Estanzo

Timeline Bar

Registered1 May 2024
Today29 Jul 2026
Promised10 Oct 2028

Timeline

Promised completion10 Oct 2028
Revised completion10 Oct 2028
Actual completion
Possession delayOn time

Registration & Cost Details

Registration fee (in ₹)₹2,50,000
Project cost (in ₹ Lakhs)₹17,303 Lakhs
Project duration60 months
Project categoryCommercial
LocalityTZ-06
Original start date
Proposed start date1 Nov 2023

Inventory

Total units425
Unit TypeUnitsCarpet Area (sqm)
OTHER42526.79–1207.94

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile8860003516
EmailLegal@migsun.in
Coordinator8860016650
Address201, Nirmal Towers Barakhamba Road NA Delhi New Delhi

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2023-Q3
2023-Q4
2024-Q1
2024-Q2
2024-Q3
2024-Q4
2025-Q1
2025-Q21.1%
2025-Q32.0%
2025-Q42.2%
2026-Q11.6%

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
PLG/BPSM-29-Dec-202218 Oct 202317 Oct 202810 Oct 202816 Oct 2030

Land Parcels

Khasra No.AreaPlot Type
TZ-06304053.46Plot
IT SEZ TZ-0623904.60Plot

Approved Unit Plan

Unit plan rows on file243
Total flats (sum of rows)425
BlocksT2
Floor typesOTHER

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of Migsun Nehru Place 3?

The RERA registration number of Migsun Nehru Place 3 is UPRERAPRJ585500, as recorded on the UP-RERA portal.

What is the RERA status of Migsun Nehru Place 3?

As reported by UP-RERA, the status of Migsun Nehru Place 3 is "Registered".

Where is Migsun Nehru Place 3 located?

As reported to UP-RERA, Migsun Nehru Place 3 is located at IT SEZ-1A, TZ-06, Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

When will Migsun Nehru Place 3 be completed?

The latest completion date reported to UP-RERA for Migsun Nehru Place 3 is 10 Oct 2028.

Is Migsun Nehru Place 3 delayed?

Measured against the latest completion date reported to UP-RERA, Migsun Nehru Place 3 is on time.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 28 Jul 2026