Numax City - 2

UPRERARegistered

Numax City - 2 is a RERA-registered residential project by NUMAX REALCON PRIVATE LIMITED in Jarauda, Muzaffarnagar (RERA ID UPRERAPRJ937192). Registered with a completion deadline of 23 Jun 2030.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
28.9%Q4'25
47.18%Q1'26
48.5%Q2'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ937192
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryMuzaffarnagar Development Authority
Proposed start1 Oct 2025
Project duration57 months
AddressKhasra No. 1379/17, 1379/18, 1383, 1384, 1385M, 1386, 1387, 1388, 1388M, 1389, 1390, 1391, 1392, 1393, 1396, 1406, 1407/1, 1407/2, 1408M, 1409, 1410M, 1420, 1420/2, 1421, 1422, 1424M, 1425/3, Village: Jarauda, Tehsil: Sadar, District: Muzzarnagr, U.P., Jarauda, Muzaffarnagar, Muzaffarnagar
TehsilMuzaffarnagar
Applicant typeCompany
Applicant addressFARM 37C RADHEY MOHAN DRIVE BANDH ROAD ASOLA, FATEHPUR BERI, South Delhi, New Delhi, Delhi, India, 110074
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    MZDA/LD/24-25/0541

  2. Registered with RERA

  3. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered8 Sept 2025
Original completion23 Jun 2030
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹4,58,000
Sanctioning authorityMuzaffarnagar Development Authority

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Vishal Mittal
License CA/1998/23185
B-34, Sector-67, Noida - 201301
Engineer
Mohd Zulquer Nain
SNC-1510, 14th Floor, Shipra Neo Indirapuram, Ghaziabad, UP - 201014
Contractor
Star Associate
262D, Sector - 24, Faridabad, Near Lakhani Rubber Works, Faridabad - 121005
Sr.Development work declared to RERA
1Demarcation of Plots
Layout of site according to both the survey and the approved layout plan using a total station. Plots will be very well demarcated at the site. Demarcation of plots is done through brick work in zig zag pattern
2Boundary Wall
In this Project there will be Precast boundary wall of 6 ft height is being cconstructed and there will be project logo in the center which give next level of viewing experinace to the clients
3Road Work
In this project roads finished with trimix / concrete pavers as per design and laid over compacted earth granular subbase (GSB) WBM PCC (1 4 8) and sand bed wide roads 7.5 Mtr to 30 Mtr
4Footpaths
In this Project there footpaths will be made of Interlocking Concrete Pavers
5Water Supply Including Drinking Water Facilities
The potable water supply of desired quality and purity shall be ensured by tapping underground water. The Primary treatment facility shall be ensured before making it supplied to the use of people
6Sewer System
In this Project an efficient designed sewerage system connected to STP and all sewer water shall go to the STP to be developed on this Project
7Drain
In this Project an efficient underground drainage system proposed. The surface runoff from the roads, open space and areas other than roof tops will be transported through the system to the nearest existing water body for harvesting and the overflow from the water bodies will disposed in the existing darin
8Parks
Greenery development in this township Project is proposed in the parks. These green space are provided with the sectors creating healthy and moderate environment for the residents of township. Rich planation kids area will be also there in this Project
9Tree Planting
Plants of local species trees will be there on boundary roads parks and on common areas 1 mtr to 4 mtr high plants and trees along the roads of evergreen nature
10Design For Electric Supply Including Street Lighting
The proposed township shall supply electric supply through 33 KV sub-station from where power shall be supplied at 11 KV level through various underground 11 KV feeders to the distribution transformers of 11 KV / 433 KV variation and then the LT underground distribution system Electric cabling we will used LED lights fitting in external areas
11Community Buildings
In this Project various community area and various activities will be proposed in this project
12Treatment and Disposal System of Sewage and Sullage water
Treatment and disposal system of sewage and sullage water will be treated in the STP proposed in the various zone in the township Under ground drainage system.
13Solid Waste Management And Disposal System
As all the waste will be segregated at source only after that all the organic waste generated in this township will be used after its treatment to make it zero-waste discharge township however all the e-waste and toxic water and recycleable waste will be handed over to the agency suggected by muzaffarnagar Developemt authority else we will hand over such waste to the hired government approved solid waste managment agency from the market
14Water Conservation System
Every household will get piped water supply through a designed system and no area will be allowed to install their own individual system of water supply
15Energy Management System Including Use of Renewable Energy
Solar lights in the Park and common area and EWS LIG area will be provided partially to save the energy
16Fire Protection And Fire Safety System
a reserve for fire fighting has proposed in the township
17Social Infrastructure And Other Public Amenities Including Public Health Services
In this New Township social infrastructre such as schools Community centers club Post office etc are provided to make this township convenient for living
18Emergency Evacuation Services
Sufficient open space provided in the township for the gathering of people in emergency
19Other Miscellaneous Work
NA
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 23 Jun 2030.

