1OAK NATURA

UPRERARegistered

1OAK NATURA is a RERA-registered residential project by ANGEL DWELLINGS PRIVATE LIMITED in Lucknow (RERA ID UPRERAPRJ132075). Registered with a completion deadline of 28 Jan 2026.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Jan–Mar 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q2'24
—Q3'24
—Q4'24
—Q1'25
—Q2'25
81.57%Q3'25
100%Q4'25
100%Q1'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ132075
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryLucknow Development Authority
Proposed start1 Feb 2020
Project duration72 months
AddressSarojini Nagar, Lucknow
TehsilSarojini Nagar
Applicant typeCompany
Applicant address43, Hewatt Road, Shakku Compound, Bhanmati Circle, Shivaji Marg Lucknow UP 226001
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Permit revalidated (2)

  2. 3 building permits sanctioned

  3. Registered with RERA

  4. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  5. to

    Extension granted

    “Six months extension in view of force majeure caused by covid-19 pandemic”

  6. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  7. to

    Extension granted

  8. Completion certificate filed

  9. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2020-21
Q1Q2Q3Q4
FY 2021-22
Q1Q2Q3Q4
FY 2022-23
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered30 Jan 2020
Original completion30 Jan 2024
Revised completion28 Jan 2026
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary16 Dec 2025
Registration fee₹82,500
Sanctioning authorityLucknow Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors272 · 3 · 15 (units from plan)
  • 3 BHK160 59%
  • 2 BHK108 40%
  • PENTHOUSE4 1%
ConfigurationUnitsCarpet area
3 BHK160120-131
2 BHK10877-89
PENTHOUSE4239-241
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
TOWER-A1 · 3 BHK, 2 BHK1413677-131
TOWER-A2 · 3 BHK, PENTHOUSE1554120-241
TOWER-A3 · 2 BHK, 3 BHK148284-120
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Praveen Kumar Patel
License CA/2012/54689
Janpath, Hazratganj, Lucknow
Engineer
Maqsud e Nazar
G-20, 2nd Floor, Jaswant Plaza, Near Kalindi Kunj, Main Sarita Vihar Road, Shaheen Bagh, Okhla, New Delhi-110025
Contractor
TILL YET NOT FINALIZED
TILL YET NOT FINALIZED
Sr.Development work declared to RERA
1Demarcation of Plots
This is a sold FSI plot, part of a larger group housing in an hi-tech township, having total 3 no.of entrances within the hi-tech township.
2Boundary Wall
1.8 - 2.1m high and 200 mm thick Boundary wall designed. AAC block work and rcc work in column and beam may be used as per design. Entrance gates will be created at the main entrance.
3Road Work
TRIMIX based road will be created for all internal road works with concrete pavers at certain junction points.
4Footpaths
All internal roads will have 0.75 m wide footpath in 40- 60 mm thick concrete pavers or equivalent finishes.
5Water Supply Including Drinking Water Facilities
As we have purchased FSI from Parent developer who is developing an hi-tech Township, So they will provide the water supply to the Plot. Ground water may also be used after taking approval from statuary departmen. Also end user shall be used their individual RO system as per their requirement. Overhead tanks shall be provided.
6Sewer System
Centralized Sewerage system shall be Provided. All Sewerage water shall be go to the township STP for treatment after treatment water shall be recycled and it will use in gardening and overflow from the STP shall be connect with the township sewerage system.
7Drain
Storm water system shall be Provided. Storm water from Roads and other landscape area shall be connected to the Storm water drain channel and go to the Rain water harvesting Pit for recharge the Ground water and overflow shall be connect with township drain.
8Parks
There is one central green between the towers with different recreational activities. There are more green patches in the hi-tech township
9Tree Planting
There are a number of trees provided in site along with the green areas and at certain peripheral walls.
10Design For Electric Supply Including Street Lighting
We have design the system as per local electricity Board and consider centralized Transformer,HT panel,LT Panel,Feeder Pillar and DG back for common service like External lighting, STP, Pump room etc.
11Community Buildings
Community activity area shall be provided which shall be accessed by all residents
12Treatment and Disposal System of Sewage and Sullage water
Centralized Sewerage system shall be Provided. All Sewerage water shall be go to the STP for treatment after treatment ,water shall be recycle and it will use in gardening and flushing system and overflow from the STP shall be connect with the Municipal.
13Solid Waste Management And Disposal System
There are a proper garbage collection area provided for the solid waste management.
14Water Conservation System
A well designed rain water harvesting system shall be provided for the whole building complex to conserve water
15Energy Management System Including Use of Renewable Energy
We will use LED lights fitting in external area. In STP and Pump room all the equipment shall have energy efficient motor.
16Fire Protection And Fire Safety System
Since the building is higher than 45m in height all the fire norms shall be followed as per NBC and approval of fire department.
17Social Infrastructure And Other Public Amenities Including Public Health Services
Sewerage, Storm water and water supply system shall be Provided. We have Proposed common Pump Room with Primary filtration, Transfer pumps to fill the domestic overhead tank. Water for domestic use & Flushing go down through gravity from domestic.
18Emergency Evacuation Services
Balcony will be used as refuge area for individuals apartment. Evacuation signage will be demarcated for earthquake and other possible disasters.
19Other Miscellaneous Work
As per Approved Map
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Registered agents

4 agents

Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.

Sr.AgentRERA registration
1ASA FINCAP ADVISORS LLPUPRERAAGT10926
2SeedWill Consulting Private LimitedUPRERAAGT15794
3SINAN REALTY LLPUPRERAAGT11785
4Smart InfraReality Private LimitedUPRERAAGT10057
Agents as filed against this project. The grid does not say whether a registration is still valid, so no validity is shown

Permits & extensions

3 permits

An approval and the date it runs to - not proof the work matching it was done.

