Timeline Bar
Registered12 Aug 2017
Promised31 Mar 2019
Today4 Aug 2026
Timeline
Promised completion31 Mar 2019
Revised completion—
Actual completion—
Possession delay88 mo delay
Registration & Cost Details
Registration fee (in ₹)₹3,75,000
Project cost (in ₹ Lakhs)₹6,000 Lakhs
Project duration91 months
Project categoryCommercial
Locality—
Original start date28 Sept 2011
Proposed start date28 Sept 2011
Inventory
Total units—
Promoters & Contact
Contact Details
Applicant TypeCompany
Mobile9919623667
Emailcorrespondence.rera@gmail.com
Coordinator8960380119
AddressP. NO. - 16 , VILL- KHARGAPUR, CHINHAT, LUCKNOW LUCKNOW Lucknow UP 226028 IN
No promoter data available.
Land Parcels
| Khasra No. | Area | Plot Type |
|---|---|---|
| T-CB3/3 | VIBHUTI KHAND LUCKNOW | — |
Registry & Agreement Filings
| Registry Number | Registry Date | Land Type | Area |
|---|---|---|---|
| 9526 | 31 Oct 2005 | — | — |
Frequently Asked Questions
What is the RERA registration number of Rohtas summit?
The RERA registration number of Rohtas summit is UPRERAPRJ9331, as recorded on the UP-RERA portal.
What is the RERA status of Rohtas summit?
As reported by UP-RERA, the status of Rohtas summit is "Registered".
Where is Rohtas summit located?
As reported to UP-RERA, Rohtas summit is located at Lucknow, Lucknow, Uttar Pradesh.
When will Rohtas summit be completed?
The latest completion date reported to UP-RERA for Rohtas summit is 31 Mar 2019.
Is Rohtas summit delayed?
Measured against the latest completion date reported to UP-RERA, Rohtas summit is 88 months beyond that date.
Answers generated from this project's public UP-RERA record — data as reported by RERA.