Mega Green City

UPRERARegistered

Mega Green City is a RERA-registered residential project by Mega Infradreams Consortium in Kuantanda and Purnapur, Bareilly (RERA ID UPRERAPRJ988483). Registered with a completion deadline of 3 Aug 2027.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
0%Q3'25
0%Q4'25
3.73%Q1'26
6.59%Q2'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ988483
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryBareily Development Authority
Proposed start1 Jul 2025
Project duration26 months
AddressKhasra no. 19, 20, 26, 27, 29, 30, 33, 316, 322, 324, 325, Kuantanda and Purnapur, Bareilly, Bareilly
TehsilBareilly
Applicant typeAssociation Of Persons (AOP)
Applicant addressC-2, Mega City, Sanjay Nagar, Bareilly. 243001
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    02/PMAY/9277Ma./Ka.b.d.a./2019

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered20 Dec 2025
Original completion3 Aug 2027
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹3,80,000
Sanctioning authorityBareily Development Authority

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Sonali Khandelwal
License CA/2010/47760
288, Mega Dream Homes, Karamchari Nagar, Bareilly
Engineer
P K Gupta
BF-102, Janakpuri, New Delhi-110058
Contractor
Arif Khan
123 Chameli Ki Bagiya Lichi Bagh Quila Bareilly
Sr.Development work declared to RERA
1Demarcation of Plots
As per layout plan.
2Boundary Wall
R.C.C. Framed, Brick wall 2.0 mt height work in column and beam.
3Road Work
One layer of 100 mm thick GSB + 2 layers of 100 mm thick + 75 mm thick BM + 25 mm thick BC with topcoat & seal-coat.
4Footpaths
60 mm thick R.C.C blocks
5Water Supply Including Drinking Water Facilities
Supply from under ground water tank
6Sewer System
Underground Sewerage system shall be Provided. All Sewerage water shall be go to the STP for treatment & disposal. STP of 300 KLD for sewage treatment.
7Drain
Underground water system shall be provided. Storm water from roads and other landscape area shall be connected to the storm water drain and go the Rain water harvesting pits.
8Parks
Green grass with plants & walkways, benches etc.
9Tree Planting
Various type of trees all around the park boundary wall & green area.
10Design For Electric Supply Including Street Lighting
Designing & implement the system as per local electricity Board norms.
11Community Buildings
Not Applicable
12Treatment and Disposal System of Sewage and Sullage water
Underground Sewerage system shall be Provided. All Sewerage water shall be go to the STP for treatment & disposal. STP of 300 KLD for sewage treatment.
13Solid Waste Management And Disposal System
Garbage/Dustbin area located in different places for the solid waste collection & disposal.
14Water Conservation System
Rain water Harvesting as mentioned in point of Drain.
15Energy Management System Including Use of Renewable Energy
35% Solar street lights fitting in external area and LED lights.
16Fire Protection And Fire Safety System
Not Applicable
17Social Infrastructure And Other Public Amenities Including Public Health Services
As per approved layout
18Emergency Evacuation Services
Not Applicable
19Other Miscellaneous Work
Not Applicable
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 3 Aug 2027.

Sanctioned by Bareily Development Authority · 75,000 sqm of land. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total.

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
02/PMAY/9277Ma./Ka.b.d.a./201917 Jun 20253 Aug 20273 Feb 20283 Aug 2027
Plans and approvals filed with RERA
DocumentFile
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
no file published
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗

Land & documents

21 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
33,30,29,19,20,26,27,316,325,324,32276588Plot
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Sale deed · 6474
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 9016
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 2574
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 6785
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 6254
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 6860
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 7461
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 8646
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 9794
The registered deed by which the promoter bought the land.
PDF ↗
Khatauni extract · 1424-1429
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1425-1430
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · Consortium Agreement Govt Policy
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Registry document · 383
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Khatauni extract · Net Worth Requirement
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · Updated_Affidavit_ChakRoad
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Sale deed · 18011
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 18012
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 18013
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 18014
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 18015
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 18016
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 18017
The registered deed by which the promoter bought the land.
PDF ↗
Khatauni extract · Application for Mutation
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Document checklist
DocumentStatusUploaded
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
not reported—
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
not reported—
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
not reported—
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
not reported—
Agreement for sale (proforma)
The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New25 Aug 2025 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New25 Aug 2025 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New25 Aug 2025 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New25 Aug 2025 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New21 Aug 2025 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New21 Aug 2025 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New21 Aug 2025 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New25 Aug 2025 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New21 Aug 2025 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New8 Sept 2025 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New23 Sept 2025 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New23 Sept 2025 ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
New25 Aug 2025 ↗
Agreement for sale (proforma)
The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind.
New25 Aug 2025 ↗

Quarterly progress reports

4 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

4 quarterly progress reports are on file with UPRERA, covering 2025-Q2 to 2026-Q1.

