Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ5764
Project categoryResidential
Registration typeOngoing
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryNoida Authority
Proposed start31 Dec 2012
Original start31 Dec 2012
Project duration167 months
AddressGautam Buddha Nagar, Gautam Budh Nagar
TehsilGautam Buddha Nagar
Applicant typeCompany
Applicant addressC60 PREET VIHAR DELHI-110092
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Permit revalidated (2)

  2. 3 building permits sanctioned

  3. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  4. Registered with RERA

  5. to

    Extension granted

    “Six months extension in view of force majeure caused by covid-19 pandemic”

  6. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  7. to

    Extension granted

  8. to

    Extension granted

  9. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2020-21
Q1Q2Q3Q4
FY 2022-23
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered4 Aug 2017
Original completion30 Jun 2022
Revised completion31 Oct 2026
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹2,57,000
Sanctioning authorityNoida Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors1,247 · 12 · 18 (units from plan)
Homes · commercial units1,187 · 60 (shops and offices filed in the same plan)
  • 2 BHK540 43%
  • 3 BHK404 32%
  • 1 BHK129 10%
  • 4 BHK66 5%
  • SHOP60 5%
  • PENTHOUSE48 4%
ConfigurationUnitsCarpet area
1 BHK12933-45
2 BHK54033-75
3 BHK40474-100
4 BHK66128
SHOP60448
PENTHOUSE48124-210
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
BLOOM · 1 BHK, 2 BHK, PENTHOUSE1810833-153
COMMERCIAL · SHOP260448
DIGNITY · 1 BHK, 2 BHK, 3 BHK, 4 BHK, PENTHOUSE1810845-210
ELEGANCE · 1 BHK, 2 BHK, PENTHOUSE1810833-153
ESTEEM · 1 BHK, 2 BHK, PENTHOUSE1810833-153
FAMED · 1 BHK, 2 BHK, PENTHOUSE1810833-153
GLORY · 1 BHK, 2 BHK, 3 BHK, PENTHOUSE1810840-179
HONOUR · 1 BHK, 2 BHK, 3 BHK, PENTHOUSE1810840-179
LAUREL · 1 BHK, 2 BHK, 3 BHK1710239-99
PRESTIGE · 1 BHK, 2 BHK, 3 BHK, 4 BHK, PENTHOUSE1810845-210
PRIME · 1 BHK1511940-40
SPLENDER · 3 BHK, 1 BHK, 2 BHK1710239-99
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.The plan also files 80,399 m² for a 3 BHK, far outside the rest of that type, so the ranges above leave it out.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
DEEPAK MEHTA AND SANDEEP SINGH
License CA/97/22261
PLOT NO 16 IIND FLOOR ABHISHEK PLAZA LOCAL SHOPPING CENTER MAYUR VIHAR PH II DELHI -110091
Engineer
AK BANSAL
SLIP TECH PVT LTD 2ND FLOOR C62 VIVEK VIHAR DELHI -110095
Contractor
VVS CONSTRUCTION PVT LTD
554/6 BANK COLONY NEW DELHI 110062
Sr.Development work declared to RERA
1Demarcation of Plots
This project envisages setting up a Group Housing in a land area of 50,000sqm.Comprising1614 units as per sanction and 1655 units as per revision submission with Noida Authority.
2Boundary Wall
1800mm high Boundary wall has been considered along the plot line
3Road Work
6 metres and 7.5 metres wide fire tender road has been considered
4Footpaths
Footpath/pathways/jogging track having a minimum width of about 1500mm has been considered
5Water Supply Including Drinking Water Facilities
Authority water supply will be providing after treating in water treatment plant
6Sewer System
Complete sewer system will be provided as per PHE rules comprising 600kld sewer treatment plant and rain water harvesting arrangement complete in all respect
7Drain
Total surface drain &sullage system will be provided as per PHE and state environment rules
8Parks
20343.97sqm. Green area has been provided comprising kids play area, senior citizen sitting and green vegetation area
9Tree Planting
300 Nos. trees proposed to be planted. Ashoka-60Nos., Gulmohar-80Nos., bottle palm-80Nos., bamboo-80Nos
10Design For Electric Supply Including Street Lighting
External development lighting plan attached
11Community Buildings
Community building, Library, Gymnasium and other amenities proposed to be provided
12Treatment and Disposal System of Sewage and Sullage water
STP with capacity of 600 KLD proposed in the project
13Solid Waste Management And Disposal System
Solid waste management & disposal system is already provided in DPR
14Water Conservation System
Recycled/treated water from STP will be used for flushing system and Landscaping/Irrigation requirements
15Energy Management System Including Use of Renewable Energy
Highly energy efficient LED lighting system proposed in external development, street lighting, all common areas in tower and in parking location will be provided
16Fire Protection And Fire Safety System
All fire protection system has been complied with part-4 of NBC of India and as per BIS-3844 will be maintained in all common areas, staircases and in basements
17Social Infrastructure And Other Public Amenities Including Public Health Services
Parking arrangement, entrance area,common toilet/visitor toilet has been arranged for differently able person. Beside several social infrastructures has been considered for senior citizen
18Emergency Evacuation Services
Emergency evacuation in case of fire or natural disaster has been considered in this project
19Other Miscellaneous Work
Amenities have been provided in this project considering health & hygiene in the complex; viz swimming pool, basketball court, badminton court
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Registered agents