Sanctioned by Muzaffarnagar Development Authority · 90,587 sqm of land. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total.

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
MZDA/LD/24-25/054124 Jun 202523 Jun 203023 Jun 203023 Jun 2030
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗

Land & documents

17 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
1379/17, 1379/18, 1383, 1384, 1385M, 1386, 1387, 1388, 1388M, 1389, 1390, 1391, 1392, 1393, 1396, 1406, 1407/1, 1407/2, 1408M, 1409, 1410M, 1420, 1420/2, 1421, 1422, 1424M, 1425/390587.48Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Registry document · 3751
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 4001
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 4003
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 4005
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 4458
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 4491
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 9697
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 9699
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 9701
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 10753
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 10755
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 10763
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 10767
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 10769
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 10929
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 18500
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 19523
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Khatauni extract · 1425-1430
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1425-1430
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1425-1430
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1425-1430
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1425-1430
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1430-1435
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1425-1430
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1425-1430
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1425-1430
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1425-1430
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1425-1430
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Registry document · Consortium
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Document checklist
DocumentStatusUploaded
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New13 Aug 2025 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New13 Aug 2025 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New13 Aug 2025 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New13 Aug 2025 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New13 Aug 2025 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New13 Aug 2025 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New13 Aug 2025 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New13 Aug 2025 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New13 Aug 2025 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New13 Aug 2025 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New13 Aug 2025 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New13 Aug 2025 ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
New13 Aug 2025 ↗
Agreement for sale (proforma)
The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind.
New13 Aug 2025 ↗

Quarterly progress reports

3 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

3 quarterly progress reports are on file with UPRERA, covering 2025-Q3 to 2026-Q1.

QuarterConstructionCertificates
2025-Q328.9%CA ↗ · Arch ↗ · Eng ↗
2025-Q447.18%CA ↗ · Arch ↗ · Eng ↗
2026-Q148.5%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameNUMAX REALCON PRIVATE LIMITED
RolePromoter · current
RERA IDUPRERAPRM358427
PANAAFCN8821J
CIN / TANU70109DL2017PTC327504
Name of chairmanSunil Goel
Registered addressFARM 37C RADHEY MOHAN DRIVE BANDH ROAD ASOLA, FATEHPUR BERI, South Delhi, New Delhi, Delhi, India, 110074
RERA contact
Registered since2025
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.
Legal nameSPARKSTONE REALTY LLP
RoleCo-promoter
Applicant typeLimited Liability Partnership (LLP)
AddressF-37C, RADHEY MOHAN DRIVE ASOLA, FATEHPUR BERI SOUTH WEST DELHI SAWAN PUBLIC SCHOOL SOUTH WEST DELHI-110074
RERA contact
Legal nameMORNINGSTAR REALTY LLP
RoleCo-promoter
Applicant typeLimited Liability Partnership (LLP)
AddressF-37C, RADHEY MOHAN DRIVE, ,ASOLA, FATEHPUR BERI, Sawan Public School, F55VXM Asola Homes Asola New Delhi 110074,
RERA contact
Legal nameNUMAX INFRATECH LLP
RoleCo-promoter
Applicant typeLimited Liability Partnership (LLP)
AddressF-37C,RADHEY MOHAN DRIVE, ASOLA, FATEHPUR BERI, Sawan Public School, F582 638, POLICE STATION RD, JONA PUR, JUANAPUR, NEW DELHI, DELHI 110074
RERA contact
Legal nameOASISOPUS REALTY PRIVATE LIMITED
RoleCo-promoter
Applicant typeCompany
AddressF-37, RADHEY MOHAN DRIVE, FATEHPUR BERI, Sawan Public School, South West Delhi, South West Delhi- 110074, Delhi
RERA contact
Legal nameNUMAX BUILDTECH LLP
RoleCo-promoter
Applicant typeLimited Liability Partnership (LLP)
AddressF37C, RADHEY MOHAN DRIVE, ASOLA, FATEHPUR BERI, Sawan Public School, F582 638, POLICE STATION RD, JONA PUR, JUANAPUR, NEW DELHI, DELHI 110074
RERA contact
Legal nameNUMAX BUILD HOMES LLP
RoleCo-promoter
Applicant typeLimited Liability Partnership (LLP)
AddressF-37C,RADHEY MOHAN DRIVE, ASOLA, FATEHPUR BERI, Sawan Public School, F 582 683, POLICE STATION RD, JONA PUR, JUANAPUR, NEW DELHI, DELHI 110074
RERA contact
Legal nameNUMAX BLUEHOMES LLP
RoleCo-promoter
Applicant typeLimited Liability Partnership (LLP)
AddressF-37C,RADHEY MOHAN DRIVE, ASOLA, FATEHPUR BERI, Sawan Public School, F582 638, POLICE STATION RD, JONA PUR, JUANAPUR, NEW DELHI, DELHI 110074
RERA contact
Legal nameAABHAARA REAL VENTURES LLP
RoleCo-promoter
Applicant typeLimited Liability Partnership (LLP)
AddressF-37C, RADHEY MOHAN DRIV, ASOLA, FATEHPUR BERI, Sawan Public School, F55VXM ASOLA HOMES NEW DELHI 110074
RERA contact
Legal nameRPS INFRASTRUCTURE LIMITED
RoleCo-promoter
Applicant typeCompany
Address1117-1120, 11TH FLOOR, TOWER-B, DLF TOWERS, JASOLA DISTRICT CENTER, NEW DELHI-110025
RERA contact
Legal nameNUMAX PINK HOMES LLP
RoleCo-promoter
Applicant typeLimited Liability Partnership (LLP)
AddressF-37C RADHEY MOHAN DRIVE, ASOLA, FATEHPUR BERI, Sawan Public School, F55VXM Asola Homes Asola New Delhi 110074
RERA contact
Legal nameGENGILLION LLP
RoleCo-promoter
Applicant typeLimited Liability Partnership (LLP)
AddressF-37C, RADHEY MOHAN DRIVE, ASOLA, FATEHPUR BERI, Sawan Public School, F55VXM ASOLA HOMES NEW DELHI 110074
RERA contact
Legal nameVASTUSHILPI REALTY PRIVATE LIMITED
RoleCo-promoter
Applicant typeCompany
AddressF-37C, RADHEY MOHAN DRIVE, FATEHPUR BERI, Sawan Public School, South West Delhi, South West Delhi- 110074, Delhi
RERA contact
Legal nameNUMAX EAGLE PRO LLP
RoleCo-promoter
Applicant typeLimited Liability Partnership (LLP)
AddressF-37C,RADHEY MOHAN DRIVE, ASOLA, FATEHPUR BERI, Sawan Public School, F582 638, POLICE STATION RD, JONA PUR, JUANAPUR, NEW DELHI, DELHI 110074
RERA contact

