Registered31 Jul 2017
Promised30 Dec 2021
Revised29 Jun 2022
Today4 Aug 2026

Timeline

Promised completion30 Dec 2021
Revised completion29 Jun 2022
Actual completion
Possession delay49 mo delay

Registration & Cost Details

Registration fee (in ₹)₹50,000
Project cost (in ₹ Lakhs)₹8,000 Lakhs
Project duration84 months
Project categoryResidential
Locality
Original start date4 Jan 2017
Proposed start date4 Jan 2017

Inventory

Total units270
Unit TypeUnitsCarpet Area (sqm)
2 BHK22561.16–77.75
3 BHK4598

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile7081109839
Emailprasoon.shukla@urbanaxis.in
Coordinator7081104233
Address405-406,ELDECO CORPORATE TOWER,VIBHUTI KHAND,GOMTINAGAR,LUCKNOW-226010

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q1
2020-Q2
2020-Q3
2020-Q4
2021-Q1
2021-Q2
2021-Q3
2021-Q4
2022-Q1
2022-Q2
2022-Q3
2022-Q4
2023-Q1
2023-Q2
2023-Q3

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
3993416 Apr 201615 Apr 202130 Dec 202115 Apr 2024
39934

Revalidated: 39934 (16 Apr 2016)

16 Apr 201615 Apr 2021

Revalidated upto: 1 Jan 1900

30 Dec 202115 Apr 2024
39934

Revalidated: 39934 (1 Oct 2019)

16 Apr 201615 Apr 2021

Revalidated upto: 15 Apr 2024

29 Jun 202215 Apr 2024

Land Parcels

Khasra No.AreaPlot Type
GH-2 SECTOR-C, POCKET 7, SUSHANT GOLF CITY,ANSAL A6893Plot

Approved Unit Plan

Unit plan rows on file181
Total flats (sum of rows)270
BlocksTOWER B, TOWER C, Tower A
Floor types2 BHK, 3 BHK, OTHER

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of URBAN WOODS-I?

The RERA registration number of URBAN WOODS-I is UPRERAPRJ2696, as recorded on the UP-RERA portal.

What is the RERA status of URBAN WOODS-I?

As reported by UP-RERA, the status of URBAN WOODS-I is "Registered".

Where is URBAN WOODS-I located?

As reported to UP-RERA, URBAN WOODS-I is located at Mohanlalganj, Lucknow, Uttar Pradesh.

When will URBAN WOODS-I be completed?

The latest completion date reported to UP-RERA for URBAN WOODS-I is 29 Jun 2022.

Is URBAN WOODS-I delayed?

Measured against the latest completion date reported to UP-RERA, URBAN WOODS-I is 49 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026