PEARL GREEN is a RERA-registered residential project by PEYUSH INFRAREALTORS LLP in Moradabad (RERA ID UPRERAPRJ877113). Registered with a completion deadline of 30 Jun 2027.
RERA status as reported: Registered.Construction progress
Construction stayed at 89% across 3 consecutive filed quarters (Jul–Sep 2025 to Jan–Mar 2026). The promoter filed the same figure each time. Quarters with no percentage filed are not counted either way.
Basic details
The promoter’s own descriptions, published as filed. UP-RERA does not certify them.
| RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossary | UPRERAPRJ877113 |
| Project category | Residential |
| Registration type | New |
| RERA status | Registered |
| Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossary | Moradabad Development Authority |
| Proposed start | 7 Sept 2022 |
| Project duration | 58 months |
| Address | Moradabad, Moradabad |
| Tehsil | Moradabad |
| Applicant type | Partnership Firm |
| Applicant address | A-42, HIG, Ram Ganga Vihar, Kanth Road Moradabad Uttar Pradesh 244001 |
| Applicant contact |
Project timeline
Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.
Building permit sanctioned
MBDA/LD/21-22/0537
Construction start, as declared
A date on the record, not a filing — what was planned as of this entry.
Registered with RERA
Completion promised at registration
A date on the record, not a filing — what was planned as of this entry.
Revised completion deadline
A date on the record, not a filing — what was planned as of this entry.
A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.
Registration & timeline
Dates on the registration itself, not on construction - the quarterly reports carry that.
| RERA registered | 28 Jul 2023 |
| Original completion | 30 Jun 2027 |
| Revised completion | — none granted |
| First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary | - not on record |
| Registration fee | ₹2,04,500 |
| Sanctioning authority | Moradabad Development Authority |
Project team & development works
Who was engaged and what was promised. No status is filed against any of it.
| Sr. | Development work declared to RERA |
|---|---|
| 1 | Demarcation of Plots Demarcation will be done as per approved Layout. Total No. of plots are 139. |
| 2 | Boundary Wall On Going construction on site, Boundary wall is 3 Meter in Height to be built in 230 mm thick brick work. |
| 3 | Road Work Internal roads are 18 Meter , 12 Meter,9 Meter and 7.5 Meter wide. |
| 4 | Footpaths Footpaths will be constructed along with roads. Pedestrians are 1.5 meter wide. |
| 5 | Water Supply Including Drinking Water Facilities Water supply will be provided by developer through pump Room. Domestic water supply /irrigation water supply /treated water supply providing , laying and jointing in position HDPE PE 100 PN 6.0 MAINLINE PIPE CONFORMING to IS 4984 and suitable for the respecting working pressure with all fittings complete. |
| 6 | Sewer System Sewer system will be provided by Developer and STP system is also proposed by Developer. sewer pipe of 150mm-300mm diameter are laid on site. |
| 7 | Drain Strom Lines have been provided by developers along with Roads. providing and laying cement concrete 1-5-10(1 cement-5fine sand-10 graded stone aggregate 40 mm nominal size) below S.W. pipes including bed concrete as per standard design. |
| 8 | Parks Land has been reserved for Park as per Layout. landscaping work will be done in parks including all plants and grass, pathways , sitting area and children play area. |
| 9 | Tree Planting Tree Planting will be done along the roads as per approved Layout. |
| 10 | Design For Electric Supply Including Street Lighting Electrical substation are proposed by developer. Supply and erection of electric pole grounded with p.c.c. 1-3-6 including excavated refilling, painting of all completion of the work supply and installation of G.I. wire earthing and installation of transformer. |
| 11 | Community Buildings N/A |
| 12 | Treatment and Disposal System of Sewage and Sullage water STP system has been proposed by Developer for Treatment and disposal system of Sewage and Sullage water. |
| 13 | Solid Waste Management And Disposal System Solid waste Management and Disposal system has been provided by Developer as per requirement. |
| 14 | Water Conservation System Rain Water Harvesting Tanks will be construction on site for water conservation. |
| 15 | Energy Management System Including Use of Renewable Energy N/A |
| 16 | Fire Protection And Fire Safety System N/A |
| 17 | Social Infrastructure And Other Public Amenities Including Public Health Services N/A |
| 18 | Emergency Evacuation Services N/A |
| 19 | Other Miscellaneous Work To be Executed on site as per Sanctioned Plan |
Permits & extensions
1 permit
An approval and the date it runs to - not proof the work matching it was done.
1 sanctioning permit is on record with UPRERA, valid to 31 Jul 2027.
