Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ7200
Project categoryResidential
Registration typeOngoing
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryBareily Development Authority
Proposed start16 Apr 2016
Original start16 Apr 2016
Project duration66 months
AddressBareilly, Bareilly
TehsilBareilly
Applicant typeCompany
Applicant addressC-2, MEGA CITY, SANJAY NAGAR BYPASS, BAREILLY
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    192/02/LO/15

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. to

    Extension granted

    “Six months extension in view of force majeure caused by covid-19 pandemic”

  5. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  6. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

  7. 2 completion certificates filed

  8. Completion certificate filed

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2020-21
Q1Q2Q3Q4
FY 2021-22
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered31 Jul 2017
Original completion15 Apr 2021
Revised completion14 Oct 2021
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary19 Jan 2022
Registration fee₹59,000
Sanctioning authorityBareily Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors— · 1 · 9 (from plan)
ConfigurationUnitsCarpet area
1 BHK—337
2 BHK—1,514
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
TOWER · 1 BHK, 2 BHK9—337-1,514
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.No unit total is shown: the plan's flat-count column contradicts this project's other filings.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
ANUJ MEHTA
License CA-88/11912
MEHTA AND ASSOCIATES, C-74 ANAND VIHAR, NEW DELHI
Engineer
KAMAL SABBARWAL
CECON ENGINEERS, MAYUR VIHAR, NEW DELHI
Contractor
N/A
N/A
Sr.Development work declared to RERA
1Demarcation of Plots
BRICK WORK
2Boundary Wall
BRICK AND RCC COLUMNS , FINISHED WITH PLASTER AND FANSING WIRE
3Road Work
BITUMEN ROAD
4Footpaths
GRASS PAVERS
5Water Supply Including Drinking Water Facilities
UNDERGROUND WATER TANK WITH PRESSURIZED LINES
6Sewer System
UNDERGROUND SEVER LINES
7Drain
UNDERGROUND DRAINS
8Parks
GRASS, TREES KIDS PLAY AREA
9Tree Planting
GULMOHAR, CHAMPA, MANGO
10Design For Electric Supply Including Street Lighting
OPEN TRENCH
11Community Buildings
N.A.
12Treatment and Disposal System of Sewage and Sullage water
N.A.
13Solid Waste Management And Disposal System
N.A.
14Water Conservation System
RAINWATER HARVESTING
15Energy Management System Including Use of Renewable Energy
SOLAR PANELS FOR STREET LIGHTS
16Fire Protection And Fire Safety System
WATER TANK ON THE TOP OF THE TOWER
17Social Infrastructure And Other Public Amenities Including Public Health Services
N.A.
18Emergency Evacuation Services
N.A.
19Other Miscellaneous Work
N.A.
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 15 Apr 2021.

Sanctioned by Bareily Development Authority · 10,724 sqm of land. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
192/02/LO/1516 Apr 201615 Apr 202116 Apr 202314 Oct 2021
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗
Project approval
The approval the promoter filed as the basis for registering the project.
PDF ↗
Project approval
The approval the promoter filed as the basis for registering the project.
PDF ↗
Sanctioned layout plan
The approved layout of the whole site: where the towers, roads and open areas sit on the plot.
PDF ↗
Floor plans of all unit types
The approved plan of each unit type, which is what a carpet-area figure is measured from.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 1 completion extension for this project, running to 14 Oct 2021.

#Granted fromExtended uptoNote
115 Apr 202114 Oct 2021Six months extension in view of force majeure caused by covid-19 pandemic

Land & documents

27 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
140,141,142,143,144,145,146,147,148,149,15065485.44—
140,141,142,143,144,145,146,147,149,15065485.44Khasra
Registry & lease deedsRegistry / lease deedThe deed by which the land changed hands, recorded with the sub-registrar and stamped.Read the full entry in the glossary

2 registry or lease-deed filings are on this project’s record with UPRERA, the earliest dated 8 Aug 2012.

