South City Extension Phase 1 is a RERA-registered residential project by Kunjshree Infrabuild LLP in Shahjahanpur (RERA ID UPRERAPRJ409057). Registered with a completion deadline of 23 Nov 2025.
RERA status as reported: Registered.Construction progress
Construction stayed at 33.33% across 9 consecutive filed quarters (Oct–Dec 2023 to Oct–Dec 2025). The promoter filed the same figure each time. Quarters with no percentage filed are not counted either way.
Basic details
The promoter’s own descriptions, published as filed. UP-RERA does not certify them.
| RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossary | UPRERAPRJ409057 |
| Project category | Residential |
| Registration type | New |
| RERA status | Registered |
| Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossary | Any Other Competent Authority |
| Proposed start | 24 Nov 2020 |
| Project duration | 60 months |
| Address | Shahjahanpur, Shahjahanpur |
| Tehsil | Shahjahanpur |
| Applicant type | Partnership Firm |
| Applicant address | Q1, Kunj Bihari Colony , South City , Shahjahanpur |
| Applicant contact |
Project timeline
Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.
2 building permits sanctioned
Construction start, as declared
A date on the record, not a filing — what was planned as of this entry.
Registered with RERA
Completion certificate filed
Completion promised at registration
A date on the record, not a filing — what was planned as of this entry.
Revised completion deadline
A date on the record, not a filing — what was planned as of this entry.
A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.
Registration & timeline
Dates on the registration itself, not on construction - the quarterly reports carry that.
| RERA registered | 18 May 2021 |
| Original completion | 23 Nov 2025 |
| Revised completion | — none granted |
| First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary | 28 Jun 2022 |
| Registration fee | ₹51,500 |
| Sanctioning authority | Any Other Competent Authority |
Project team & development works
Who was engaged and what was promised. No status is filed against any of it.
| Sr. | Development work declared to RERA |
|---|---|
| 1 | Demarcation of Plots We Have total 31 plots of different sizes, from 97.12 Sqmtr. to 137.97 sqmtr. In Ths Phase of the Project. |
| 2 | Boundary Wall Boundary wall is proposed in this part of the project. |
| 3 | Road Work From the main entrance gate we have proposed CC road work through out the entire project. whose wideness ranges between 12 mtr to 9 mtr/ as approved by prescribed authority, Shahjahanpur. |
| 4 | Footpaths we will provide footpath both side of the road with adequate width and beautiful pattern. |
| 5 | Water Supply Including Drinking Water Facilities we will provide separate submersible Boaring pump to each houses. |
| 6 | Sewer System Sewerage system shall be provided. All Sewerage water shall be connect with the Nearest Municipal Line. |
| 7 | Drain Drains Shall be connect with all units and 11 links drains shall be connect with a Main Drain, it shall be connect with nearest Municipal Drain Line. |
| 8 | Parks 1457.50 Sqm Green Areas are proposed through out the Whole project. |
| 9 | Tree Planting we will provide evergreen and best available types of trees all along with the boundary wall and green area as per sanction map approved by the development authority |
| 10 | Design For Electric Supply Including Street Lighting we will design and implement the system as per local electricity Board and will consider centralized Transformer, HT Panel, LT Panel, Feeder Pillar etc. |
| 11 | Community Buildings Not Proposed in this Phase. |
| 12 | Treatment and Disposal System of Sewage and Sullage water Sewerage system shall be provided. All Sewerage water shall be connect with the Nearest Municipal Line. |
| 13 | Solid Waste Management And Disposal System There are a proper garbage collection area provided for the solid waste management as per municipal guidelines |
| 14 | Water Conservation System we will suggest individuals to use low fixtures as well dual flush cistern and raw water harvesting system to reduce the water consumption and improve the ground water level. |
| 15 | Energy Management System Including Use of Renewable Energy We will use LED lights fittings in External area and Streets Lights |
| 16 | Fire Protection And Fire Safety System For Fire Fighting facility, Individual owner can install thier own system as per their need and local authorities requirement. |
| 17 | Social Infrastructure And Other Public Amenities Including Public Health Services Sewerage, Drain water and water supply system shall be provided. We Have Proposed Common Pump room. Roads and other area shall be connect to the storm water drain channel, Ground water and overflow shall be connect with municipal drain. |
| 18 | Emergency Evacuation Services As the project is a plotted development, Individuals will take care of this at their own level |
| 19 | Other Miscellaneous Work NA |
Permits & extensions
2 permits
An approval and the date it runs to - not proof the work matching it was done.
2 sanctioning permits are on record with UPRERA, the latest valid to 23 Nov 2025.