Sanctioned by Moradabad Development Authority · 39,635.08 sqm of land. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total.
| Permit no. | Date | Valid upto | Extendable upto | Revised end | Documents filed |
|---|---|---|---|---|---|
| MBDA/LD/21-22/0537 | 24 Jun 2022 | 31 Jul 2027 | 30 Jul 2028 | 30 Jun 2027 |
| Document | File |
|---|---|
| Other plan A plan the promoter filed that does not fall under the authority’s named headings. | no file published |
| Commencement certificate The sanctioning authority’s permission to begin construction - the document that says work could lawfully start. | PDF ↗ |
Land & documents
49 filings
How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.
| KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossary | Area | Type |
|---|---|---|
| 2174 | 1215 | Khasra |
| 2168 MI | 540 | Khasra |
| 2168 MI | 880 | Khasra |
| 2169 MI | 1830 | Khasra |
| 2170 MI | 1270 | Khasra |
| 2103 | 4440 | Khasra |
| 2156 | 3240 | Khasra |
| 2161 | 1780 | Khasra |
| 2162 MI | 1980 | Khasra |
| 2163 MI | 1860 | Khasra |
| 2164 | 3605 | Khasra |
| 2157 MI | 1150 | Khasra |
| 2166/2 | 870 | Khasra |
| 2167/2 | 870 | Khasra |
| 2158 MI | 3320 | Khasra |
| 2155 | 2230 | Khasra |
| 2172 | 2707 | Khasra |
| 2165 | 1300 | Khasra |
| 2166/1 | 1150 | Khasra |
| 2167/1 | 1150 | Khasra |
| 2171 | 1250 | Khasra |
| 2154 | 1210 | Khasra |
| Registry document · 1932 The deed as registered with the sub-registrar, which is what proves the transfer took place. | PDF ↗ |
| Registry document · 1934 The deed as registered with the sub-registrar, which is what proves the transfer took place. | PDF ↗ |
| Registry document · 1933 The deed as registered with the sub-registrar, which is what proves the transfer took place. | PDF ↗ |
| Khatauni extract · 1427-1432 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Khatauni extract · 1427-1432 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Khatauni extract · 1427-1432 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Khatauni extract · 1427-1432 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Khatauni extract · 1427-1432 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Khatauni extract · 1427-1432 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Khatauni extract · 1427-1432 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Khatauni extract · 1427-1432 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Khatauni extract · 1427-1432 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Khatauni extract · 1427-1432 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Khatauni extract · 1427-1432 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Khatauni extract · 1427-1432 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Khatauni extract · 1427-1432 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Khatauni extract · 1427-1432 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Registry document · 7394 The deed as registered with the sub-registrar, which is what proves the transfer took place. | PDF ↗ |
| Registry document · 6632 The deed as registered with the sub-registrar, which is what proves the transfer took place. | PDF ↗ |
| Registry document · 7817 The deed as registered with the sub-registrar, which is what proves the transfer took place. | PDF ↗ |
| Registry document · 7819 The deed as registered with the sub-registrar, which is what proves the transfer took place. | PDF ↗ |
| Registry document · 4041 The deed as registered with the sub-registrar, which is what proves the transfer took place. | PDF ↗ |
| Registry document · 6345 The deed as registered with the sub-registrar, which is what proves the transfer took place. | PDF ↗ |
| Registry document · 7818 The deed as registered with the sub-registrar, which is what proves the transfer took place. | PDF ↗ |
| Registry document · landchart The deed as registered with the sub-registrar, which is what proves the transfer took place. | PDF ↗ |
| Document | Status | Uploaded |
|---|---|---|
| Encumbrance details What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer. | not reported | — |
| Encumbrance details What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer. | not reported | — |
| Conveyance deed (proforma) The blank deed by which title would eventually transfer to the buyer or the association. | not reported | — |
| Completion / occupancy certificate (proforma) The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued. | not reported | — |
| Water supply plan How the project proposed to supply water, as filed at registration. | not reported | — |
| Electricity supply plan How the project proposed to supply power, as filed at registration. | not reported | — |
| Electricity supply plan How the project proposed to supply power, as filed at registration. | not reported | — |
| Chartered accountant’s certificate The CA’s certification of the money drawn from the project account against the stage of construction. | not reported | — |
| Chartered accountant’s certificate The CA’s certification of the money drawn from the project account against the stage of construction. | not reported | — |
| Architect’s certificate The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage. | not reported | — |
| Architect’s certificate The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage. | not reported | — |
