Omaxshiva-2

UPRERARegistered

Omaxshiva-2 is a RERA-registered residential project by Omaxe Pancham Realcon Pvt. Ltd. (fomerly Pancham Realcon Pvt. Ltd.) in Prayagraj (RERA ID UPRERAPRJ998764). Registered with a completion deadline of 29 Dec 2026.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q3'24
—Q4'24
—Q1'25
—Q2'25
79.07%Q3'25
79.07%Q4'25
79.07%Q1'26
100%Q2'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ998764
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryAllahabad Development Authority
Proposed start1 Jul 2019
Project duration90 months
AddressKarchhana, Prayagraj
TehsilKarchhana
Applicant typeCompany
Applicant address10, Local Shopping Center, Kalkaji, New Delhi - 110019
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    185/PR0A0(T0S0)ZONE-4/G0H0/2018-19

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. Completion certificate filed

  5. to

    Extension granted

    “Six months extension in view of force majeure caused by covid-19 pandemic”

  6. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  7. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2020-21
Q1Q2Q3Q4
FY 2021-22
Q1Q2Q3Q4
FY 2022-23
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered16 Jul 2019
Original completion30 Jun 2026
Revised completion29 Dec 2026
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary4 Aug 2025
Registration fee₹1,13,000
Sanctioning authorityAllahabad Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors120 · 15 · 4 (units from plan)
ConfigurationUnitsCarpet area
3 BHK120119
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
14 · 3 BHK48119
15 · 3 BHK48119
16 · 3 BHK48119
17 · 3 BHK48119
18 · 3 BHK48119
19 · 3 BHK48119
20 · 3 BHK48119
21 · 3 BHK48119
22 · 3 BHK48119
23 · 3 BHK48119
24 · 3 BHK48119
25 · 3 BHK48119
26 · 3 BHK48119
27 · 3 BHK48119
12A · 3 BHK48119
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Mr. Durgi Mahesh Kumar
License CA/1990/13441
7, LSC KalkaJi, New Delhi
Engineer
Mr. T.D. Aneja (F109427-7)
460, Tower 9, HEWO-2, Sector-56, Gurugram
Contractor
In House
10, LSC, Kalkaji New Delhi
Sr.Development work declared to RERA
1Demarcation of Plots
Demarcation of Plots will be done as per Layout plan.
2Boundary Wall
Boundary wall will be constructed as per drawing
3Road Work
Road work will be constructed by promoter as per Layout plan.
4Footpaths
Footpaths will be constructed on road sides.
5Water Supply Including Drinking Water Facilities
Water supply including Drinking water Facilities will developed as per plan. Water supply will be provided by UGT/OHT.
6Sewer System
Sewerage system including STP will be developed as designed. And developed by Promoter
7Drain
All Drainage system will be constructed as per requirement and designed.
8Parks
All Parks within Pockets will be developed as designed by Promoters.
9Tree Planting
Trees will be Planted on the Road side and Green areas as per designed and requirements by Promoter.
10Design For Electric Supply Including Street Lighting
Street Lighting will be provided and electricity supply line will be laid by Promoter
11Community Buildings
Common community building will be provided as per layout
12Treatment and Disposal System of Sewage and Sullage water
STP will be Constructed at site and Disposal as per Requirement
13Solid Waste Management And Disposal System
Solid waste management and disposal system will be Provided as per Requrement.
14Water Conservation System
Rain Water Harvesting will be developed as per required and designed by Promoter
15Energy Management System Including Use of Renewable Energy
Energy management system i/c use of renewable energy will be Provided as per Govt. Norms and designed by Promoter.
16Fire Protection And Fire Safety System
Fire NOC Received and Fire Protection and Fire Safety System will be Provided as per Govt. Norms and designed by Promoter.
17Social Infrastructure And Other Public Amenities Including Public Health Services
All Social infrastructure and public amenities i/c Public health Services will be provided as per Govt. Policy and layout.
18Emergency Evacuation Services
Will be Provided as per plan.
19Other Miscellaneous Work
If required will be Provided as requirement/designed by Promoter
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Registered agents

17 agents

Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.