3 sanctioning permits are on record with UPRERA, the latest valid to 11 Sept 2023. 2 of them carry a revalidation, the latest valid to 26 Jul 2026.

Sanctioned by Lucknow Development Authority · 15,418 sqm of land · an approved plan of 3 blocks and 272 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endRevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossaryDocuments filed
4301912 Sept 201811 Sept 202311 Sept 202630 Jan 2024—
4301912 Sept 201811 Sept 202313 May 202929 Jul 202412 Sept 2018
valid to 13 May 2026
4301912 Sept 201811 Sept 202326 Jul 202928 Jan 202612 Sept 2018
valid to 26 Jul 2026
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 2 completion extensions for this project, the latest running to 28 Jan 2026.

#Granted fromExtended uptoNote
130 Jan 202429 Jul 2024Six months extension in view of force majeure caused by covid-19 pandemic
229 Jul 202428 Jan 2026—

Land & documents

15 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
592, 593, 594, 597 & 59815417.69Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Registry document · 8559
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Khatauni extract · Reply to objection letter for registration
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Document checklist
DocumentStatusUploaded
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Electricity supply plan
How the project proposed to supply power, as filed at registration.
not reported—
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New2 Jan 2020 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New2 Jan 2020 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New2 Jan 2020 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New2 Jan 2020 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New2 Jan 2020 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New2 Jan 2020 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New17 Jan 2020 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New2 Jan 2020 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New2 Jan 2020 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New2 Jan 2020 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New2 Jan 2020 ↗

Quarterly progress reports

24 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

24 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2025-Q4.

QuarterConstructionCertificates
2020-Q1—CA ↗ · Arch ↗ · Eng ↗
2020-Q2—CA ↗ · Arch ↗ · Eng ↗
2020-Q3—CA ↗ · Arch ↗ · Eng ↗
2020-Q4—CA ↗ · Arch ↗ · Eng ↗
2021-Q1—CA ↗ · Arch ↗ · Eng ↗
2021-Q2—CA ↗ · Arch ↗ · Eng ↗
2021-Q3—CA ↗ · Arch ↗ · Eng ↗
2021-Q4—CA ↗ · Arch ↗ · Eng ↗
2022-Q1—CA ↗ · Arch ↗ · Eng ↗
2022-Q2—CA ↗ · Arch ↗ · Eng ↗
2022-Q3—CA ↗ · Arch ↗ · Eng ↗
2022-Q4—CA ↗ · Arch ↗ · Eng ↗
2023-Q1—CA ↗ · Arch ↗ · Eng ↗
2023-Q2—CA ↗ · Arch ↗ · Eng ↗
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q281.57%CA ↗ · Arch ↗ · Eng ↗
2025-Q3100%CA ↗ · Arch ↗ · Eng ↗
2025-Q4100%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2025-Q4. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameANGEL DWELLINGS PRIVATE LIMITED
RolePromoter · current
RERA IDUPRERAPRM106559
PANAAJCA9036C
CIN / TANU70102UP2011PTC046838
Name of chairmanAmritanshu Roy
Registered address43, Hewatt Road, Shakku Compound, Bhanmati Circle, Shivaji Marg Lucknow UP 226001
RERA contact
Registered since2019
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Lucknow

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.

AccountAs filed with RERA
Bank account as filed
ANGEL DWELLINGS PRIVATE LIMITEDBankINDUSIND BANKBranchVibhuti Khand, Gomtinagar LucknowA/C no.IFSCINDB0001028
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

2 movements

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Promoter’s complaints tally (all their projects)4 (Under Registration - 2 ) → 4 (Under Registration - 1 )
changed in Estanzo’s record
25 Sept 2026
Promoter’s complaints tally (all their projects)3 (Under Registration - 1 ) → 4 (Under Registration - 2 )
changed in Estanzo’s record
5 Sept 2026
When these facts last moved
Promoter’s complaints tally (all their projects)changed in Estanzo’s record · 25 Sept 2026 · 2 movements on record
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about 1OAK NATURA

Is 1OAK NATURA RERA registered?

Yes. 1OAK NATURA is registered with UPRERA under registration number UPRERAPRJ132075, registered on 30 Jan 2020. Estanzo reproduces that filing; it does not verify the work behind it.

Has 1OAK NATURA been completed?

UPRERA still lists 1OAK NATURA as Registered, so it is not shown as completed here. A completion certificate dated 16 Dec 2025 is on the record - RERA accepts these tower-wise, so one on file does not mean the whole project is complete.

Who is the builder of 1OAK NATURA?

ANGEL DWELLINGS PRIVATE LIMITED is the promoter entity that filed 1OAK NATURA with UPRERA (promoter RERA ID UPRERAPRM106559). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Has UPRERA granted 1OAK NATURA more time to complete?

UPRERA's record carries 2 completion extensions for 1OAK NATURA, the latest running to 28 Jan 2026. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does 1OAK NATURA have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is 1OAK NATURA located?

1OAK NATURA is registered in Lucknow, as filed with UPRERA.

What configurations are available in 1OAK NATURA?

The unit plan filed with UPRERA lists 3 BHK, 2 BHK and PENTHOUSE. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in 1OAK NATURA?

The approved unit plan filed with UPRERA runs from 77 to 241 m² of carpet area (about 825 to 2,591 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in 1OAK NATURA?

The approved unit plan describes 3 blocks and 272 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is 1OAK NATURA?

About 71 units per acre: 272 planned units across 3.81 acres (15,418 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