Shivalik Akshay

UPRERARegistered

Shivalik Akshay is a RERA-registered residential project by Galaxy Real Estate Developers And Builders Pvt.Ltd in Kanpur Nagar (RERA ID UPRERAPRJ141252). Registered with a completion deadline of 31 Dec 2026.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q3'24
—Q4'24
—Q1'25
—Q2'25
54%Q3'25
54%Q4'25
54%Q1'26
54%Q2'26

Construction stayed at 54% across 4 consecutive filed quarters (Jul–Sep 2025 to Apr–Jun 2026). The promoter filed the same figure each time. Quarters with no percentage filed are not counted either way.

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ141252
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryKanpur Development Authority
Proposed start8 Aug 2020
Project duration77 months
AddressKanpur, Kanpur Nagar
TehsilKanpur
Applicant typeCompany
Applicant address12/483, Macroberts Ganj, Near Society Motors, Kanpur-208001
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    14/Bhawan/Online/2019-20

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2020-21
Q1Q2Q3Q4
FY 2021-22
Q1Q2Q3Q4
FY 2022-23
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered1 Oct 2020
Original completion31 Dec 2026
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹36,000
Sanctioning authorityKanpur Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors188 · 3 · 15 (units from plan)
Homes · commercial units185 · 3 (shops and offices filed in the same plan)
  • 2 BHK141 75%
  • 3 BHK40 21%
  • OTHER4 2%
  • SHOP3 2%
ConfigurationUnitsCarpet area
SHOP313-14
3 BHK4098-104
2 BHK14157-59
OTHER457-59
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
A · SHOP, 3 BHK124313-104
B · 2 BHK, OTHER147157-59
C · 2 BHK, OTHER147457-59
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Ar. Vijai Prakash Gupta
License C.O.A. No. 93/16574
12/483, Mac-Roberts Ganj, Kanpur
Engineer
Er. Arvind Garg
Techpro Engineers Pvt Ltd 103, Ratandham Apartment 12/483, Mc-Roberts Ganj, Kanpur
Contractor
Vinamra Constructions
12/483, 4th Floor MAC-Roberts Ganj, Kanpur UP
Sr.Development work declared to RERA
1Demarcation of Plots
We have one plot of size 6140 sq.mtr, having one main entrance gate from the 30 m wide front road.
2Boundary Wall
2 m high and 230 mm thick brick work rcc work in column and beam. at the centre face of the boundary wall there would be a logo of SHIVALIK AKSHAY which give a beautiful iconic design to boundary wall.
3Road Work
from the main entrance gate we have 80mm thick interlocking brick/rcc road throughout the project.whose wideness starts from 10 m.
4Footpaths
we would not provide any footpath.
5Water Supply Including Drinking Water Facilities
we will provide two nos. of pump for the requirement of blocks, through underground pipelines.
6Sewer System
modular sewage system shall be provided.all sewage water shall be go to the STP and overflow from the STP shall be connect to the municipal sewage system when come into force.
7Drain
storm water shall be provided. storm water form the roads and other landscape area shall be connect to the storm water drain channel and go to the rain water harvesting pit for recharge the ground water and overflow shall be connected to the municipal drain line.
8Parks
we will provide with the green area different activities and green area will have gaming activities for kids.
9Tree Planting
we will provide many types of trees along the boundary wall and the green area.
10Design For Electric Supply Including Street Lighting
we will design and implement the system according to the local electricity board and will consider centralized transformer, ht panel , lt panel and feeder pillar and dg back for common service like external lightning ,fountain, stp . pump room. etc.
11Community Buildings
NA
12Treatment and Disposal System of Sewage and Sullage water
modular sewage system shall be provided . all sewage water shall be go to the STP. and overflow from the stp shall be connect with the municipal sewage system when come into force.
13Solid Waste Management And Disposal System
there is a proper garbage collection area provided for the solid waste management.
14Water Conservation System
we will suggest to individuals to use low flow fixtures as well as dual flush cistern and raw water harvesting system to reduce the water consumption and improve the ground water level .
15Energy Management System Including Use of Renewable Energy
we will use energy light fittings in the external area as well as solar lights. in the pump room also all the equipment shall have energy efficient motor. and we will suggest the individual also to use.
16Fire Protection And Fire Safety System
this project only has residential flats.hence we will provide fire fighting facilities in the common area while individual owner can install their own system as per their and local authorities requirement.
17Social Infrastructure And Other Public Amenities Including Public Health Services
NA
18Emergency Evacuation Services
we have proposed common pump room all sewage shall be go to the stp. road sand other area shall be connected to the storm water drain channel and go to the rainwater.
19Other Miscellaneous Work
NA
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 6 Aug 2025.

