying.
Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:
One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.
| Account | As filed with RERA |
|---|---|
| Bank account as filed | BALAJI ENTERPRISESBankSTATE BANK OF INDIABranchPERSONAL BANKING BRANCHA/C no.IFSCSBIN0004216 |
What has changed on this record
nothing recorded yet
When Estanzo first saw a difference - not proof RERA’s record changed that day.
Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.Common questions about LANDMARK
Is LANDMARK RERA registered?
Yes. LANDMARK is registered with UPRERA under registration number UPRERAPRJ5016, registered on 2 Aug 2017. Estanzo reproduces that filing; it does not verify the work behind it.
Has LANDMARK been completed?
UPRERA still lists LANDMARK as Registered, so it is not shown as completed here. A completion certificate dated 6 Jan 2024 is on the record - RERA accepts these tower-wise, so one on file does not mean the whole project is complete.
Who is the builder of LANDMARK?
Balaji Enterprises is the promoter entity that filed LANDMARK with UPRERA (promoter RERA ID UPRERAPRM4003). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.
Has UPRERA granted LANDMARK more time to complete?
UPRERA's record carries 2 completion extensions for LANDMARK, the latest running to 17 Jan 2023. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.
Does LANDMARK have a RERA bank account?
Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.
Where is LANDMARK located?
LANDMARK is registered in Lucknow, as filed with UPRERA.
What configurations are available in LANDMARK?
The unit plan filed with UPRERA lists 4 BHK, 2 BHK and 3 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.
What is the carpet area of flats in LANDMARK?
The approved unit plan filed with UPRERA runs from 71 to 235 m² of carpet area (about 760 to 2,530 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.
How many towers and units are planned in LANDMARK?
The approved unit plan describes 1 block and 78 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.
How dense is LANDMARK?
About 37 units per acre: 78 planned units across 2.09 acres (8,439 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.
Data as reported by UPRERA, as of 21 Oct 2026. official source ↗