SCC BLOSSOM BLOCK A AND B

UPRERARegistered

SCC BLOSSOM BLOCK A AND B is a RERA-registered residential project by SCC BUILDERS PVT. LTD. in Noor Nagar, Raj Nagar Extension, Ghaziabad (RERA ID UPRERAPRJ260266). Registered with a completion deadline of 20 Mar 2029.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q3'24
—Q4'24
—Q1'25
—Q2'25
16.69%Q3'25
20.18%Q4'25
21.99%Q1'26
25.91%Q2'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ260266
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryGhaziabad Development Authority
Proposed start1 Sept 2024
Project duration55 months
AddressKHASRA NO. 1179 & 1180,, Noor Nagar, Raj Nagar Extension, Ghaziabad, Ghaziabad
TehsilGhaziabad
Applicant typeCompany
Applicant address3RD FLOOR H-69, SECTOR-63, NOIDA-201301, GAUTAMBUDH NAGAR ( UP)
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    Group Housing/03499/GDA/BP/21-22/1570/29072022

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered14 Sept 2024
Original completion20 Mar 2029
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹29,000
Sanctioning authorityGhaziabad Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors189 · 2 · 19 (units from plan)
  • 3 BHK91 48%
  • 4 BHK80 42%
  • 2 BHK18 10%
ConfigurationUnitsCarpet area
4 BHK80118
2 BHK1846
3 BHK9146-95
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
Block A · 4 BHK1680118
Block B · 2 BHK, 3 BHK1910946-95
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
ANUJ AGARWAL ARCHITECTS
License CA/96/19503
A-244, KAUSHAMBI, GHAZIABAD,UTTAR PRADESH-201010
Engineer
V D SHARMA
B-24,SECTOR-67, NOIDA, 201301
Contractor
S.C.C. BUILDERS PRIVATE LIMITED
SCC BIZZ PLAZA, H-69,SECTOR-63, NOIDA,201301, INDIA
Sr.Development work declared to RERA
1Demarcation of Plots
North-30meter wide road, South- 24-Meter-Wide road (Proposed as per GDA master plan) , East- Khasra no. 1178 and West- Khasra no. 1181
2Boundary Wall
10 Feet height boundry wall of RCC/Column and Brick work as per Drawings
3Road Work
all internals roads in the project will be combination of concrete pavers of different shapes, colours/interlocking tiles/ Cement Concrete as per design.
4Footpaths
Footpaths will be developed with interlocking tiles as per design.
5Water Supply Including Drinking Water Facilities
Water supply will be provided to individuals flats from the overhead tanks. The water will be lifted to overhead tanks from the underground tanks through adequate pumping system. source will be connection from the concerned authority.
6Sewer System
Internal sewerage system pipeline will be developed as per drawing and the same will connected to project STP for treatment/GDA Sewer Line Connection.
7Drain
Internal network of drainage will be developed as per drawing.
8Parks
Parks will be developed in 10 percent of the project Land i.e. Green Area as per the sanctioned layout .
9Tree Planting
Tree plantation will be done along the project boundary and in green area as per the sanctioned letter.
10Design For Electric Supply Including Street Lighting
Electricity system of the project will be developed for supply electricity to individual flat and for common areas. Adequate streetlights will be provided in the common areas. whereas electricity connection provided directly by UPPCL.
11Community Buildings
NA
12Treatment and Disposal System of Sewage and Sullage water
The sewerage will be treated internally in the STP installed in the project.
13Solid Waste Management And Disposal System
Solid waste generated in the project will be treated/processed in solid waste plant installed in the project.
14Water Conservation System
Rain water harvesting pits/system will be provided as per the sanctioned plan.
15Energy Management System Including Use of Renewable Energy
External electrification syustem will be developed in the project by Promoter but electricity supply will be provided by UPPCL to individual flat as well as common area and services. The power will be supplied by the UPPCL by directly to flat owner and common area.
16Fire Protection And Fire Safety System
Requisite Fire protection system will be installed as per the terms of the Fire NOC granted by Fire Department.
17Social Infrastructure And Other Public Amenities Including Public Health Services
Multipurpose Hall, Dedicated Area for Gym, Kids Play area within the 10 percent of Project, Area For indoor Games will be Provided.
18Emergency Evacuation Services
Fire staircases will be provided as per the approved Maps for evacuation to open areas.
19Other Miscellaneous Work
As per project requirements.
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Registered agents

1 agent

Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.

Sr.AgentRERA registration
1infrabrick india pvt ltdUPRERAAGT21343
Agents as filed against this project. The grid does not say whether a registration is still valid, so no validity is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 20 Mar 2029.

