Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ357829
Project categoryResidential
Registration typeNew
RERA statusCompleted
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryLucknow Development Authority
Proposed start1 Jan 2019
Project duration57 months
AddressSarojini Nagar, Lucknow
TehsilSarojini Nagar
Applicant typeCompany
Applicant addressUnit No. 1201, 12th Floor, Tower T-2, Crescent Heights, Sultanpur Road, Sushant Golf City, Lucknow, Lucknow, Uttar Pradesh, India, 226030
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    42917

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. Completion certificate filed

  5. to

    Extension granted

    “Six months extension in view of force majeure caused by covid-19 pandemic”

  6. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  7. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Completed.
Quarterly report cadence
FY 2020-21
Q1Q2Q3Q4
FY 2021-22
Q1Q2Q3Q4
FY 2022-23
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered15 Feb 2019
Original completion31 Mar 2023
Revised completion30 Sept 2023
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary31 Dec 2021
Registration fee₹44,000
Sanctioning authorityLucknow Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors118 · 1 · 15 (units from plan)
  • 3 BHK60 51%
  • 2 BHK58 49%
ConfigurationUnitsCarpet area
2 BHK5875-79
3 BHK60111
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
Tower E1 · 2 BHK, 3 BHK1511875-111
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Design Forum International
License CA/2012/57857
K-47, Kailash Colony, New Delhi
Engineer
Er. Maqsud-e-Nazar
P.N. 25, Ground Floor, Pocket-2, Jasola, New Delhi
Contractor
Rishita Developers Pvt. Ltd.
116/117, Vibhuti Khand, Corronation Anand Tower, Lucknow
Sr.Development work declared to RERA
1Demarcation of Plots
This is single plot of rectangular shape , having total 3 no. of entry gate in which 1 main gate having grand entrance from the 45m wide front road and rest of 2 are secondary gates from 24 m wide road. Site is surronded by other plots on one side and 30m wide road.
2Boundary Wall
1.8 - 2.4m high and 200 mm thick Boundary wall designed . Concrete hollow block work and rcc work in column and beam may be used as per design. Entrance gates will be created at the main entrance .Steel Gates will used at secondary entrances
3Road Work
Paver/tremix based road will be created for all internal road works with concrete pavers at certain junction points.
4Footpaths
All internal roads will have 1.5m wide footpath in 40- 60 mm thick concrete pavers or equivalent finishes
5Water Supply Including Drinking Water Facilities
Underground Tank of 830 KL Capacity.
6Sewer System
Underground System using uPVC(SN-4) Sewer pipes.
7Drain
Underground System using uPVC(SN-4) pipes.
8Parks
There is one main central park between the towers with different recretional activities. There are more green parks by the boundary wall on two sides of the complex
9Tree Planting
"There are 3 type of trees povided in site which are Bahunia Blackena(12 no.), Phoenix Dactylifera(220 No.), Ficus Benjamina(218 No.)"
10Design For Electric Supply Including Street Lighting
Five nos. Transformers of 1600 KVA, 33 / 0.4 KV capacity each shall be used along with necessary switch-gear for distributing electricity at LT voltage. All street / landscape lighting shall be LED based & automatically controlled by astronomical timer and for energy saving, the same shall be selectively controlled by timer as per the time zone
11Community Buildings
Community activity area shall be provided at the site in central area which shall be accessed by all residents.
12Treatment and Disposal System of Sewage and Sullage water
STP of Capacity 720 KLD shall be provided. Treated water shall be used for Flushing, irrigation, carwash, pathway cleaning & excess water shall be discharged into the Municipal Sewer as per site.
13Solid Waste Management And Disposal System
There are a proper garbage collection area provided for the solid waste management.
14Water Conservation System
Rain Water Harvesting facilities shall be provided & treated sewage water shall be recycled to the extent feasible.
15Energy Management System Including Use of Renewable Energy
Solar panels shall be provided on terrace for renewable energy. Energy purchased from the grid/ power supply company & metering will be done as per electricity supply authority guideline.
16Fire Protection And Fire Safety System
Fire Tender path shall be provided as per NBC. Fire Fighting system along with pumps & water storage tanks shall be provided as per NBC & NOC from Fire Department.
17Social Infrastructure And Other Public Amenities Including Public Health Services
"Sewerage ,Storm water and water supply system shall be Provided. We have Proposed common Pump Room with Primary filteration, Transfer pumps to fill the domestic overhead tank. Water for domestic use & Flushing go down through gravity from domestic as well as flushing tanks. All Sewgage shall be go to the STP for recycling the water. Storm water for Roof,Roads and other area shall be connect to the Storm water drain channel and go to the Rain water harvesting Pit for recharge the Ground water and overflow shall be connect with Municiple drain."
18Emergency Evacuation Services
Balcony will also be used for evacuation.Assembly points areas will be demarcated for earthquake and other possible disasters
19Other Miscellaneous Work
Not Applicable
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Registered agents

