Timeline Bar
Registered29 Dec 2021
Completed13 Sept 2024
Promised12 Oct 2025
Timeline
Promised completion12 Oct 2025
Revised completion12 Oct 2025
Actual completion13 Sept 2024
Possession delayOn time
Registration & Cost Details
Registration fee (in ₹)₹2,53,000
Project cost (in ₹ Lakhs)₹5,804 Lakhs
Project duration55 months
Project categoryCommercial
Locality—
Original start date—
Proposed start date1 Apr 2021
Inventory
Total units628
| Unit Type | Units | Carpet Area (sqm) |
|---|---|---|
| 1 BHK | 364 | 28.11–34.01 |
| SHOP | 18 | 14.98 |
| OTHER | 246 | 20.47 |
Promoters & Contact
Contact Details
Applicant TypeCompany
Mobile9919164164
Emailcoordination@emaar-india.com
Coordinator9919164164
AddressEmaar MGF Land Ltd., Gomti Greens, Sector-7, Amar Shaheed Path, Near Suda office, Gomti Nagar Extension, LUCKNOW-226002
No promoter data available.
Quarterly Progress Reports
Permit & Extension History
| Permit Number | Permit Date | Valid Upto | Revised End Date | Extended Upto |
|---|---|---|---|---|
| 37158 | 31 Dec 2020 | 12 Oct 2025 | 12 Oct 2025 | 12 Oct 2026 |
Land Parcels
| Khasra No. | Area | Plot Type |
|---|---|---|
| 168 | 3800 | Khasra |
| 169 | 6610 | Khasra |
| 174 | 2460 | Khasra |
| 167 | 2950 | Khasra |
Approved Unit Plan
Unit plan rows on file183
Total flats (sum of rows)628
Total shops18
BlocksE1, E2, E3, E6, TowerA, TowerB
Floor types1 BHK, SHOP, OTHER
Individual floor/unit rows are not listed here.
Frequently Asked Questions
What is the RERA registration number of SAMARTH at Emaar Gomti Greens?
The RERA registration number of SAMARTH at Emaar Gomti Greens is UPRERAPRJ221843, as recorded on the UP-RERA portal.
What is the RERA status of SAMARTH at Emaar Gomti Greens?
As reported by UP-RERA, the status of SAMARTH at Emaar Gomti Greens is "Registered".
Where is SAMARTH at Emaar Gomti Greens located?
As reported to UP-RERA, SAMARTH at Emaar Gomti Greens is located at Sarojini Nagar, Lucknow, Uttar Pradesh.
Is SAMARTH at Emaar Gomti Greens completed?
As reported to UP-RERA, SAMARTH at Emaar Gomti Greens was completed on 13 Sept 2024.
Is SAMARTH at Emaar Gomti Greens delayed?
Measured against the latest completion date reported to UP-RERA, SAMARTH at Emaar Gomti Greens is on time.
Answers generated from this project's public UP-RERA record — data as reported by RERA.
Data as reported by RERA. View source · Scraped 3 Aug 2026