Timeline Bar
Registered12 Aug 2017
Promised31 Mar 2019
Today4 Aug 2026
Timeline
Promised completion31 Mar 2019
Revised completion31 Mar 2019
Actual completion—
Possession delay88 mo delay
Registration & Cost Details
Registration fee (in ₹)₹75,000
Project cost (in ₹ Lakhs)₹11,500 Lakhs
Project duration67 months
Project categoryResidential
Locality—
Original start date1 Nov 2014
Proposed start date1 Mar 2015
Inventory
Total units292
| Unit Type | Units | Carpet Area (sqm) |
|---|---|---|
| 1 BHK | 4 | 64.71 |
| 2 BHK | 4 | 85.05 |
| 3 BHK | 232 | 112.88–119.55 |
| 4 BHK | 52 | 152 |
Promoters & Contact
Contact Details
Applicant TypePartnership Firm
Mobile9536873844
Emailsunil332156@gmail.com
Coordinator7534011133
AddressG/C-1, TAJNAGRI PHASE - 2
FATEHABAD ROAD, AGRA - 282001
No promoter data available.
Quarterly Progress Reports
Permit & Extension History
| Permit Number | Permit Date | Valid Upto | Revised End Date | Extended Upto |
|---|---|---|---|---|
| 1587/BFT/03/07-08 | 19 Jul 2014 | 18 Jul 2019 | 31 Mar 2019 | 18 Jul 2022 |
| 1587/BFT/03/07-08 Revalidated: 1587/BFT/03/07-08 (19 Jul 2014) | 19 Jul 2014 | 19 Jul 2019 Revalidated upto: 18 Jul 2021 | 31 Mar 2019 | 18 Jul 2022 |
Land Parcels
| Khasra No. | Area | Plot Type |
|---|---|---|
| 91, 92, 93, 94, 95, 96, 97, 98, 99, 101, 103, 1955 | 13902 | — |
| PART OF PLOT NO. GC-1, TAJ NAGRI PHASE-II | 5319.10 | Plot |
| PART OF PLOT NO. GC-1, TAJ NAGRI PHASE-II | 5319.10 | Plot |
| PART OF PLOT NO. G/C-1, TAJ NAGRI PHASE-II | 3264.16 | Plot |
Approved Unit Plan
Unit plan rows on file56
Total flats (sum of rows)292
BlocksLOTUS TOWER, MARIGOLD TOWER, TULIP TOWER
Floor types1 BHK, 2 BHK, 3 BHK, 4 BHK, OTHER
Individual floor/unit rows are not listed here.
Registry & Agreement Filings
| Registry Number | Registry Date | Land Type | Area |
|---|---|---|---|
| 8964 | 31 Jul 2014 | — | — |
| 8965 | 31 Jul 2014 | — | — |
| 8966 | 31 Jul 2014 | — | — |
Frequently Asked Questions
What is the RERA registration number of Taj Royale?
The RERA registration number of Taj Royale is UPRERAPRJ4847, as recorded on the UP-RERA portal.
What is the RERA status of Taj Royale?
As reported by UP-RERA, the status of Taj Royale is "Registered".
Where is Taj Royale located?
As reported to UP-RERA, Taj Royale is located at Etmadpur, Agra, Uttar Pradesh.
When will Taj Royale be completed?
The latest completion date reported to UP-RERA for Taj Royale is 31 Mar 2019.
Is Taj Royale delayed?
Measured against the latest completion date reported to UP-RERA, Taj Royale is 88 months beyond that date.
Answers generated from this project's public UP-RERA record — data as reported by RERA.
Data as reported by RERA. View source · Scraped 3 Aug 2026