46 agents

Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.

Sr.AgentRERA registration
1360 REALTORS LLPUPRERAAGT10868
2ABHISHEK KUMAR SINGHUPRERAAGT15288
3AMIT AGARWALUPRERAAGT11945
4AMIT KUMAR NISHADUPRERAAGT14016
5ANAND KUMAR SHUKLAUPRERAAGT10831
6ARADHYA REAL ESTATEUPRERAAGT13179
7ARCHANA GUPTAUPRERAAGT10881
8ASA FINCAP ADVISORS LLPUPRERAAGT10926
9ASHUTOSH KUMAR SINGHUPRERAAGT14912
10BRIXWELL REALTY & CONSTRUCTION LLPUPRERAAGT15068
11DAIWIK REALTORSUPRERAAGT12075
12GOLDEN ESTATEUPRERAAGT10397
13HITESH KHANNAUPRERAAGT13833
14INVESTORS CARE INFRATECH PVT LTDUPRERAAGT13542
15Karshni Buildwell Pvt LtdUPRERAAGT11401
16KAUSHTUBH REALTY PRIVET LIMITEDUPRERAAGT13025
17KONRAI OVERSEASUPRERAAGT14764
18M.S. ConsultantsUPRERAAGT10079
19M.S. Property Consultants L.L.P.UPRERAAGT10074
20Mukesh kumar SharmaUPRERAAGT11494
21Pankaj MittalUPRERAAGT13523
22PIXEL GLOBAL INFRA PRIVATE LIMITEDUPRERAAGT13936
23Raj Kumar UpadhyayUPRERAAGT10920
24RAM KUMAR TIWARIUPRERAAGT14400
25REALTYSTRUCTURE INFRATECH PRIVATE LIMITEDUPRERAAGT10144
26RELIVE SOLUTIONS PVT. LTD.UPRERAAGT10078
27Rishabh SaxenaUPRERAAGT13851
28RISHTA INFRABUILD PVT LTDUPRERAAGT15197
29Sachan Estate Pvt LtdUPRERAAGT10143
30SAIM AHMADUPRERAAGT15637
31SANJEEV KUMAR BANKAUPRERAAGT10894
32SANTOSH KUMARUPRERAAGT10156
33SDR INFRA BUILD PVT LTDUPRERAAGT11062
34SHRI RUDRA REAL ESTATESUPRERAAGT14251
35shrikant upadhyayUPRERAAGT15563
36SIDHA CONSTRUCTIONSUPRERAAGT11253
37SILVER EDGE REAL ESTATE SOLUTIONUPRERAAGT12168
38Smart InfraReality Private LimitedUPRERAAGT10057
39SMC Real Estate Advisors Private LimitedUPRERAAGT10113
40SMITA SINGHUPRERAAGT12566
41SQUARE YARDS CONSULTING PRIVATE LIMITEDUPRERAAGT10119
42TARUN PREET SINGH SAHNIUPRERAAGT12537
43Unnisis Infrratech Private LimitedUPRERAAGT15300
44VIKAS SINGHUPRERAAGT12163
45vikram Jeet Singh ChadhaUPRERAAGT10805
46WEALTH CLINIC PRIVATE LIMITEDUPRERAAGT10521
Agents as filed against this project. The grid does not say whether a registration is still valid, so no validity is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 22 Apr 2023.

Sanctioned by Lucknow Development Authority · 7,796 sqm of land · an approved plan of 1 block and 118 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
4291723 Apr 201822 Apr 202322 Apr 202631 Mar 2023
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 1 completion extension for this project, running to 30 Sept 2023.