Sr.AgentRERA registration
1ADITYA KATYALUPRERAAGT13148
2ALMIGHTY INFRAESTATE PVT LTDUPRERAAGT10163
3ALOK UPADHYAYUPRERAAGT12497
4ARCHANA GUPTAUPRERAAGT10881
5ASHOK KUMAR KUSHWAHAUPRERAAGT14495
6DHARMENDRA KUMAR PANDEYUPRERAAGT10923
7DILIP KUMAR SINGHUPRERAAGT10948
8GAUTAM ASSOCIATESUPRERAAGT11617
9GUNJAN PANDEYUPRERAAGT13682
10Purvanchal BuildhomeUPRERAAGT10883
11REENA PANDEYUPRERAAGT11611
12Robins AgarwalUPRERAAGT13151
13SANJEEV KUMAR BANKAUPRERAAGT10894
14SHASHI KANT SHUKLAUPRERAAGT12289
15VELOCITY DEVELOPERSUPRERAAGT10813
16VIKAS PANDEYUPRERAAGT11324
17VIKAS SINGHUPRERAAGT12163
Agents as filed against this project. The grid does not say whether a registration is still valid, so no validity is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 7 Mar 2024.

Sanctioned by Allahabad Development Authority · 21,513 sqm of land · an approved plan of 15 blocks and 120 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
185/PR0A0(T0S0)ZONE-4/G0H0/2018-198 Mar 20197 Mar 20247 Mar 202730 Jun 2026
Plans and approvals filed with RERA
DocumentFile
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
no file published
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 1 completion extension for this project, running to 29 Dec 2026.

#Granted fromExtended uptoNote
130 Jun 202629 Dec 2026Six months extension in view of force majeure caused by covid-19 pandemic

Land & documents

41 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
1981140Khasra
1991600Khasra
2056390Khasra
207230Khasra
2081600Khasra
209910Khasra
2104220Khasra
231k+kh1600Khasra
232 +kha2367Khasra
233+kha4320Khasra
2341260Khasra
2351600Khasra
2373880Khasra
2481370Khasra
249230Khasra
250460Khasra
251 +kha2268Khasra
2534110Khasra
2801480Khasra
2814088Khasra
2821140Khasra
283910Khasra
2841600Khasra
2852459Khasra
2863880Khasra
2981600Khasra
3036390Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Registry document · 35/18
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Sale deed · 2231
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 2442
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 4988
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 5323
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 6096
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 5881
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 6340
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 4340
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 5321
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 1298
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 1514
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 1746
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 3015
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 3440
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 4006
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 4007
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 4261
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 4262
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 4305
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 5322
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 7534
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 7987
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 8431
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 5908
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 352
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 856
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 1864
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 4260
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 6895
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 4260
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 2304
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 2333
The registered deed by which the promoter bought the land.
PDF ↗
Document checklist
DocumentStatusUploaded
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
not reported—
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New21 May 2019 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New21 May 2019 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New21 May 2019 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New21 May 2019 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New21 May 2019 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New21 May 2019 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New28 May 2019 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New21 May 2019 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New2 Jul 2019 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New23 May 2019 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New8 Jul 2019 ↗

Quarterly progress reports

25 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

25 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2026-Q1.

