Radhe Kunj ExtensionUPRERA
Home › Projects › Shahjahanpur › Radhe Kunj Extension

Radhe Kunj Extension

UPRERARegisteredConstruction 100% · 2026 Q1updated 4 Aug 2026

Radhe Kunj Extension is a RERA-registered real-estate project in Nawada Indeypur, Shahjahanpur (RERA ID UPRERAPRJ917908). Registered with a completion deadline of 31 Mar 2029. Data as reported by UP-RERA. as reported by UPRERA

RERA status as reported: Registered.
Project cost
₹4
Land area
not reported
Units
not reported
Density (derived)
not reported
Towers
not reported
Config
not reported
Carpet
not reported
Registered
7 Aug 2024

Construction progress

As filed in quarterly progress reports · % complete · latest filed 2026 Q1
—Q2'24
—Q3'24
—Q4'24
—Q1'25
0%Q2'25
0%Q3'25
100%Q4'25
100%Q1'26

Basic details

RERA IDUPRERAPRJ917908
Applicant typePartnership Firm
Project categoryResidential
Project typeother
RERA statusRegistered
Proposed start1 Jun 2024
Project duration58
AddressKeshav Kunj Colony, Nawada Indeypur, Shahjahanpur, Shahjahanpur

Registration & timeline

RERA registered7 Aug 2024
Promised completion31 Mar 2029
Revised completion— none granted
Completion certificate filed— not on record
Registration fee₹38,000

Permits & extensions

1 permit
Permit no.DateValid uptoRevised end
298/2023-2420 Apr 202419 Apr 202931 Mar 2029

Land & documents

1 filing
KhasraAreaType
406555Khasra

Quarterly progress reports

9 filed reports
QuarterConstructionCertificatesSource
2024-Q1—CA · Arch · Engview ↗
2024-Q2—CA · Arch · Engview ↗
2024-Q3—CA · Arch · Engview ↗
2024-Q4—CA · Arch · Engview ↗
2025-Q1—CA · Arch · Engview ↗
2025-Q20%CA · Arch · Engview ↗
2025-Q30%CA · Arch · Engview ↗
2025-Q4100%CA · Arch · Engview ↗
2026-Q1100%CA · Arch · Engview ↗
“—” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1.

Nearby projects

Shahjahanpur

Other projects registered in Shahjahanpur.

CITY PARK
UPRERA ▲ 91 mo
CITY PARK
UPRERA ▲ 79 mo
City Park Extension
UPRERA ▲ 38 mo
MEGHA CITY TOWNSHIP
UPRERA ▲ 18 mo
Model Town
UPRERA ▲ 36 mo
Radhe Kunj
UPRERA ▲ 57 mo

Common questions about Radhe Kunj Extension

Is Radhe Kunj Extension RERA registered?

Yes. Radhe Kunj Extension is registered with UPRERA under registration number UPRERAPRJ917908, registered on 7 Aug 2024. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for Radhe Kunj Extension?

The completion date filed with UPRERA is 31 Mar 2029. No completion certificate is on record yet, and that deadline has not passed.

Where is Radhe Kunj Extension located?

Radhe Kunj Extension is registered in Nawada Indeypur, Shahjahanpur, as filed with UPRERA.

Data as reported by UPRERA, last collected 4 Aug 2026. official source ↗

At a glance

StatusRegistered
QPR filingNo default reported
DistrictShahjahanpur
LocalityNawada Indeypur
Last updated4 Aug 2026

Location

AddressKeshav Kunj Colony
View on map ↗

RERA buyer helpline

Coordinator9235588888
official grievance contact, as published by RERA