#Granted fromExtended uptoNote
131 Mar 202330 Sept 2023Six months extension in view of force majeure caused by covid-19 pandemic

Land & documents

17 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
Part of G.H. I, Plot no SECTOR C, POCKET 67796.03Plot
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Registry document · 14152/18
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Sale deed · 1250
The registered deed by which the promoter bought the land.
PDF ↗
Document checklist
DocumentStatusUploaded
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
not reported—
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
not reported—
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New30 Jan 2019 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New26 Dec 2018 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New26 Dec 2018 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New30 Jan 2019 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New26 Dec 2018 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New30 Jan 2019 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New30 Jan 2019 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New30 Jan 2019 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New27 Dec 2018 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New28 Dec 2018 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New26 Dec 2018 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New26 Dec 2018 ↗

Quarterly progress reports

14 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

14 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2023-Q2.

QuarterConstructionCertificates
2020-Q1—CA ↗ · Arch ↗ · Eng ↗
2020-Q2—CA ↗ · Arch ↗ · Eng ↗
2020-Q3—CA ↗ · Arch ↗ · Eng ↗
2020-Q4—CA ↗ · Arch ↗ · Eng ↗
2021-Q1—CA ↗ · Arch ↗ · Eng ↗
2021-Q2—CA ↗ · Arch ↗ · Eng ↗
2021-Q3—CA ↗ · Arch ↗ · Eng ↗
2021-Q4—CA ↗ · Arch ↗ · Eng ↗
2022-Q1—CA ↗ · Arch ↗ · Eng ↗
2022-Q2—CA ↗ · Arch ↗ · Eng ↗
2022-Q3—CA ↗ · Arch ↗ · Eng ↗
2022-Q4—CA ↗ · Arch ↗ · Eng ↗
2023-Q1—CA ↗ · Arch ↗ · Eng ↗
2023-Q2—CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameRISHITA DEVELOPERS PRIVATE LIMITED
RolePromoter · current
RERA IDUPRERAPRM4294
PANAAECR1191G
CIN / TANU45201UP2008PTC035945
Name of chairmanSUDHIR KUMAR AGARWAL
Registered addressUnit No. 1201, 12th Floor, Tower T-2, Crescent Heights, Sultanpur Road, Sushant Golf City, Lucknow, Lucknow, Uttar Pradesh, India, 226030
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Lucknow

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.

AccountAs filed with RERA
Bank account as filed
RISHITA DEVELOPERS PVT LTDBankYES BANK LTD.BranchGOMTI NAGARA/C no.IFSCYESB0000611
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about Rishita Mulberry Heights Phase 1

Is Rishita Mulberry Heights Phase 1 RERA registered?

Yes. Rishita Mulberry Heights Phase 1 is registered with UPRERA under registration number UPRERAPRJ357829, registered on 15 Feb 2019. Estanzo reproduces that filing; it does not verify the work behind it.

Has Rishita Mulberry Heights Phase 1 been completed?

UPRERA lists Rishita Mulberry Heights Phase 1 as completed, with a completion certificate dated 31 Dec 2021, against a filed deadline of 30 Sept 2023.

Who is the builder of Rishita Mulberry Heights Phase 1?

RISHITA DEVELOPERS PRIVATE LIMITED is the promoter entity that filed Rishita Mulberry Heights Phase 1 with UPRERA (promoter RERA ID UPRERAPRM4294). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Has UPRERA granted Rishita Mulberry Heights Phase 1 more time to complete?

UPRERA's record carries 1 completion extension for Rishita Mulberry Heights Phase 1, the latest running to 30 Sept 2023. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does Rishita Mulberry Heights Phase 1 have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is Rishita Mulberry Heights Phase 1 located?

Rishita Mulberry Heights Phase 1 is registered in Lucknow, as filed with UPRERA.

What configurations are available in Rishita Mulberry Heights Phase 1?

The unit plan filed with UPRERA lists 2 BHK and 3 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in Rishita Mulberry Heights Phase 1?

The approved unit plan filed with UPRERA runs from 75 to 111 m² of carpet area (about 807 to 1,195 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in Rishita Mulberry Heights Phase 1?

The approved unit plan describes 1 block and 118 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is Rishita Mulberry Heights Phase 1?

About 61 units per acre: 118 planned units across 1.93 acres (7,796 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