QuarterConstructionCertificates
2020-Q1—CA ↗ · Arch ↗ · Eng ↗
2020-Q2—CA ↗ · Arch ↗ · Eng ↗
2020-Q3—CA ↗ · Arch ↗ · Eng ↗
2020-Q4—CA ↗ · Arch ↗ · Eng ↗
2021-Q1—CA ↗ · Arch ↗ · Eng ↗
2021-Q2—CA ↗ · Arch ↗ · Eng ↗
2021-Q3—CA ↗ · Arch ↗ · Eng ↗
2021-Q4—CA ↗ · Arch ↗ · Eng ↗
2022-Q1—CA ↗ · Arch ↗ · Eng ↗
2022-Q2—CA ↗ · Arch ↗ · Eng ↗
2022-Q3—CA ↗ · Arch ↗ · Eng ↗
2022-Q4—CA ↗ · Arch ↗ · Eng ↗
2023-Q1—CA ↗ · Arch ↗ · Eng ↗
2023-Q2—CA ↗ · Arch ↗ · Eng ↗
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q279.07%CA ↗ · Arch ↗ · Eng ↗
2025-Q379.07%CA ↗ · Arch ↗ · Eng ↗
2025-Q479.07%CA ↗ · Arch ↗ · Eng ↗
2026-Q1100%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameOmaxe Pancham Realcon Pvt. Ltd. (fomerly Pancham Realcon Pvt. Ltd.)
RolePromoter · current
RERA IDUPRERAPRM5731
PANAAECP7196D
CIN / TANU45400DL2008PTC179473
Name of chairmanMr. Manoj Tiwari
Registered address10, Local Shopping Center, Kalkaji, New Delhi - 110019
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Prayagraj

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.

AccountAs filed with RERA
Bank account as filed
Pancham Realcon Pvt. Ltd.- Project Omaxeshiva 2BankAxis BankBranchCivil Lines AllahabadA/C no.IFSCUTIB0000286
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

6 movements

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Promoter’s complaints tally (all their projects)45 (Under Registration - 0 ) → 46 (Under Registration - 1 )
changed in Estanzo’s record
13 Oct 2026
Promoter’s complaints tally (all their projects)45 (Under Registration - 1 ) → 45 (Under Registration - 0 )
changed in Estanzo’s record
9 Oct 2026
Promoter’s complaints tally (all their projects)45 (Under Registration - 2 ) → 45 (Under Registration - 1 )
changed in Estanzo’s record
25 Sept 2026
Promoter’s complaints tally (all their projects)44 (Under Registration - 1 ) → 45 (Under Registration - 2 )
changed in Estanzo’s record
13 Sept 2026
Promoter’s complaints tally (all their projects)44 (Under Registration - 2 ) → 44 (Under Registration - 1 )
changed in Estanzo’s record
9 Sept 2026
Promoter’s complaints tally (all their projects)44 (Under Registration - 3 ) → 44 (Under Registration - 2 )
changed in Estanzo’s record
23 Aug 2026
When these facts last moved
Promoter’s complaints tally (all their projects)changed in Estanzo’s record · 13 Oct 2026 · 6 movements on record
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about Omaxshiva-2

Is Omaxshiva-2 RERA registered?

Yes. Omaxshiva-2 is registered with UPRERA under registration number UPRERAPRJ998764, registered on 16 Jul 2019. Estanzo reproduces that filing; it does not verify the work behind it.

Has Omaxshiva-2 been completed?

UPRERA still lists Omaxshiva-2 as Registered, so it is not shown as completed here. A completion certificate dated 4 Aug 2025 is on the record - RERA accepts these tower-wise, so one on file does not mean the whole project is complete.

Who is the builder of Omaxshiva-2?

Omaxe Pancham Realcon Pvt. Ltd. (fomerly Pancham Realcon Pvt. Ltd.) is the promoter entity that filed Omaxshiva-2 with UPRERA (promoter RERA ID UPRERAPRM5731). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Has UPRERA granted Omaxshiva-2 more time to complete?

UPRERA's record carries 1 completion extension for Omaxshiva-2, the latest running to 29 Dec 2026. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does Omaxshiva-2 have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is Omaxshiva-2 located?

Omaxshiva-2 is registered in Prayagraj, as filed with UPRERA.

What configurations are available in Omaxshiva-2?

The unit plan filed with UPRERA lists 3 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

How many towers and units are planned in Omaxshiva-2?

The approved unit plan describes 15 blocks and 120 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is Omaxshiva-2?

About 23 units per acre: 120 planned units across 5.32 acres (21,513 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