Sanctioned by Kanpur Development Authority · 6,140 sqm of land · an approved plan of 3 blocks and 188 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
14/Bhawan/Online/2019-207 Aug 20206 Aug 20256 Aug 202831 Dec 2026
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗

Land & documents

14 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
317(P) and 318(P)6140Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Sale deed · 2613
The registered deed by which the promoter bought the land.
PDF ↗
Sale deed · 2613
The registered deed by which the promoter bought the land.
PDF ↗
Document checklist
DocumentStatusUploaded
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New31 Aug 2020 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New31 Aug 2020 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New31 Aug 2020 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New31 Aug 2020 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New31 Aug 2020 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New10 Sept 2020 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New10 Sept 2020 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New31 Aug 2020 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New31 Aug 2020 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New2 Sept 2020 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New2 Sept 2020 ↗

Quarterly progress reports

25 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

25 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2026-Q1.

QuarterConstructionCertificates
2020-Q1—CA ↗ · Arch ↗ · Eng ↗
2020-Q2—CA ↗ · Arch ↗ · Eng ↗
2020-Q3—CA ↗ · Arch ↗ · Eng ↗
2020-Q4—CA ↗ · Arch ↗ · Eng ↗
2021-Q1—CA ↗ · Arch ↗ · Eng ↗
2021-Q2—CA ↗ · Arch ↗ · Eng ↗
2021-Q3—CA ↗ · Arch ↗ · Eng ↗
2021-Q4—CA ↗ · Arch ↗ · Eng ↗
2022-Q1—CA ↗ · Arch ↗ · Eng ↗
2022-Q2—CA ↗ · Arch ↗ · Eng ↗
2022-Q3—CA ↗ · Arch ↗ · Eng ↗
2022-Q4—CA ↗ · Arch ↗ · Eng ↗
2023-Q1—CA ↗ · Arch ↗ · Eng ↗
2023-Q2—CA ↗ · Arch ↗ · Eng ↗
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q254%CA ↗ · Arch ↗ · Eng ↗
2025-Q354%CA ↗ · Arch ↗ · Eng ↗
2025-Q454%CA ↗ · Arch ↗ · Eng ↗
2026-Q154%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameGalaxy Real Estate Developers And Builders Pvt.Ltd
RolePromoter · current
RERA IDUPRERAPRM4793
PANAACCG5726G
CIN / TANU70102UP2005PTC031098
Name of chairmanSanjai Kumar Jain
Registered address12/483, Macroberts Ganj, Near Society Motors, Kanpur-208001
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Kanpur Nagar

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
Galaxy Real Estate Collection AC For Shivalik AkshayBankIndian BankBranchKanpur Swarup NagarBranch addressSwarup Nagar, KanpurBranch districtKanpur Nagar, Uttar PradeshA/C no.IFSCIDIB000S810
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
Galaxy Real Estate Dev. and Builders Pvt Ltd RERA Designated AC Shivalik AkshayBankState Bank of IndiaBranchEmrald BranchBranch addressTilak Nagar Rave-3 Kanpur UPBranch districtKanpur Nagar, Uttar PradeshA/C no.IFSCSBIN0030283
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
Galaxy Real Estate Developers and Build ers Private LimitedBankIndian BankBranchKanpur Swarup NagarBranch addressSwarup Nagar, KanpurBranch districtKanpur Nagar, Uttar PradeshA/C no.IFSCIDIB000S810
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about Shivalik Akshay

Is Shivalik Akshay RERA registered?

Yes. Shivalik Akshay is registered with UPRERA under registration number UPRERAPRJ141252, registered on 1 Oct 2020. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for Shivalik Akshay?

The completion date filed with UPRERA is 31 Dec 2026. No completion certificate is on record yet.

Who is the builder of Shivalik Akshay?

Galaxy Real Estate Developers And Builders Pvt.Ltd is the promoter entity that filed Shivalik Akshay with UPRERA (promoter RERA ID UPRERAPRM4793). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does Shivalik Akshay have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is Shivalik Akshay located?

Shivalik Akshay is registered in Kanpur Nagar, as filed with UPRERA.

What configurations are available in Shivalik Akshay?

The unit plan filed with UPRERA lists SHOP, 3 BHK, 2 BHK and OTHER. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in Shivalik Akshay?

The approved unit plan filed with UPRERA runs from 13 to 104 m² of carpet area (about 143 to 1,118 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in Shivalik Akshay?

The approved unit plan describes 3 blocks and 188 units of which 185 are homes and 3 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is Shivalik Akshay?

About 124 units per acre: 188 planned units across 1.52 acres (6,140 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.