Registry no.DateTypeArea
97108 Aug 2012self—
1518319 Dec 2012self—
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Registry document · 15183
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 15183
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 9710
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Document checklist
DocumentStatusUploaded
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New5 Jul 2018 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New5 Jul 2018 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New5 Jul 2018 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New5 Jul 2018 ↗
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
New5 Jul 2018 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New5 Jul 2018 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New5 Jul 2018 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New5 Jul 2018 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New5 Jul 2018 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New5 Jul 2018 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New6 Jul 2018 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New6 Jul 2018 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New6 Jul 2018 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
Old8 Mar 2018 ↗
Registry document (own land)
The registered deed for land the promoter holds itself, rather than under an agreement with a landowner.
Old8 Mar 2018 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
Old8 Mar 2018 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
Old8 Mar 2018 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
Old8 Mar 2018 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
Old8 Mar 2018 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
Old9 Mar 2018 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
Old9 Mar 2018 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
Old9 Mar 2018 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
Old9 Mar 2018 ↗
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
Old9 Mar 2018 ↗
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
Old9 Mar 2018 ↗

Facilities

as declared to RERA

Mostly reference numbers for filings made elsewhere, such as a fire NOC. Not live certifications, and verified by neither RERA nor Estanzo.

Drinking waterAS PER AUTHORITY NORMS
Fire safety (as filed with RERA)AS PER AUTHORITY NORMS
Renewable energyAS PER AUTHORITY NORMS
Other facilitiesNO

The fire-safety value above is the filing reference UPRERA published for this project, not a live safety certification.

Quarterly progress reports

7 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

7 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2021-Q3.

QuarterConstructionCertificates
2020-Q1—CA ↗ · Arch ↗ · Eng ↗
2020-Q2—CA ↗ · Arch ↗ · Eng ↗
2020-Q3—CA ↗ · Arch ↗ · Eng ↗
2020-Q4—CA ↗ · Arch ↗ · Eng ↗
2021-Q1—CA ↗ · Arch ↗ · Eng ↗
2021-Q2—CA ↗ · Arch ↗ · Eng ↗
2021-Q3—CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameMEGA INFRACITY PRIVATE LIMITED
RolePromoter · current
RERA IDUPRERAPRM13808
PANAAHCM9846J
CIN / TANU45400UP2012PTC050824
Name of chairmanPIYUSH KUMAR AGARWAL
Registered addressC-2, MEGA CITY, SANJAY NAGAR BYPASS, BAREILLY
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Bareilly

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.

AccountAs filed with RERA
Bank account as filed
MEGA INFRACITY PRIVATE LIMITEDBankSTATE BANK OF INDIABranchSPECIALISED COMMERCIAL BRANCHA/C no.IFSCSBIN0017644
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

Common questions about MEGA DREAM HOMES (PHASE-3)

Is MEGA DREAM HOMES (PHASE-3) RERA registered?

Yes. MEGA DREAM HOMES (PHASE-3) is registered with UPRERA under registration number UPRERAPRJ7200, registered on 31 Jul 2017. Estanzo reproduces that filing; it does not verify the work behind it.

Has MEGA DREAM HOMES (PHASE-3) been completed?

UPRERA still lists MEGA DREAM HOMES (PHASE-3) as Registered, so it is not shown as completed here. A completion certificate dated 19 Jan 2022 is on the record - RERA accepts these tower-wise, so one on file does not mean the whole project is complete.

Who is the builder of MEGA DREAM HOMES (PHASE-3)?

MEGA INFRACITY PRIVATE LIMITED is the promoter entity that filed MEGA DREAM HOMES (PHASE-3) with UPRERA (promoter RERA ID UPRERAPRM13808). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Has UPRERA granted MEGA DREAM HOMES (PHASE-3) more time to complete?

UPRERA's record carries 1 completion extension for MEGA DREAM HOMES (PHASE-3), the latest running to 14 Oct 2021. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does MEGA DREAM HOMES (PHASE-3) have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is MEGA DREAM HOMES (PHASE-3) located?

MEGA DREAM HOMES (PHASE-3) is registered in Bareilly, as filed with UPRERA.

What configurations are available in MEGA DREAM HOMES (PHASE-3)?

The unit plan filed with UPRERA lists 1 BHK and 2 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in MEGA DREAM HOMES (PHASE-3)?

The approved unit plan filed with UPRERA runs from 337 to 1,514 m² of carpet area (about 3,627 to 16,295 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