| Engineer’s certificate The engineer’s certification of the cost incurred on construction to date. | not reported | — |
| Other A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is. | not reported | — |
| Other A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is. | not reported | — |
| Encumbrance details What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer. | New | 19 Jul 2023 ↗ |
| Application form (proforma) The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking. | New | 20 Jun 2023 ↗ |
| Allotment letter (proforma) The blank allotment letter on record - what the promoter said it would issue on booking. | New | 20 Jun 2023 ↗ |
| Conveyance deed (proforma) The blank deed by which title would eventually transfer to the buyer or the association. | New | 13 Jul 2023 ↗ |
| Waste disposal plan How the project proposed to handle sewage and solid waste, as filed at registration. | New | 20 Jun 2023 ↗ |
| Water supply plan How the project proposed to supply water, as filed at registration. | New | 19 Jul 2023 ↗ |
| Electricity supply plan How the project proposed to supply power, as filed at registration. | New | 19 Jul 2023 ↗ |
| Development work plan The internal development the promoter undertook to build - roads, drainage and the rest of the site works. | New | 18 Jul 2023 ↗ |
| Affidavit (Form B) The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account. | New | 20 Jun 2023 ↗ |
| Chartered accountant’s certificate The CA’s certification of the money drawn from the project account against the stage of construction. | New | 14 Jul 2023 ↗ |
| Architect’s certificate The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage. | New | 14 Jul 2023 ↗ |
| Engineer’s certificate The engineer’s certification of the cost incurred on construction to date. | New | 14 Jul 2023 ↗ |
| Other A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is. | New | 18 Jul 2023 ↗ |
Quarterly progress reports
15 filed reports
The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.
15 quarterly progress reports are on file with UPRERA, covering 2022-Q2 to 2025-Q4.
| Quarter | Construction | Certificates |
|---|---|---|
| 2022-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q2 | 89% | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q3 | 89% | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q4 | 89% | CA ↗ · Arch ↗ · Eng ↗ |
Promoter (SPV) details
The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.
| Legal name | PEYUSH INFRAREALTORS LLP |
| Role | Promoter · current |
| RERA ID | UPRERAPRM217561 |
| PAN | ABCFP8133C |
| CIN / TAN | LKNP11482C |
| Registered address | A-42, HIG, Ram Ganga Vihar, Kanth Road Moradabad Uttar Pradesh 244001 |
| RERA contact | |
| Registered since | 2023 |
Nearby projects
Moradabad
Straight-line distance between filed coordinates. Not a comparison and not a travel time.
Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.
RERA bank accounts
verify before payment
Not confirmation that money is in these accounts, and details change - verify at the source before paying.
Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:
3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.
| Account | As filed with RERA |
|---|---|
| CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary | PEYUSH INFRAREALTORS LLP COLLECTION ACCOUNT FOR PEARL GREENBankPUNJAB NATIONAL BANKBranchCIVIL LINESBranch addressCIVIL LINES,MORADABADBranch districtMoradabad, Uttar PradeshA/C no.IFSCPUNB0254000 |
| SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary | PEYUSH INFRAREALTORS LLP SEPARATE BANK ACCOUNT FOR PEARL GREENBankPUNJAB NATIONAL BANKBranchCIVIL LINESBranch addressCIVIL LINES,MORADABADBranch districtMoradabad, Uttar PradeshA/C no.IFSCPUNB0254000 |
| TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary | PEYUSH INFRAREALTORS LLP RERA TRANSACTION ACCOUNT FOR PEARL GREENBankPUNJAB NATIONAL BANKBranchCIVIL LINESBranch addressCIVIL LINES,MORADABADBranch districtMoradabad, Uttar PradeshA/C no.IFSCPUNB0254000 |
What has changed on this record
nothing recorded yet
When Estanzo first saw a difference - not proof RERA’s record changed that day.
Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.What to verify and what to ask
2 not published
Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.
- No approved unit plan is published for this project.Ask for the carpet area of the specific unit in writing, and for the approved floor plan it is measured from.
- No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.
Common questions about PEARL GREEN
Is PEARL GREEN RERA registered?
Yes. PEARL GREEN is registered with UPRERA under registration number UPRERAPRJ877113, registered on 28 Jul 2023. Estanzo reproduces that filing; it does not verify the work behind it.
When is possession due for PEARL GREEN?
The completion date filed with UPRERA is 30 Jun 2027. No completion certificate is on record yet.
Who is the builder of PEARL GREEN?
PEYUSH INFRAREALTORS LLP is the promoter entity that filed PEARL GREEN with UPRERA (promoter RERA ID UPRERAPRM217561). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.
Does PEARL GREEN have a RERA bank account?
Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.
Where is PEARL GREEN located?
PEARL GREEN is registered in Moradabad, as filed with UPRERA.
Data as reported by UPRERA, as of 21 Oct 2026. official source ↗