Timeline Bar

Registered25 Apr 2023
Completed15 Oct 2025
Promised30 Mar 2027

Timeline

Promised completion30 Mar 2027
Revised completion30 Mar 2027
Actual completion15 Oct 2025
Possession delayOn time

Registration & Cost Details

Registration fee (in ₹)₹15,500
Project cost (in ₹ Lakhs)₹906 Lakhs
Project duration48 months
Project categoryResidential
Locality
Original start date
Proposed start date1 Apr 2023

Inventory

Total units49
Unit TypeUnitsCarpet Area (sqm)
2 BHK1675.53
3 BHK3386.11–87.97

Promoters & Contact

Contact Details

Applicant TypePartnership Firm
Mobile9389056474
Emailsandeep@sankit.in
Coordinator9389056474
AddressKHASRA NO 357, TAPA KHURD, JALESAR ROAD FIROZABAD-283203, UTTAR PRADESH

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2023-Q1
2023-Q2
2023-Q3
2023-Q4
2024-Q1
2024-Q2
2024-Q3
2024-Q4
2025-Q1
2025-Q2100.0%
2025-Q3100.0%

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
Group Housing/00816/FSDA/BP/22-23/0167/28092022 ( Old Permit No. Group Housing/00632/BP/21022/0300/1503202223 Dec 202230 Mar 202730 Mar 202730 Mar 2027

Land Parcels

Khasra No.AreaPlot Type
Plot No. 01 on Khasra No. 357, Mauja Tapa Khurd, Firozabad2024.95Plot
Plot No. 01 on Khasra No. 357, Mauja Tapa Khurd, Firozabad2024.95Plot

Approved Unit Plan

Unit plan rows on file27
Total flats (sum of rows)49
BlocksOM HEIGHTS -01
Floor types2 BHK, 3 BHK, OTHER

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of Om Heights 01?

The RERA registration number of Om Heights 01 is UPRERAPRJ466704, as recorded on the UP-RERA portal.

What is the RERA status of Om Heights 01?

As reported by UP-RERA, the status of Om Heights 01 is "Registered".

Where is Om Heights 01 located?

As reported to UP-RERA, Om Heights 01 is located at Firozabad, Firozabad, Uttar Pradesh.

Is Om Heights 01 completed?

As reported to UP-RERA, Om Heights 01 was completed on 15 Oct 2025.

Is Om Heights 01 delayed?

Measured against the latest completion date reported to UP-RERA, Om Heights 01 is on time.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 4 Aug 2026