Nearby projects

Muzaffarnagar

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
Numax Realcon Private Limited Collection A/C Numax City - 2BankPunjab National BankBranchPNB Industrial Area MuzaffarnagarBranch addressPNB Industrial Area, Muzaffarnagar, Meerut Road, Opposite ShahTimes, Muzzafarnagar, U.P. 251003Branch districtMuzaffarnagar, Uttar PradeshA/C no.IFSCPUNB0251400Branch emailbo2514@pnb.co.in
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
Numax Realcon Private Limited Separate A/C Numax City 2BankPunjab National BankBranchPNB Industrial Area MuzaffarnagarBranch addressPNB Industrial Area, Muzaffarnagar, Meerut Road, Opposite Shah Times, Muzaffarnagar, U.P. 251003Branch districtMuzaffarnagar, Uttar PradeshA/C no.IFSCPUNB0251400
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
Numax Realcon Private Limited Transaction A/C Numax City 2BankPunjab National BankBranchPNB Industrial Area MuzaffarnagarBranch addressPNB Industrial Area, Muzaffarnagar, Meerut Road, Opposite Shah Times, Muzaffarnagar, UP 251003Branch districtMuzaffarnagar, Uttar PradeshA/C no.IFSCPUNB0251400
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

2 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No approved unit plan is published for this project.Ask for the carpet area of the specific unit in writing, and for the approved floor plan it is measured from.
  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about Numax City - 2

Is Numax City - 2 RERA registered?

Yes. Numax City - 2 is registered with UPRERA under registration number UPRERAPRJ937192, registered on 8 Sept 2025. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for Numax City - 2?

The completion date filed with UPRERA is 23 Jun 2030. No completion certificate is on record yet.

Who is the builder of Numax City - 2?

NUMAX REALCON PRIVATE LIMITED is the promoter entity that filed Numax City - 2 with UPRERA (promoter RERA ID UPRERAPRM358427). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does Numax City - 2 have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is Numax City - 2 located?

Numax City - 2 is registered in Jarauda, Muzaffarnagar, as filed with UPRERA.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