Sanctioned by Any Other Competent Authority · 9,221 sqm of land. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total.
| Permit no. | Date | Valid upto | Extendable upto | Revised end | Documents filed |
|---|---|---|---|---|---|
| 88/2020-21 | 24 Nov 2020 | 23 Nov 2025 | 23 Nov 2028 | 23 Nov 2025 | |
| 88/2020-21 | 24 Nov 2020 | 23 Nov 2025 | 23 Nov 2028 | 23 Nov 2025 |
| Document | File |
|---|---|
| Commencement certificate The sanctioning authority’s permission to begin construction - the document that says work could lawfully start. | PDF ↗ |
| Other plan A plan the promoter filed that does not fall under the authority’s named headings. | PDF ↗ |
Land & documents
16 filings
How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.
| KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossary | Area | Type |
|---|---|---|
| 299,300,301 | 9715 | Khasra |
| Sale deed · 9930 The registered deed by which the promoter bought the land. | PDF ↗ |
| Sale deed · 9929 The registered deed by which the promoter bought the land. | PDF ↗ |
| Khatauni extract · 1428-1433 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Khatauni extract · 1428-1433 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Khatauni extract · 1428-1433 An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Khatauni extract · Reply to query letter An extract of the village land record showing the khasra plots and who is recorded against them. | PDF ↗ |
| Document | Status | Uploaded |
|---|---|---|
| Completion / occupancy certificate (proforma) The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued. | not reported | — |
| Architect’s certificate The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage. | not reported | — |
| Engineer’s certificate The engineer’s certification of the cost incurred on construction to date. | not reported | — |
| Encumbrance details What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer. | New | 7 Apr 2021 ↗ |
| Application form (proforma) The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking. | New | 19 Mar 2021 ↗ |
| Allotment letter (proforma) The blank allotment letter on record - what the promoter said it would issue on booking. | New | 7 Apr 2021 ↗ |
| Conveyance deed (proforma) The blank deed by which title would eventually transfer to the buyer or the association. | New | 19 Mar 2021 ↗ |
| Waste disposal plan How the project proposed to handle sewage and solid waste, as filed at registration. | New | 19 Mar 2021 ↗ |
| Water supply plan How the project proposed to supply water, as filed at registration. | New | 19 Mar 2021 ↗ |
| Electricity supply plan How the project proposed to supply power, as filed at registration. | New | 19 Mar 2021 ↗ |
| Development work plan The internal development the promoter undertook to build - roads, drainage and the rest of the site works. | New | 19 Mar 2021 ↗ |
| Affidavit (Form B) The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account. | New | 19 Mar 2021 ↗ |
| Chartered accountant’s certificate The CA’s certification of the money drawn from the project account against the stage of construction. | New | 19 Mar 2021 ↗ |
| Architect’s certificate The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage. | New | 7 Apr 2021 ↗ |
| Engineer’s certificate The engineer’s certification of the cost incurred on construction to date. | New | 7 Apr 2021 ↗ |
Quarterly progress reports
21 filed reports
The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.
21 quarterly progress reports are on file with UPRERA, covering 2020-Q3 to 2025-Q3.
| Quarter | Construction | Certificates |
|---|---|---|
| 2020-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2020-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2021-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q3 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2022-Q4 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q1 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q2 | — | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q3 | 33.33% | CA ↗ · Arch ↗ · Eng ↗ |
| 2023-Q4 | 33.33% | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q1 | 33.33% | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q2 | 33.33% | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q3 | 33.33% | CA ↗ · Arch ↗ · Eng ↗ |
| 2024-Q4 | 33.33% | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q1 | 33.33% | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q2 | 33.33% | CA ↗ · Arch ↗ · Eng ↗ |
| 2025-Q3 | 33.33% | CA ↗ · Arch ↗ · Eng ↗ |
Promoter (SPV) details
The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.
| Legal name | Kunjshree Infrabuild LLP |
| Role | Promoter · current |
| RERA ID | UPRERAPRM138323 |
| PAN | AAVFK5803G |
| CIN / TAN | LKNK08394B |
| Registered address | Q1, Kunj Bihari Colony , South City , Shahjahanpur |
| RERA contact | |
| Registered since | 2021 |
Nearby projects
Shahjahanpur
Straight-line distance between filed coordinates. Not a comparison and not a travel time.
Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.
RERA bank accounts
verify before payment
Not confirmation that money is in these accounts, and details change - verify at the source before paying.
Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:
One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.
| Account | As filed with RERA |
|---|---|
| Bank account as filed | Kunjshree Infrabuild LLPBankState Bank of IndiaBranchKNSB ShahjahanpurA/C no.IFSCSBIN0004000 |
What has changed on this record
nothing recorded yet
When Estanzo first saw a difference - not proof RERA’s record changed that day.
Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.What to verify and what to ask
2 not published
Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.
- No approved unit plan is published for this project.Ask for the carpet area of the specific unit in writing, and for the approved floor plan it is measured from.
- No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.
Common questions about South City Extension Phase 1
Is South City Extension Phase 1 RERA registered?
Yes. South City Extension Phase 1 is registered with UPRERA under registration number UPRERAPRJ409057, registered on 18 May 2021. Estanzo reproduces that filing; it does not verify the work behind it.
Has South City Extension Phase 1 been completed?
UPRERA still lists South City Extension Phase 1 as Registered, so it is not shown as completed here. A completion certificate dated 28 Jun 2022 is on the record - RERA accepts these tower-wise, so one on file does not mean the whole project is complete.
Who is the builder of South City Extension Phase 1?
Kunjshree Infrabuild LLP is the promoter entity that filed South City Extension Phase 1 with UPRERA (promoter RERA ID UPRERAPRM138323). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.
Does South City Extension Phase 1 have a RERA bank account?
Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.
Where is South City Extension Phase 1 located?
South City Extension Phase 1 is registered in Shahjahanpur, as filed with UPRERA.
Data as reported by UPRERA, as of 21 Oct 2026. official source ↗