Rudra Garden City Phase-2

UPRERARegistered

Rudra Garden City Phase-2 is a RERA-registered residential project by MM AGROTECH AND DEVELOPERS in Chandauli (RERA ID UPRERAPRJ165029). Registered with a completion deadline of 22 Nov 2026.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q3'24
—Q4'24
—Q1'25
—Q2'25
87.07%Q3'25
94%Q4'25
98.32%Q1'26
98.32%Q2'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ165029
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryVaranasi Development Authority
Proposed start1 Feb 2021
Project duration70 months
AddressARAZI NO.-512, MAUZA- GODHANA, PARGANA-DHUS DISTT.- CHANDAULI, MUGHALSARAI (DDU), Chandauli, Chandauli
TehsilChandauli
Applicant typePartnership Firm
Applicant addressRUDRA HOUSE C-27/273, C-13, INDIAN PRESS COLONY, MALDAHIYA, VARANASI 221001
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Permit revalidated (2)

  2. 3 building permits sanctioned

  3. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  4. Registered with RERA

  5. to

    Extension granted

  6. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  7. to

    Extension granted

  8. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2020-21
Q1Q2Q3Q4
FY 2021-22
Q1Q2Q3Q4
FY 2022-23
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered20 May 2021
Original completion1 Feb 2025
Revised completion22 Nov 2026
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹25,000
Sanctioning authorityVaranasi Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors80 · 1 · 11 (units from plan)
  • 3 BHK40 50%
  • 2 BHK40 50%
ConfigurationUnitsCarpet area
3 BHK4072-73
2 BHK4047-54
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
Block-C Tower-3 · OTHER, 3 BHK, 2 BHK118047-73
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Ravji Bajpai
License CA/2002/29796
Rudra House, 15/63, Civil Lines Opposite, green park stadium, Gate no.-2, Kanpur
Engineer
Maqsud e nazar
G-70, 2nd Floor, Jaswant Plaza, Near kalandi kunj, main sarita vihar road okhla, New Delhi, 110025
Contractor
BB REAL TECH. MR. PRADEEP TYAGI
207, Gali-01, Sarvodya nagar, Gaziabad, U.P.-201009
Sr.Development work declared to RERA
1Demarcation of Plots
This is single plot ploygon shaped, having total 1 no. of entry gate and 1 no. of exit gate from the 46m wide front road, site is surrounded by other plots of farmers form three sides.
2Boundary Wall
1.8-2.1 meter high and 200 mm thick boundary all designed. Brick work of 9 inch and rcc work in column and beam may be used as per design. MS board entrance and exit gate are developed with boundary.
3Road Work
Trimix road will be used as per design suggested by the architect for internal road.
4Footpaths
All internal road will have narrow footpath with matt finish tiles pavers or equivalent finishes.
5Water Supply Including Drinking Water Facilities
Ground water may also be used, also end user shall be used their individual RO system as per their requirement. Overhead tank shall be provide on building terrace for distribution through gravity.
6Sewer System
Centralized Sewerage system shall be provided. All sewerage water shall be go to the STP for treatment. after treatment, water shall be recycled and it will use in gardening, flush tanks nad vehicle washing, overflow form the STP shall be connect with the municipal sewerage system in future or a seasonal natural drain dunning along the site boundary.
7Drain
Strome water system shall be provided. Strome water shall from road and other landscape area shall be connect to the strom water drain channel and go to rain water harvesting pit for recharge the ground water and overflow shall be connect with municipal drain line.
8Parks
There are many green/ landscape area in front/ side of building including green parks, play area for the children and recreational activity.
9Tree Planting
There are different type of tree plantation is proposed at site in order to maintain greenery and natural view.
10Design For Electric Supply Including Street Lighting
We have design the system as per local electricity board and consider centralization transformer, HT penal, LT penal, feeder pillar and DG back for common service like external lighting , HTP, pump room etc.
11Community Buildings
Club house/community center id provide, swimming pool with sitting area and garden.
12Treatment and Disposal System of Sewage and Sullage water
Centralized sewerage system shall be provided . All sewerage water shall be go to STP for treatment, after treatment water shall be recycle and it will be use in gardening, flush tanks and vehicle washing, overflow from STP shall be connect with municipal sewerage system in future or A seasonal natural drain running along the site boundary.
13Solid Waste Management And Disposal System
There are a paper garbage collection area provide for the solid waste management.
14Water Conservation System
we have design rain water harvesting system shall be provided for the whole building complex to conserve water.
15Energy Management System Including Use of Renewable Energy
We will use LED light fitting in external area as well as solar light. In STP and pump room all the equipment shall have energy efficiency motor. Terrace will be provided with solar voltaic penal to provide renewable source of energy for common areas in building complex.
16Fire Protection And Fire Safety System
Since the building is less than 45m in height all the fire norms shall be followed as NBC and approval of fire department.
17Social Infrastructure And Other Public Amenities Including Public Health Services
Sewerage, storm water and water supply system shall be provided. we have proposed common pump room with the primary filtration, transfer to fill the domestic overhead tank. Water for domestic use and flushing go down through gravity from domestic as well as flushing tank. All sewerage shall be go to the STP gravity from domestic as well as flashing tanks. All sewerage shall be go to the STP for recycling the water. Strom water for roof, road and other area shall be connect to the storm water drain channel and go to the rain water harvesting pit for recharge the ground water and overflow shall be connect with municipal drain or a seasonal natural drain running along the site boundary.
18Emergency Evacuation Services
Fire staircase is provided in the each building, with fire resistant doors, basement have one access and exit in case of emergency.
19Other Miscellaneous Work
Luxurious entrance lobby in each block, convenience store for day to day small purchasing, lush green shrubs at every vacant space on ground.
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

3 permits

An approval and the date it runs to - not proof the work matching it was done.