1 agent

Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.

Sr.AgentRERA registration
1ANAROCK Property Consultants Private LimitedUPRERAAGT10265
Agents as filed against this project. The grid does not say whether a registration is still valid, so no validity is shown

Permits & extensions

3 permits

An approval and the date it runs to - not proof the work matching it was done.

3 sanctioning permits are on record with UPRERA, the latest valid to 5 Jul 2017. 2 of them carry a revalidation, the latest valid to 3 Jul 2027.

Sanctioned by Noida Authority · 36,851 sqm of land · an approved plan of 12 blocks and 1247 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endRevalidatedRevalidationThe sanctioning authority renewing a building permit that has expired or is close to expiring.Read the full entry in the glossaryDocuments filed
IV/1316/5035 Jul 20124 Jul 201730 Jun 202230 Jun 2022—
IV/1316/5305 Jul 20125 Jul 20173 Jul 202729 Dec 20225 Jul 2012
valid to 3 Jul 2027
IV/1316/5305 Jul 20125 Jul 20173 Jul 202729 Dec 20225 Jul 2012
valid to 3 Jul 2027
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 3 completion extensions for this project, the latest running to 31 Oct 2026.

#Granted fromExtended uptoNote
130 Jun 202229 Dec 2022Six months extension in view of force majeure caused by covid-19 pandemic
229 Dec 202231 Oct 2025—
331 Oct 202531 Oct 2026—

Land & documents

13 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Lease deed · 5815
The deed by which a development authority leased the land to the promoter, with the term and the conditions on it.
PDF ↗
Document checklist
DocumentStatusUploaded
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New31 Jul 2018 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New29 Jul 2018 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New29 Jul 2018 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New29 Jul 2018 ↗
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
New3 Nov 2022 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New29 Jul 2018 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New29 Jul 2018 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New29 Jul 2018 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New31 Jul 2018 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New31 Jul 2018 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New31 Jul 2018 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New29 Jul 2018 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New31 Jul 2018 ↗

Facilities

as declared to RERA

Mostly reference numbers for filings made elsewhere, such as a fire NOC. Not live certifications, and verified by neither RERA nor Estanzo.

Drinking waterWTP PROVIDED
Fire safety (as filed with RERA)AS PER PART IV NBC OF INDIA
Renewable energyPROVISION OF SOLAR WATER HEATER PROVIDED

The fire-safety value above is the filing reference UPRERA published for this project, not a live safety certification.

Quarterly progress reports

11 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

11 quarterly progress reports are on file with UPRERA, covering 2020-Q3 to 2025-Q4.

