SHREE VINAYAKAM ARADHYA

UPRERARegistered

SHREE VINAYAKAM ARADHYA is a RERA-registered residential project by SHAKUNTALAM INFRADEVELOPERS LIMITED in Varanasi (RERA ID UPRERAPRJ423217). Registered with a completion deadline of 2 Dec 2027.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q4'24
—Q1'25
—Q2'25
58.83%Q3'25
66.21%Q4'25
75.23%Q1'26
80.39%Q2'26
—Q3'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ423217
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryVaranasi Development Authority
Proposed start1 Feb 2023
Project duration59 months
AddressVaranasi, Varanasi
TehsilVaranasi
Applicant typeCompany
Applicant addressB.38/47-K-8-H, Gokul Nagar Colony, Mahmoorganj, Varanasi-221010 (U.P.)
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    Group Housing/01171/VDA/BP/21-22/0191/17022022

  2. Registered with RERA

  3. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2022-23
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered17 Jan 2023
Original completion2 Dec 2027
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹50,000
Sanctioning authorityVaranasi Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors252 · 3 · 16 (units from plan)
Homes · commercial units248 · 4 (shops and offices filed in the same plan)
  • 2 BHK131 52%
  • 3 BHK117 46%
  • SHOP4 2%
ConfigurationUnitsCarpet area
3 BHK11787-130
2 BHK13155-88
SHOP415-15
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
Block A / RIDDHI · 3 BHK, 2 BHK1517674-130
Block B / SIDDHI · 2 BHK97255-58
Block D · SHOP1415-15
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
CHAHAT MEHROTRA
License CA/2022/148424
SHIV NIWAS, B.D. KAPOOR MARG, ARYA NAGAR SITAPUR, UTTAR PRADESH-261001
Engineer
SANJEEV KUMAR GUPTA
A-1, VIRAT VILLA, MAHMOORGANJ, VARANASI-221010
Contractor
ABHISHEKH SINGH
KADIPUR, VARANASI UTTAR PRADESH-221116
Sr.Development work declared to RERA
1Demarcation of Plots
South West-25.284729-82.916901 to North West-25.286823-82.916718, South East-25.284748-82.916991 to North East-25.286819-82.917187
2Boundary Wall
Boundry wall will have 2.2 meter hight with RCC Frame structure(Required RCC Columns and Beams). Designed boundry wall will have 125mm Brick work, both side plaster and good quality weather coat paint.
3Road Work
7.5 meter internal CC Road thickness 150 mm around the towers as per designed given by our architect.
4Footpaths
Footpaths will have pavers/tiles or equivalent finish
5Water Supply Including Drinking Water Facilities
Two numbers of borewell with overhead tanks. We will be providing fresh water supply direct and tank water supply in all flats through overhead tanks.
6Sewer System
Sewerage system shall be provided. All sewerage water shall be go to the STP for treatment after treatment recycled water will be use in gardening flushing and washing of vehicles, rest recycled water will be attached in sewerage line.
7Drain
Drain water along with boundry wall and will be attached in rain water harvesting system
8Parks
There will be provided green landscape area including green park, play area for children and different activities.
9Tree Planting
Different type of tree plantation are proposed around the towers
10Design For Electric Supply Including Street Lighting
Street light shall be provided and electric will be supply through separate electrical transformers
11Community Buildings
Club House / Community Building will be provided
12Treatment and Disposal System of Sewage and Sullage water
STP will be provided as per design.
13Solid Waste Management And Disposal System
Generated solid waste shall be segregated and collected on common solid waste garbage bins at site, from where it will be transported by municipal corporation for there treatment and disposal
14Water Conservation System
Rain water harvesting (RWH) system shall be provided
15Energy Management System Including Use of Renewable Energy
Solar panels on terrace will be provided for common area.
16Fire Protection And Fire Safety System
Entire fire safety system shall be provided as per fire norms (NOC)
17Social Infrastructure And Other Public Amenities Including Public Health Services
Parks, Health Club and other public amenities shall be provided
18Emergency Evacuation Services
Fire stairs will be available in towers for emergency exist
19Other Miscellaneous Work
Two passenger lift, one goods lift 24"x 7" security system with C,C,t,v cameras and other essential services shall be available in towers
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 19 Dec 2027.

