Registered9 Oct 2025
Today4 Aug 2026
Promised11 Sept 2030

Timeline

Promised completion11 Sept 2030
Revised completion11 Sept 2030
Actual completion
Possession delayOn time

Registration & Cost Details

Registration fee (in ₹)₹24,72,500
Project cost (in ₹ Lakhs)₹26,993 Lakhs
Project duration60 months
Project categoryResidential
LocalityRund Karari Jhansi
Original start date
Proposed start date1 Oct 2025

Inventory

Total units

Promoters & Contact

Contact Details

Applicant TypeCompetent authority
Mobile9506034343
Emailjda_jhansi@rediffmail.com
Coordinator9473816758
HelplineNA
AddressJhansi Vikas Pradhikaran, Behind Zila Vikas Karyalana, Jhansi

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2025-Q30.0%
2025-Q40.0%
2026-Q10.0%

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
1089/JDA/2025-2611 Sept 202511 Sept 203011 Sept 203011 Sept 2033

Land Parcels

Khasra No.AreaPlot Type
31,51,52,55,56,58,59,60,61,62,63,64,65,66,67,68,69,70,71,72,73,74,75,77,,78,80,81,83,85,86,87,89,90,91,92,93,94,95,96,97,98,386,387,388,389,390,391,392,393,394,395,396,397,398,399,400,401,402,403,404,405,406,407,408,409,410,411,415,416,418,419,420,421,423,424,426,427,428,429450172.40Khasra

Frequently Asked Questions

What is the RERA registration number of Manniya Mukhyamantri Shehari Vistarikaran Yojana (New Jhansi) Phase-1?

The RERA registration number of Manniya Mukhyamantri Shehari Vistarikaran Yojana (New Jhansi) Phase-1 is UPRERAPRJ801541, as recorded on the UP-RERA portal.

What is the RERA status of Manniya Mukhyamantri Shehari Vistarikaran Yojana (New Jhansi) Phase-1?

As reported by UP-RERA, the status of Manniya Mukhyamantri Shehari Vistarikaran Yojana (New Jhansi) Phase-1 is "Registered".

Where is Manniya Mukhyamantri Shehari Vistarikaran Yojana (New Jhansi) Phase-1 located?

As reported to UP-RERA, Manniya Mukhyamantri Shehari Vistarikaran Yojana (New Jhansi) Phase-1 is located at Rund Karari Jhansi, Rund Karari Jhansi, Jhansi, Jhansi, Uttar Pradesh.

When will Manniya Mukhyamantri Shehari Vistarikaran Yojana (New Jhansi) Phase-1 be completed?

The latest completion date reported to UP-RERA for Manniya Mukhyamantri Shehari Vistarikaran Yojana (New Jhansi) Phase-1 is 11 Sept 2030.

Is Manniya Mukhyamantri Shehari Vistarikaran Yojana (New Jhansi) Phase-1 delayed?

Measured against the latest completion date reported to UP-RERA, Manniya Mukhyamantri Shehari Vistarikaran Yojana (New Jhansi) Phase-1 is on time.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026