Registered15 Aug 2017
Promised31 Mar 2021
Today4 Aug 2026

Timeline

Promised completion31 Mar 2021
Revised completion31 Mar 2021
Actual completion
Possession delay64 mo delay

Registration & Cost Details

Registration fee (in ₹)₹19,000
Project cost (in ₹ Lakhs)₹1,700 Lakhs
Project duration84 months
Project categoryResidential
Locality
Original start date9 Oct 2014
Proposed start date9 Oct 2014

Inventory

Total units52
Unit TypeUnitsCarpet Area (sqm)
3 BHK52103.32–138.12

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile8477066667
Emaildaujiom@gmail.com
Coordinator8006107900
Address508, 5th FLOOR, MARUTI PLAZA SANJAY PLACE AGRA Agra UP 282002 IN

No promoter data available.

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
FN. 505/BFT/7/13-149 Oct 20148 Oct 201931 Mar 20218 Oct 2022
FN. 505/BFT/7/13-14

Revalidated: FN. 505/BFT/7/13-14 (9 Oct 2014)

9 Oct 20148 Oct 2019

Revalidated upto: 1 Jan 1900

31 Mar 20218 Oct 2022

Land Parcels

Khasra No.AreaPlot Type
461680.36 sq mtr
461680.36 sq mtr
461680.36 sq mtr
461680.36 sq mtr

Approved Unit Plan

Unit plan rows on file52
Total flats (sum of rows)52
BlocksA
Floor types3 BHK

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
1/2083/87-124/387312 Jun 2008
1/2083/125-163/387412 Jun 2008
1/2094/317-354/406517 Jun 2008
1/2104/269-308/423921 Jun 2008

Frequently Asked Questions

What is the RERA registration number of OMSHREE PLATINUM?

The RERA registration number of OMSHREE PLATINUM is UPRERAPRJ11392, as recorded on the UP-RERA portal.

What is the RERA status of OMSHREE PLATINUM?

As reported by UP-RERA, the status of OMSHREE PLATINUM is "Registered".

Where is OMSHREE PLATINUM located?

As reported to UP-RERA, OMSHREE PLATINUM is located at Agra, Agra, Uttar Pradesh.

When will OMSHREE PLATINUM be completed?

The latest completion date reported to UP-RERA for OMSHREE PLATINUM is 31 Mar 2021.

Is OMSHREE PLATINUM delayed?

Measured against the latest completion date reported to UP-RERA, OMSHREE PLATINUM is 64 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026