Timeline Bar

Registered26 May 2022
Today3 Aug 2026
Promised27 Mar 2027

Timeline

Promised completion27 Mar 2027
Revised completion27 Mar 2027
Actual completion
Possession delayOn time

Registration & Cost Details

Registration fee (in ₹)₹59,000
Project cost (in ₹ Lakhs)₹5,149 Lakhs
Project duration60 months
Project categoryResidential
Locality
Original start date
Proposed start date28 Mar 2022

Inventory

Total units

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9310293775
Emailinfo@ascentlimited.com
Coordinator9310293775
Helpline9310293775
Address39 G, POCKET A-1, MAYUR VIHAR, PHASE -III, DELHI-110092

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2021-Q4
2022-Q197.0%
2022-Q297.0%
2022-Q397.0%
2022-Q497.0%
2023-Q197.0%
2023-Q297.0%
2023-Q397.0%
2023-Q497.0%
2024-Q197.0%
2024-Q297.0%
2024-Q397.0%
2024-Q497.0%
2025-Q197.0%
2025-Q297.0%
2025-Q397.0%
2025-Q498.0%

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
Plotting Resi development/Plotted Housing/01324/GDA/LD/20-21/0675/1505202128 Mar 202227 Mar 202727 Mar 202727 Sept 2027

Land Parcels

Khasra No.AreaPlot Type
12269720Khasra
12271888Khasra

Frequently Asked Questions

What is the RERA registration number of LAXMI VILLAS?

The RERA registration number of LAXMI VILLAS is UPRERAPRJ230024, as recorded on the UP-RERA portal.

What is the RERA status of LAXMI VILLAS?

As reported by UP-RERA, the status of LAXMI VILLAS is "Registered".

Where is LAXMI VILLAS located?

As reported to UP-RERA, LAXMI VILLAS is located at 125, Ghaziabad, Uttar Pradesh.

When will LAXMI VILLAS be completed?

The latest completion date reported to UP-RERA for LAXMI VILLAS is 27 Mar 2027.

Is LAXMI VILLAS delayed?

Measured against the latest completion date reported to UP-RERA, LAXMI VILLAS is on time.