ORCHID BOUNTY

UPRERARegistered

ORCHID BOUNTY is a RERA-registered residential project by SHANTI LAL NIRMAN PRIVATE LIMITED in MOUJA DHOLPURA, Firozabad (RERA ID UPRERAPRJ174389). Registered with a completion deadline of 25 Mar 2029.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
9%Q4'24
9%Q1'25
9%Q2'25
9%Q3'25
9%Q4'25
13.45%Q1'26
15.47%Q2'26
—Q3'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ174389
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryFirozabad-Shikohabad Development Authority
Proposed start4 Oct 2024
Project duration54 months
AddressKHASRA NO. 98, MOUJA DHOLPURA TAHSIL AND DISTRICT FIROZABAD, MOUJA DHOLPURA, Firozabad, Firozabad
TehsilFirozabad
Applicant typeCompany
Applicant addressHOUSE NO. 24, FLOOR 1ST OLD NO-240, B BLOCK-UB LANDMARK NEAR MCDOWNALDS, JAWAHAR NAGAR, New Delhi
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    SHAMAN/210/2020/VI. PRA./(B.NI.)/

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered21 Apr 2026
Original completion25 Mar 2029
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹15,500
Sanctioning authorityFirozabad-Shikohabad Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors19 · 1 · 10 (units from plan)
ConfigurationUnitsCarpet area
4 BHK19194-202
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
ORCHID BOUNTY · 4 BHK1019194-202
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
ASHOK MISHRA
License CA/1991/13916
C-35, Lajpat Marg, C-Scheme, Jaipur
Engineer
KISHAN KULSHRESTHA
JAIN NAGAR KHERA NEAR SAIYYAD MANDIR FIROZABAD 283203
Contractor
ABDUL WASEEM
148/10 MOHALLA HUNDAWALA BAGH FIROZABAD 283203
Sr.Development work declared to RERA
1Demarcation of Plots
We have a plot of 2050 sq. mtr. having 1 main entrance gate from the 30m wide front road.
2Boundary Wall
188 m Length of boundary wall and 2 m high and 230 mm thick Brick work and rcc work in column and beam. At the center face of boundary wall there would be a Logo of the project which give a beautiful iconic design to boundary wall.
3Road Work
From the main entrance gate we have 80 mm thick interlocking brick / RCC road through out the project. Whose wideness starts from 12 mtr. Approx Road Interlocking Area 673 sq. mt.
4Footpaths
We would not provide any footpath.
5Water Supply Including Drinking Water Facilities
We will provide Two nos. of pump for the requirement of blocks through underground pipelines. Size of the Domestic Water tank approx. 20000 Lt.
6Sewer System
Modular Sewerage system shall be Provided. All Sewerage water shall be go to the ST and overflow from the STP shall be connect with the Municipal sewerage system. when come into force and the STP Size is 25 KLD.
7Drain
Strom water shall be Provided. Strom water from Roads and other landscape area shall be connect to the Strom water drain channel and go to the rain water harvesting Pit for recharge the Ground water and overflow shall be connect with Municipal drain line.
8Parks
NA
9Tree Planting
We will provides many type of trees all along the boundary wall and green area.
10Design For Electric Supply Including Street Lighting
We will design and implement the system as per local electricity Board and will consider centralized One Transformer 250 KVA , HT panel, LT panel, Feeder Pillar and DG back for common service like External lighting, Fountain, STP 25 KLD, Pump room etc.
11Community Buildings
NA
12Treatment and Disposal System of Sewage and Sullage water
Modular Sewerage system shall be Provided. All Sewerage water shall be go to the STP and overflow from the STP shall be connect with the Municipal sewerage system., when come into force.
13Solid Waste Management And Disposal System
There are a proper garbage collection area provided for the solid waste management.
14Water Conservation System
We will suggest to individual to use low flow fixtures as well dual flush cistern and raw water harvesting system to reduce the water consumption and improve the ground water level.
15Energy Management System Including Use of Renewable Energy
We will use LED lights fitting in external area as well as solar lights . In Pump room also all the equipment shall have energy efficient motor. And we will suggest to individual also to use. We are providing the One 250 KVA Transformer..
16Fire Protection And Fire Safety System
We will provide Fire Fighting facility in common areas while Individual owner can install their own system as per their and local authorities requirement.
17Social Infrastructure And Other Public Amenities Including Public Health Services
NA
18Emergency Evacuation Services
We will provide have staircases which will be provided with emergency exit doors and emergency exit gates
19Other Miscellaneous Work
NA
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 25 Mar 2029.