QuarterConstructionCertificates
2020-Q3—Eng ↗
2022-Q2—Arch ↗
2022-Q3—Arch ↗
2022-Q4—Arch ↗
2023-Q1—Arch ↗
2023-Q3—Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q2—Eng ↗
2025-Q3—Eng ↗
2025-Q4—Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameSIKKA INFRASTRUCTURE PVT LTD
RolePromoter · current
RERA IDUPRERAPRM11975
PANAAOCS8666N
CIN / TANU70102DL2010PTC209656
Name of chairman1. HARVINDER SINGH SIKKA 2. ANIL MEHRA
Registered addressC60 PREET VIHAR DELHI-110092
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Gautam Budh Nagar

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
SIPL COLLECTION A/C FOR SIKKA KARNAM GREENS (100PERCENT)BankHDFC BANK LIMITEDBranchNOIDA, SECTOR-18Branch addressANSALS ARCADE SECTOR-18, NOIDA -201301Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCHDFC0000088Branch emailsupportathdfcbank.com
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
SEPARATE A/C SIKKA KARNAM GREENS (70PERCENT)BankHDFCBranchNOIDA, SECTOR-18Branch addressANSALS FORTUNE ARCADE,K- BLOCK ,SECTOR-18, NOIDABranch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCHDFC0000088Branch emailsupportathdfcbank.com
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
SIPL TRANSANCTION A/C FOR SIKKA KARNAM GREENS (30 PERCENT)BankHDFC BANK LIMITEDBranchNOIDA, SECTOR-18Branch addressANSAL ARCADE SECTOR-18,NOIDABranch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCHDFC0000088Branch emailsupportathdfcbank.com
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

3 movements

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Promoter’s complaints tally (all their projects)331 (Under Registration - 6 ) → 331 (Under Registration - 5 )
changed in Estanzo’s record
29 Sept 2026
Promoter’s complaints tally (all their projects)330 (Under Registration - 5 ) → 331 (Under Registration - 6 )
changed in Estanzo’s record
31 Aug 2026
Promoter’s complaints tally (all their projects)330 (Under Registration - 6 ) → 330 (Under Registration - 5 )
changed in Estanzo’s record
23 Aug 2026
When these facts last moved
Promoter’s complaints tally (all their projects)changed in Estanzo’s record · 29 Sept 2026 · 3 movements on record
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No khasra or plot detail is published for this project.Ask which khasra numbers the project stands on, so the plot can be matched against the deed and the revenue record.

Common questions about SIKKA KARNAM GREENS

Is SIKKA KARNAM GREENS RERA registered?

Yes. SIKKA KARNAM GREENS is registered with UPRERA under registration number UPRERAPRJ5764, registered on 4 Aug 2017. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for SIKKA KARNAM GREENS?

The completion date filed with UPRERA is 31 Oct 2026. No completion certificate is on record yet.

Who is the builder of SIKKA KARNAM GREENS?

SIKKA INFRASTRUCTURE PVT LTD is the promoter entity that filed SIKKA KARNAM GREENS with UPRERA (promoter RERA ID UPRERAPRM11975). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Has UPRERA granted SIKKA KARNAM GREENS more time to complete?

UPRERA's record carries 3 completion extensions for SIKKA KARNAM GREENS, the latest running to 31 Oct 2026. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does SIKKA KARNAM GREENS have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is SIKKA KARNAM GREENS located?

SIKKA KARNAM GREENS is registered in Gautam Budh Nagar, as filed with UPRERA.

What configurations are available in SIKKA KARNAM GREENS?

The unit plan filed with UPRERA lists 1 BHK, 2 BHK, 3 BHK, 4 BHK, SHOP and PENTHOUSE. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in SIKKA KARNAM GREENS?

The approved unit plan filed with UPRERA runs from 33 to 448 m² of carpet area (about 355 to 4,820 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in SIKKA KARNAM GREENS?

The approved unit plan describes 12 blocks and 1,247 units of which 1,187 are homes and 60 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is SIKKA KARNAM GREENS?

About 137 units per acre: 1,247 planned units across 9.11 acres (36,851 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