Sanctioned by Ghaziabad Development Authority · 4,703 sqm of land · an approved plan of 2 blocks and 189 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
Group Housing/03499/GDA/BP/21-22/1570/2907202221 Mar 202420 Mar 202920 Mar 202920 Mar 2029
Plans and approvals filed with RERA
DocumentFile
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
no file published
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
no file published
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗

Land & documents

24 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
1179 and 118014800Khasra
11802530Khasra
1179 and 118014800Khasra
11802530Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Sale deed · 172
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 173
The registered deed by which the promoter bought the land.
PDF ↗
Khatauni extract · 1421-1426
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1421-26
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Document checklist
DocumentStatusUploaded
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
not reported—
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
not reported—
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
not reported—
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
not reported—
Agreement for sale (proforma)
The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New7 Aug 2024 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New27 Jul 2024 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New27 Jul 2024 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New27 Jul 2024 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New27 Jul 2024 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New27 Jul 2024 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New27 Jul 2024 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New27 Jul 2024 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New8 Sept 2024 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New10 Sept 2024 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New27 Jul 2024 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New27 Jul 2024 ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
New7 Aug 2024 ↗
Agreement for sale (proforma)
The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind.
New7 Aug 2024 ↗

Quarterly progress reports

8 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

8 quarterly progress reports are on file with UPRERA, covering 2024-Q2 to 2026-Q1.

QuarterConstructionCertificates
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q216.69%CA ↗ · Arch ↗ · Eng ↗
2025-Q320.18%CA ↗ · Arch ↗ · Eng ↗
2025-Q421.99%CA ↗ · Arch ↗ · Eng ↗
2026-Q125.91%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameSCC BUILDERS PVT. LTD.
RolePromoter · current
RERA IDUPRERAPRM2347
PANAAJCS3238G
CIN / TANU45201DL2005PTC139039
Name of chairmanMR. VIPUL GIRI
Registered address3RD FLOOR H-69, SECTOR-63, NOIDA-201301, GAUTAMBUDH NAGAR ( UP)
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Ghaziabad

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
SCC BUIDERS PVT LTD SCC BLOSSOM COLLECTION ACCOUNT BLOCK A & BBankPUNJAB & SIND BANKBranchKAUSHAMBI BRANCHBranch addressSHOP NO.-14A, NEAR WAVE CINEMA, KAUSHAMBI GHAZIBADBranch districtGhaziabad, Uttar PradeshA/C no.IFSCPSIB0021226Branch emailK1226@PSB.CO.IN
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
SCC BUILDERS PVT LTD SCC BLOSSOM SEPARATE ACCOUNT BLOCK A AND BBankPUNJAB AND SIND BANKBranchKAUSHAMBI BRANCHBranch addressSHOP NO.- 14A, NEAR WAVE CINEMA, KAUSHAMBI, GHAZIABAD,U. P.201010Branch districtGhaziabad, Uttar PradeshA/C no.IFSCPSIN0021226
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
SCC BUILDERS PVT LTD SCC BLOSSOM TRANSACTION ACCOUNT BLOCK A AND BBankPUNJAB AND SIND BANKBranchKAUSHAMBI BRANCHBranch addressSHOP NO.-14A, NEAR WAVE CINEMA, KAUSHAMBI, GHAZIABAD, U.P. ,201010Branch districtGhaziabad, Uttar PradeshA/C no.IFSCPSIB0021226
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about SCC BLOSSOM BLOCK A AND B

Is SCC BLOSSOM BLOCK A AND B RERA registered?

Yes. SCC BLOSSOM BLOCK A AND B is registered with UPRERA under registration number UPRERAPRJ260266, registered on 14 Sept 2024. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for SCC BLOSSOM BLOCK A AND B?

The completion date filed with UPRERA is 20 Mar 2029. No completion certificate is on record yet.

Who is the builder of SCC BLOSSOM BLOCK A AND B?

SCC BUILDERS PVT. LTD. is the promoter entity that filed SCC BLOSSOM BLOCK A AND B with UPRERA (promoter RERA ID UPRERAPRM2347). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does SCC BLOSSOM BLOCK A AND B have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is SCC BLOSSOM BLOCK A AND B located?

SCC BLOSSOM BLOCK A AND B is registered in Noor Nagar, Raj Nagar Extension, Ghaziabad, as filed with UPRERA.

What configurations are available in SCC BLOSSOM BLOCK A AND B?

The unit plan filed with UPRERA lists 4 BHK, 2 BHK and 3 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in SCC BLOSSOM BLOCK A AND B?

The approved unit plan filed with UPRERA runs from 46 to 118 m² of carpet area (about 498 to 1,267 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in SCC BLOSSOM BLOCK A AND B?

The approved unit plan describes 2 blocks and 189 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is SCC BLOSSOM BLOCK A AND B?

About 163 units per acre: 189 planned units across 1.16 acres (4,703 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