Sanctioned by Varanasi Development Authority · 8,669.89 sqm of land · an approved plan of 3 blocks and 252 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
Group Housing/01171/VDA/BP/21-22/0191/1702202220 Dec 202219 Dec 202719 Dec 20302 Dec 2027
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗

Land & documents

20 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
4G,5G (Naraur)568.77Khasra
4G,5G (Naraur)1195.18Khasra
219 (Balirampur)2517.76Khasra
185,184KH,219 (Balirampur)4792.86Khasra
184KH (Balirampur)1152.71Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Registry document · 11219
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 11313
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 5387
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 6355
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 5939
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Khatauni extract · 1427-1432
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · 1427-1432
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Document checklist
DocumentStatusUploaded
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New28 Dec 2022 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New28 Dec 2022 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New28 Dec 2022 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New28 Dec 2022 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New30 Dec 2022 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New28 Dec 2022 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New28 Dec 2022 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New28 Dec 2022 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New17 Jan 2023 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New29 Dec 2022 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New30 Dec 2022 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New29 Dec 2022 ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
New28 Dec 2022 ↗

Quarterly progress reports

15 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

15 quarterly progress reports are on file with UPRERA, covering 2022-Q4 to 2026-Q2.

QuarterConstructionCertificates
2022-Q4—CA ↗ · Arch ↗ · Eng ↗
2023-Q1—CA ↗ · Arch ↗ · Eng ↗
2023-Q2—CA ↗ · Arch ↗ · Eng ↗
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q258.83%CA ↗ · Arch ↗ · Eng ↗
2025-Q366.21%CA ↗ · Arch ↗ · Eng ↗
2025-Q475.23%CA ↗ · Arch ↗ · Eng ↗
2026-Q180.39%CA ↗ · Arch ↗ · Eng ↗
2026-Q2—CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameSHAKUNTALAM INFRADEVELOPERS LIMITED
RolePromoter · current
RERA IDUPRERAPRM11344
PANAANCS1428C
CIN / TANALDS04112D
Name of chairmanSHARAD AGRAWAL
Registered addressB.38/47-K-8-H, Gokul Nagar Colony, Mahmoorganj, Varanasi-221010 (U.P.)
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Varanasi

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
Shakuntalam Infradevelopers Limited for Rera Collection Account for Project Shree Vinayakam AradhyaBankState Bank of IndiaBranchSME Branch Club Road VaranasiBranch addressSBI Main Branch Campus Oppsite Kachahari Varanasi-221002Branch districtVaranasi, Uttar PradeshA/C no.IFSCSBIN0009252
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
Shakuntalam Infradevelopers Limited for Rera Separate Account for Project Shree Vinayakam AradhyaBankState Bank of IndiaBranchSME Branch, Club Road, Varanasi.Branch addressSBI Main Branch Campus Opposite Kachahari, Varanasi-221002Branch districtVaranasi, Uttar PradeshA/C no.IFSCSBIN0009252
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
Shakuntalam Infradevelopers Limited for Rera Transaction Account for Project Shree Vinayakam AradhyaBankState Bank of IndiaBranchSME Branch, Club Road, Varanasi.Branch addressSBI Main Branch Campus Opposite Kachahari, Varanasi-221002Branch districtVaranasi, Uttar PradeshA/C no.IFSCSBIN0009252
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

1 movement

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Quarterly progress report
2026-Q2
QPR 2026-Q2
newly filed with RERA
15 Oct 2026
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about SHREE VINAYAKAM ARADHYA

Is SHREE VINAYAKAM ARADHYA RERA registered?

Yes. SHREE VINAYAKAM ARADHYA is registered with UPRERA under registration number UPRERAPRJ423217, registered on 17 Jan 2023. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for SHREE VINAYAKAM ARADHYA?

The completion date filed with UPRERA is 2 Dec 2027. No completion certificate is on record yet.

Who is the builder of SHREE VINAYAKAM ARADHYA?

SHAKUNTALAM INFRADEVELOPERS LIMITED is the promoter entity that filed SHREE VINAYAKAM ARADHYA with UPRERA (promoter RERA ID UPRERAPRM11344). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does SHREE VINAYAKAM ARADHYA have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is SHREE VINAYAKAM ARADHYA located?

SHREE VINAYAKAM ARADHYA is registered in Varanasi, as filed with UPRERA.

What configurations are available in SHREE VINAYAKAM ARADHYA?

The unit plan filed with UPRERA lists 3 BHK, 2 BHK and SHOP. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in SHREE VINAYAKAM ARADHYA?

The approved unit plan filed with UPRERA runs from 15 to 130 m² of carpet area (about 166 to 1,400 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in SHREE VINAYAKAM ARADHYA?

The approved unit plan describes 3 blocks and 252 units of which 248 are homes and 4 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is SHREE VINAYAKAM ARADHYA?

About 118 units per acre: 252 planned units across 2.14 acres (8,669.89 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.