QuarterConstructionCertificates
2025-Q20%CA ↗ · Arch ↗ · Eng ↗
2025-Q30%CA ↗ · Arch ↗ · Eng ↗
2025-Q43.73%CA ↗ · Arch ↗ · Eng ↗
2026-Q16.59%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameMega Infradreams Consortium
RolePromoter · current
RERA IDUPRERAPRM85548
PANAAIAM3362J
CIN / TANLKNM09969B
Registered addressC-2, Mega City, Sanjay Nagar, Bareilly. 243001
RERA contact
Registered since2019
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.
Legal nameMEGA INFRACITY PRIVATE LIMITED
RoleCo-promoter · current
RERA IDUPRERAPRM13808
Applicant typeCompany
PANAAHCM9846J
CIN / TANU45400UP2012PTC050824
Name of chairmanPIYUSH KUMAR AGARWAL
Registered addressC-2, MEGA CITY, SANJAY NAGAR BYPASS, BAREILLY
RERA contact
Registered since2017
Legal nameQWALITY ASSOCIATES
RoleCo-promoter · current
RERA IDUPRERAPRM49339
Applicant typePartnership Firm
PANAAAFQ2607H
CIN / TANLKNQ05021C
Registered addressC-1 MEGA CITY, SANJAY NAGAR BYE PASS ROAD, BAREILLY
RERA contact
Registered since2018
Legal nameABPS REALTECH LLP
RoleCo-promoter
Applicant typeLimited Liability Partnership (LLP)
AddressC-2, Mega City, 1st Floor, Sanjay Nagar, Bye Pass Road, Bareilly, U.P.-243001
RERA contact
Legal nameMEGA ECO PROJECTS LLP
RoleCo-promoter
Applicant typeLimited Liability Partnership (LLP)
AddressC-2, Mega City, 1st Floor, Sanjay Nagar, Bye Pass Road, Bareilly, U.P.-243001
RERA contact
Legal nameQWALITYDREAM TOWNSHIPS LLP
RoleCo-promoter
Applicant typeLimited Liability Partnership (LLP)
AddressC-2, Mega City, 1st Floor, Sanjay Nagar, Bye Pass Road, Bareilly, U.P.-243001
RERA contact
Legal nameMEGA INFRADREAMS LLP
RoleCo-promoter
Applicant typeLimited Liability Partnership (LLP)
AddressC-2, 1st Floor, Mega City, Sanjay Nagar, Bye Pass Road, Bareilly, U.P.-243001
RERA contact
Legal nameABPS BUILDTECH LLP
RoleCo-promoter
Applicant typeLimited Liability Partnership (LLP)
AddressC-2, 1st Floor, Mega City, Sanjay Nagar, Bye Pass Road, Bareilly, U.P.-243001
RERA contact
Legal nameNAND INFRADEVELOPERS PRIVATE LIMITED
RoleCo-promoter
Applicant typeCompany
Address35-D/12, Rampur Garden, Bareilly, 243001
RERA contact
Legal nameQWALITY BRICK WORKS
RoleCo-promoter
Applicant typeProprietorship Firm
AddressBalipur, Bisalpur Road, Ahmadpur, Bareilly, Uttar Pradesh, 243001
RERA contact

Nearby projects

Bareilly

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
Mega Infradreams Consortium RERA Coll AC Mega Green CityBankState bank of IndiaBranchSpecialised Commercial BranchBranch address148, Civil Lines, SBI Administrative office, BareillyBranch districtBareilly, Uttar PradeshA/C no.IFSCSBIN0017644Branch emailSbi.17644@sbi.co.in
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
Mega Infradreams Consortium RERA Sep AC Mega Green CityBankState bank of IndiaBranchSpecialised Commercial BranchBranch address148, Civil Lines, SBI Administrative office, BareillyBranch districtBareilly, Uttar PradeshA/C no.IFSCSBIN0017644
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
Mega Infradreams Consortium RERA Trxn AC Mega Green CityBankState bank of IndiaBranchSpecialised Commercial BranchBranch address148, Civil Lines, SBI Administrative office, BareillyBranch districtBareilly, Uttar PradeshA/C no.IFSCSBIN0017644
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

2 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No approved unit plan is published for this project.Ask for the carpet area of the specific unit in writing, and for the approved floor plan it is measured from.
  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about Mega Green City

Is Mega Green City RERA registered?

Yes. Mega Green City is registered with UPRERA under registration number UPRERAPRJ988483, registered on 20 Dec 2025. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for Mega Green City?

The completion date filed with UPRERA is 3 Aug 2027. No completion certificate is on record yet.

Who is the builder of Mega Green City?

Mega Infradreams Consortium is the promoter entity that filed Mega Green City with UPRERA (promoter RERA ID UPRERAPRM85548). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does Mega Green City have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is Mega Green City located?

Mega Green City is registered in Kuantanda and Purnapur, Bareilly, as filed with UPRERA.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