Estanzo

Timeline Bar

Registered28 Jul 2017
Promised31 Dec 2020
Today29 Jul 2026

Timeline

Promised completion31 Dec 2020
Revised completion31 Dec 2020
Actual completion
Possession delay67 mo delay

Registration & Cost Details

Registration fee (in ₹)₹94,500
Project cost (in ₹ Lakhs)₹20,900 Lakhs
Project duration131 months
Project categoryResidential
Locality
Original start date5 Nov 2012
Proposed start date30 Jul 2014

Inventory

Total units585
Unit TypeUnitsCarpet Area (sqm)
3 BHK53541.41–90.04
4 BHK50109.34

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9582006011
Emailarl@ajnara.com
Coordinator9582006011
Helpline7835883228
AddressRegd. office - 502, Sacdeva Corporate Tower, Plot No.17, Karkardooma Community Centre, Delhi -92

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q2
2021-Q3
2021-Q4
2022-Q1
2022-Q2
2022-Q3
2022-Q4
2023-Q1
2023-Q2
2023-Q3
2023-Q4
2024-Q1

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
PLG/BP-2643/GH/FTS-618730 Jul 201430 Jul 201931 Dec 202030 Jul 2024

Land Parcels

Khasra No.AreaPlot Type
GH-02, SEC - 16, GREATER NOIDA72962Plot

Approved Unit Plan

Unit plan rows on file294
Total flats (sum of rows)585
BlocksTOWER K, TOWER L, TOWER M, TOWER N
Floor types3 BHK, 4 BHK

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
880819 May 2011

Frequently Asked Questions

What is the RERA registration number of Le Garden (Phase-3, Tower K L M & N)?

The RERA registration number of Le Garden (Phase-3, Tower K L M & N) is UPRERAPRJ3852, as recorded on the UP-RERA portal.

What is the RERA status of Le Garden (Phase-3, Tower K L M & N)?

As reported by UP-RERA, the status of Le Garden (Phase-3, Tower K L M & N) is "Registered".

Where is Le Garden (Phase-3, Tower K L M & N) located?

As reported to UP-RERA, Le Garden (Phase-3, Tower K L M & N) is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

When will Le Garden (Phase-3, Tower K L M & N) be completed?

The latest completion date reported to UP-RERA for Le Garden (Phase-3, Tower K L M & N) is 31 Dec 2020.

Is Le Garden (Phase-3, Tower K L M & N) delayed?

Measured against the latest completion date reported to UP-RERA, Le Garden (Phase-3, Tower K L M & N) is 67 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 28 Jul 2026