Sanctioned by Firozabad-Shikohabad Development Authority · 2,050 sqm of land · an approved plan of 1 block and 19 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
SHAMAN/210/2020/VI. PRA./(B.NI.)/26 Mar 202425 Mar 202925 Mar 202925 Mar 2029
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗

Land & documents

19 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
982050Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Sale deed · JILD NO. 12514 S NO. 5970 PRASHTHA NO. 17 TO 34
The registered deed by which the promoter bought the land.
PDF ↗
Khatauni extract · 1430 TO 1435 (1.7.22 TO 30.6.28 S NO. 218564 AC NO. 00213
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1430 TO 1435
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · FIRE NOC
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · Certified Khatoni - 98
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Document checklist
DocumentStatusUploaded
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
General body resolution
The resolution authorising an apartment owners’ association to act as the registering entity.
not reported—
Affidavit on balance development work
The promoter’s sworn statement about the development work still to be finished.
not reported—
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New10 Jan 2026 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New10 Jan 2026 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New10 Jan 2026 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New9 Feb 2026 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New9 Feb 2026 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New9 Feb 2026 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New9 Feb 2026 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New9 Feb 2026 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New13 Feb 2026 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New13 Mar 2026 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New13 Mar 2026 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New9 Feb 2026 ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
New10 Feb 2026 ↗
Agreement for sale (proforma)
The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind.
New17 Apr 2026 ↗

Quarterly progress reports

8 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

8 quarterly progress reports are on file with UPRERA, covering 2024-Q3 to 2026-Q2.

QuarterConstructionCertificates
2024-Q39%CA ↗ · Arch ↗ · Eng ↗
2024-Q49%CA ↗ · Arch ↗ · Eng ↗
2025-Q19%CA ↗ · Arch ↗ · Eng ↗
2025-Q29%CA ↗ · Arch ↗ · Eng ↗
2025-Q39%CA ↗ · Arch ↗ · Eng ↗
2025-Q413.45%CA ↗ · Arch ↗ · Eng ↗
2026-Q115.47%CA ↗ · Arch ↗ · Eng ↗
2026-Q2—CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameSHANTI LAL NIRMAN PRIVATE LIMITED
RolePromoter · current
RERA IDUPRERAPRM346996
PANAALCS4279H
CIN / TANU70102DL2007PTC162000
Name of chairmanANSHIT MITTAL
Registered addressHOUSE NO. 24, FLOOR 1ST OLD NO-240, B BLOCK-UB LANDMARK NEAR MCDOWNALDS, JAWAHAR NAGAR, New Delhi
RERA contact
Registered since2025
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Firozabad

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
SHANTI LAL NIRMAN PVT LTD COLLECTION ACCOUNT FOR ORCHID BOUNTYBankBANK OF MAHARASHTRABranchFIROZABADBranch address31 MONAPURAM GANESH NAGAR FIROZABADBranch districtFirozabad, Uttar PradeshA/C no.IFSCMAHB0001317Branch emailbom1317@mahabank.co.in
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
SHANTI LAL NIRMAN PVT LTD SEPARATE ACCOUNT FOR ORCHID BOUNTYBankBANK OF MAHARASHTRABranchFIROZABADBranch address31 MONAPURAM GANESH NAGAR FIROZABADBranch districtFirozabad, Uttar PradeshA/C no.IFSCMAHB0001317
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
SHANTI LAL NIRMAN PVT LTD TRANSACTION ACCOUNT FOR ORCHID BOUNTYBankBANK OF MAHARASHTRABranchFIROZABADBranch address31 MONAPURAM GANESH NAGAR FIROZABADBranch districtFirozabad, Uttar PradeshA/C no.IFSCMAHB0001317
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

1 movement

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Quarterly progress report
2026-Q2
QPR 2026-Q2
newly filed with RERA
18 Oct 2026
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about ORCHID BOUNTY

Is ORCHID BOUNTY RERA registered?

Yes. ORCHID BOUNTY is registered with UPRERA under registration number UPRERAPRJ174389, registered on 21 Apr 2026. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for ORCHID BOUNTY?

The completion date filed with UPRERA is 25 Mar 2029. No completion certificate is on record yet.

Who is the builder of ORCHID BOUNTY?

SHANTI LAL NIRMAN PRIVATE LIMITED is the promoter entity that filed ORCHID BOUNTY with UPRERA (promoter RERA ID UPRERAPRM346996). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does ORCHID BOUNTY have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is ORCHID BOUNTY located?

ORCHID BOUNTY is registered in MOUJA DHOLPURA, Firozabad, as filed with UPRERA.

What configurations are available in ORCHID BOUNTY?

The unit plan filed with UPRERA lists 4 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in ORCHID BOUNTY?

The approved unit plan filed with UPRERA runs from 194 to 202 m² of carpet area (about 2,087 to 2,174 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in ORCHID BOUNTY?

The approved unit plan describes 1 block and 19 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is ORCHID BOUNTY?

About 38 units per acre: 19 planned units across 0.51 acres (2,050 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