Registered31 Jul 2017
Promised31 Dec 2018
Completed20 Apr 2019

Timeline

Promised completion31 Dec 2018
Revised completion31 Dec 2018
Actual completion20 Apr 2019
Possession delay4 mo delay

Registration & Cost Details

Registration fee (in ₹)₹25,500
Project cost (in ₹ Lakhs)₹1,756 Lakhs
Project duration54 months
Project categoryResidential
Locality
Original start date5 Nov 2012
Proposed start date30 Jul 2014

Inventory

Total units63
Unit TypeUnitsCarpet Area (sqm)
SHOP634.43–54.33

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9582006011
Emailarl@ajnara.com
Coordinator9582006011
AddressRegd. office - 502, Sacdeva Corporate Tower, Plot No.17, Karkardooma Community Centre, Delhi -92

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q2
2021-Q3

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
PLG/BP-2643/GH/FTS-618730 Jul 201430 Jul 201931 Dec 201830 Jul 2024

Land Parcels

Khasra No.AreaPlot Type
GH-02, SEC - 16, GREATER NOIDA72962Plot

Approved Unit Plan

Unit plan rows on file9
Total flats (sum of rows)63
Total shops63
BlocksLE MART CONVINIENT SHOP
Floor typesSHOP

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
880819 May 2011

Frequently Asked Questions

What is the RERA registration number of Le Garden (Phase-4, LE MART Convinient Shops)?

The RERA registration number of Le Garden (Phase-4, LE MART Convinient Shops) is UPRERAPRJ4600, as recorded on the UP-RERA portal.

What is the RERA status of Le Garden (Phase-4, LE MART Convinient Shops)?

As reported by UP-RERA, the status of Le Garden (Phase-4, LE MART Convinient Shops) is "NCLT".

Where is Le Garden (Phase-4, LE MART Convinient Shops) located?

As reported to UP-RERA, Le Garden (Phase-4, LE MART Convinient Shops) is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

Is Le Garden (Phase-4, LE MART Convinient Shops) completed?

As reported to UP-RERA, Le Garden (Phase-4, LE MART Convinient Shops) was completed on 20 Apr 2019.

Is Le Garden (Phase-4, LE MART Convinient Shops) delayed?

Measured against the latest completion date reported to UP-RERA, Le Garden (Phase-4, LE MART Convinient Shops) is 4 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.