Timeline Bar
Registered9 Aug 2017
Promised11 Mar 2019
Revised10 Sept 2019
Completed8 Dec 2019
Timeline
Promised completion11 Mar 2019
Revised completion10 Sept 2019
Actual completion8 Dec 2019
Possession delay3 mo delay
Registration & Cost Details
Registration fee (in ₹)₹54,000
Project cost (in ₹ Lakhs)₹6,000 Lakhs
Project duration55 months
Project categoryCommercial
Locality—
Original start date10 Mar 2015
Proposed start date10 Mar 2015
Inventory
Total units43
| Unit Type | Units | Carpet Area (sqm) |
|---|---|---|
| SHOP | 43 | 18.68–670.4 |
Promoters & Contact
Contact Details
Applicant TypeCompany
Mobile9839981000
Emailsandeepktekriwal@gmail.com
Coordinator9936381000
Address5 F EVEREST 46/C CHOWRINGHEE ROAD KOLKATA WEST BENGAL 700071 INDIA
No promoter data available.
Permit & Extension History
| Permit Number | Permit Date | Valid Upto | Revised End Date | Extended Upto |
|---|---|---|---|---|
| 261/2013 | 10 Mar 2015 | 9 Mar 2020 | 10 Sept 2019 | 9 Mar 2023 |
| 261/2013 Revalidated: 261/2013 (10 Mar 2015) | 10 Mar 2015 | 9 Mar 2020 Revalidated upto: 1 Jan 1900 | 10 Sept 2019 | 9 Mar 2023 |
Land Parcels
| Khasra No. | Area | Plot Type |
|---|---|---|
| H.No.- C/102/686A AND C/102/686 | 3908.4934 | — |
| 374/1MI | 161.903 | — |
| 374/1MI | 344.981 | — |
Approved Unit Plan
Unit plan rows on file45
Total flats (sum of rows)43
Total shops43
Blocks1
Floor typesSHOP, OTHER
Individual floor/unit rows are not listed here.
Registry & Agreement Filings
| Registry Number | Registry Date | Land Type | Area |
|---|---|---|---|
| 9050 | 9 Aug 2012 | — | — |
| 10395 | 19 Sept 2012 | — | — |
| 9896 | 4 Sept 2012 | — | — |
Frequently Asked Questions
What is the RERA registration number of ORION MALL?
The RERA registration number of ORION MALL is UPRERAPRJ8860, as recorded on the UP-RERA portal.
What is the RERA status of ORION MALL?
As reported by UP-RERA, the status of ORION MALL is "Registered".
Where is ORION MALL located?
As reported to UP-RERA, ORION MALL is located at Gorakhpur, Gorakhpur, Uttar Pradesh.
Is ORION MALL completed?
As reported to UP-RERA, ORION MALL was completed on 8 Dec 2019.
Is ORION MALL delayed?
Measured against the latest completion date reported to UP-RERA, ORION MALL is 3 months beyond that date.
Answers generated from this project's public UP-RERA record — data as reported by RERA.
Data as reported by RERA. View source · Scraped 28 Jul 2026