Estanzo

Timeline Bar

Registered30 Aug 2022
Today3 Aug 2026
Promised20 Apr 2027

Timeline

Promised completion20 Apr 2027
Revised completion20 Apr 2027
Actual completion
Possession delayOn time

Registration & Cost Details

Registration fee (in ₹)₹3,44,000
Project cost (in ₹ Lakhs)₹3,149 Lakhs
Project duration58 months
Project categoryResidential
Locality
Original start date
Proposed start date1 Jul 2022

Inventory

Total units

Promoters & Contact

Contact Details

Applicant TypeCompetent authority
Mobile9568006403
Emailblyda@nic.in
Coordinator9568006434
AddressVikas Jyoti Complex, Pyiyadarshini Nagar, Bareilly - 243122

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2022-Q2
2022-Q3
2022-Q4
2023-Q1
2023-Q2
2023-Q3
2023-Q4
2024-Q1
2024-Q2
2024-Q3
2024-Q4
2025-Q1
2025-Q278.8%
2025-Q389.3%
2025-Q491.9%
2026-Q193.7%

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
BDA/RGN/SEC-7(PART-2)/1321 Apr 202220 Apr 202720 Apr 202720 Apr 2030

Land Parcels

Khasra No.AreaPlot Type
30P, 44, 45, 46, 47, 49, 126, 130, 132, 133, 139, 144, 146, 147, 149, 150, 15367706Khasra

Frequently Asked Questions

What is the RERA registration number of SECTOR-7 (PART-2) RAMGANGA NAGAR YOJNA?

The RERA registration number of SECTOR-7 (PART-2) RAMGANGA NAGAR YOJNA is UPRERAPRJ951799, as recorded on the UP-RERA portal.

What is the RERA status of SECTOR-7 (PART-2) RAMGANGA NAGAR YOJNA?

As reported by UP-RERA, the status of SECTOR-7 (PART-2) RAMGANGA NAGAR YOJNA is "Registered".

Where is SECTOR-7 (PART-2) RAMGANGA NAGAR YOJNA located?

As reported to UP-RERA, SECTOR-7 (PART-2) RAMGANGA NAGAR YOJNA is located at Bareilly, Bareilly, Uttar Pradesh.

When will SECTOR-7 (PART-2) RAMGANGA NAGAR YOJNA be completed?

The latest completion date reported to UP-RERA for SECTOR-7 (PART-2) RAMGANGA NAGAR YOJNA is 20 Apr 2027.

Is SECTOR-7 (PART-2) RAMGANGA NAGAR YOJNA delayed?

Measured against the latest completion date reported to UP-RERA, SECTOR-7 (PART-2) RAMGANGA NAGAR YOJNA is on time.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026