Timeline Bar
Registered14 Aug 2017
Promised30 Apr 2020
Completed24 Mar 2022
Timeline
Promised completion30 Apr 2020
Revised completion30 Apr 2020
Actual completion24 Mar 2022
Possession delay23 mo delay
Registration & Cost Details
Registration fee (in ₹)₹18,500
Project cost (in ₹ Lakhs)₹800 Lakhs
Project duration54 months
Project categoryResidential
Locality—
Original start date1 May 2016
Proposed start date1 May 2016
Inventory
Total units37
| Unit Type | Units | Carpet Area (sqm) |
|---|---|---|
| 3 BHK | 27 | 118.18 |
| 4 BHK | 9 | 141.9 |
| PENTHOUSE | 1 | 300.65 |
Promoters & Contact
Contact Details
Applicant TypeCompany
Mobile9760036921
Emaillalitca2003@rediffmail.com
Coordinator9837030405
AddressRAJA KA TAAL , ORCHID GREEN FIROZABAD
No promoter data available.
Quarterly Progress Reports
Permit & Extension History
| Permit Number | Permit Date | Valid Upto | Revised End Date | Extended Upto |
|---|---|---|---|---|
| 154/14 | 18 Apr 2016 | 17 Apr 2021 | 30 Apr 2020 | 17 Apr 2023 |
Land Parcels
| Khasra No. | Area | Plot Type |
|---|---|---|
| 699 | 2692 SQ MTR | — |
| 699 | 2691.57 | Khasra |
Approved Unit Plan
Unit plan rows on file19
Total flats (sum of rows)37
BlocksORCHID GINGER 2
Floor types3 BHK, 4 BHK, PENTHOUSE
Individual floor/unit rows are not listed here.
Registry & Agreement Filings
| Registry Number | Registry Date | Land Type | Area |
|---|---|---|---|
| 258 | 8 Jan 2015 | — | — |
Frequently Asked Questions
What is the RERA registration number of ORCHID GINGER 2?
The RERA registration number of ORCHID GINGER 2 is UPRERAPRJ10930, as recorded on the UP-RERA portal.
What is the RERA status of ORCHID GINGER 2?
As reported by UP-RERA, the status of ORCHID GINGER 2 is "Registered".
Where is ORCHID GINGER 2 located?
As reported to UP-RERA, ORCHID GINGER 2 is located at Firozabad, Firozabad, Uttar Pradesh.
Is ORCHID GINGER 2 completed?
As reported to UP-RERA, ORCHID GINGER 2 was completed on 24 Mar 2022.
Is ORCHID GINGER 2 delayed?
Measured against the latest completion date reported to UP-RERA, ORCHID GINGER 2 is 23 months beyond that date.
Answers generated from this project's public UP-RERA record — data as reported by RERA.