3 sanctioning permits are on record with UPRERA, the latest valid to 22 Nov 2025. 2 of them carry a revalidation, the latest valid to 22 Nov 2028.

Sanctioned by Varanasi Development Authority · 3,903 sqm of land · an approved plan of 1 block and 80 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endRevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossaryDocuments filed
523 Nov 202022 Nov 202522 Nov 20281 Feb 2025—
Group Housing/05272/VDA/BP/25-26/0866/1612202523 Nov 202022 Nov 202522 Nov 202822 Nov 202523 Nov 2020
valid to 22 Nov 2028
Group Housing/05272/VDA/BP/25-26/0866/1612202523 Nov 202022 Nov 202522 Nov 202822 Nov 202523 Nov 2020
valid to 22 Nov 2028
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 2 completion extensions for this project, the latest running to 22 Nov 2026.

#Granted fromExtended uptoNote
11 Feb 202522 Nov 2025—
222 Nov 202522 Nov 2026—

Land & documents

15 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
Arazi No. - 512, Mauza-Godhana, Pargana - Dhus, Distt. Chandauli23010Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Registry document · 8267
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Khatauni extract · 1426-1431
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · Reply against objection received
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Registry document · 8979
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Khatauni extract · Partners Resolution
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · Affidavit- Form RA-1
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Registry document · 8260
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Document checklist
DocumentStatusUploaded
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New18 Mar 2021 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New18 Mar 2021 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New18 Mar 2021 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New18 Mar 2021 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New18 Mar 2021 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New18 Mar 2021 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New18 Mar 2021 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New18 Mar 2021 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New18 Mar 2021 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New8 Apr 2021 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New8 Apr 2021 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New8 Apr 2021 ↗

Quarterly progress reports

22 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

22 quarterly progress reports are on file with UPRERA, covering 2020-Q4 to 2026-Q1.

QuarterConstructionCertificates
2020-Q4—CA ↗ · Arch ↗ · Eng ↗
2021-Q1—CA ↗ · Arch ↗ · Eng ↗
2021-Q2—CA ↗ · Arch ↗ · Eng ↗
2021-Q3—CA ↗ · Arch ↗ · Eng ↗
2021-Q4—CA ↗ · Arch ↗ · Eng ↗
2022-Q1—CA ↗ · Arch ↗ · Eng ↗
2022-Q2—CA ↗ · Arch ↗ · Eng ↗
2022-Q3—CA ↗ · Arch ↗ · Eng ↗
2022-Q4—CA ↗ · Arch ↗ · Eng ↗
2023-Q1—CA ↗ · Arch ↗ · Eng ↗
2023-Q2—CA ↗ · Arch ↗ · Eng ↗
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q287.07%CA ↗ · Arch ↗ · Eng ↗
2025-Q394%CA ↗ · Arch ↗ · Eng ↗
2025-Q498.32%CA ↗ · Arch ↗ · Eng ↗
2026-Q198.32%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameMM AGROTECH AND DEVELOPERS
RolePromoter · current
RERA IDUPRERAPRM12024
PANAFMPA0333B
CIN / TANALDM02558D
Registered addressRUDRA HOUSE C-27/273, C-13, INDIAN PRESS COLONY, MALDAHIYA, VARANASI 221001
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Chandauli

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
MM AGROTECH -COLL. A/C FOR RUDRA GARDEN CITY PH IIBankState Bank of IndiaBranchSPL COMMERICAL BRANCH VARANASIBranch addressSME BRANCH, CLUB ROAD, VARANASI 221002Branch districtVaranasi, Uttar PradeshA/C no.IFSCSBIN0009252Branch emailsbi.09252@sbi.co.in
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
MM AGROTECH AND DEVELOPERSBankState Bank of IndiaBranchSME BranchBranch addressClub road, Varanadsi-221002Branch districtVaranasi, Uttar PradeshA/C no.IFSCSBIN0009252
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
MM AGROTECH-RERA TRANS A/c FOR RUDRA GARDEN CITY PH IIBankState Bank of IndiaBranchSPL COMMERICAL BRANCH VARANASIBranch addressSME BRANCH, CLUB ROAD, VARANASI 221002Branch districtVaranasi, Uttar PradeshA/C no.IFSCSBIN0009252Branch emailsbi.09252@sbi.co.in
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about Rudra Garden City Phase-2

Is Rudra Garden City Phase-2 RERA registered?

Yes. Rudra Garden City Phase-2 is registered with UPRERA under registration number UPRERAPRJ165029, registered on 20 May 2021. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for Rudra Garden City Phase-2?

The completion date filed with UPRERA is 22 Nov 2026. No completion certificate is on record yet.

Who is the builder of Rudra Garden City Phase-2?

MM AGROTECH AND DEVELOPERS is the promoter entity that filed Rudra Garden City Phase-2 with UPRERA (promoter RERA ID UPRERAPRM12024). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Has UPRERA granted Rudra Garden City Phase-2 more time to complete?

UPRERA's record carries 2 completion extensions for Rudra Garden City Phase-2, the latest running to 22 Nov 2026. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does Rudra Garden City Phase-2 have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is Rudra Garden City Phase-2 located?

Rudra Garden City Phase-2 is registered in Chandauli, as filed with UPRERA.

What configurations are available in Rudra Garden City Phase-2?

The unit plan filed with UPRERA lists OTHER, 3 BHK and 2 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in Rudra Garden City Phase-2?

The approved unit plan filed with UPRERA runs from 47 to 73 m² of carpet area (about 509 to 789 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in Rudra Garden City Phase-2?

The approved unit plan describes 1 block and 80 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is Rudra Garden City Phase-2?

About 83 units per acre: 80 planned units across 0.96 acres (3,903 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