THE ESTATES

UPRERARegistered

THE ESTATES is a RERA-registered residential project by AMIT KUMAR TYAGI in NOOR NAGAR, Ghaziabad (RERA ID UPRERAPRJ265666). Registered with a completion deadline of 27 Feb 2030.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
0%Q1'25
0%Q2'25
0%Q3'25
0%Q4'25
2.31%Q1'26
3.34%Q2'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ265666
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryGhaziabad Development Authority
Proposed start28 Feb 2025
Project duration60 months
AddressKHASRA NO. 962 VILLAGE- NOOR NAGAR , RAJ NAGAR EXTENSION GHAZIABAD, NOOR NAGAR, Ghaziabad, Ghaziabad
TehsilGhaziabad
Applicant typeIndividual
Applicant addressH.No. 113, Bonja , Ghaziabad Uttar Pradesh 201001
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    GDA/LD/23-24/0564

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered27 Nov 2025
Original completion27 Feb 2030
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹43,000
Sanctioning authorityGhaziabad Development Authority

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
PRASHANT CHAUHAN
License CA/2016/74240
2nd Floor khasra No 1127 J.T.Plaza opp D.P.S School, Meerut Road Ghaziabad Uttar Pradesh
Engineer
ASRAF TAJUDDIN
KEEN ASSOCIATES PVT LTD H-53 SECTOR 63 NOIDA
Contractor
SARAS GARG- SARAS INFRASTRUCTURE CONTRACTOR AND ENGINEERS
77, ARJUN NAGAR GHAZIABAD UTTAR PRADESH
Sr.Development work declared to RERA
1Demarcation of Plots
SITE LOCATED AT KHASRA NO. 962 VILLAGE -NOOR NAGAR , RAJNAGAR EXTENSION GHAZIABAD UTTAR PRADESH TOTAL PLOT AREA IS 7514.79 SQ METER
2Boundary Wall
2.4 METERS HIGH BOUNDARY WALL WITH R.C.C COLUMN AND BRICK WALL. THE BOUNDARY WALL SHALL BE EARTHQUAKE RESISTANT.
3Road Work
ALL ROAD IN PROJECT WILL BE COMBINATION OF GRAVELS LAYER, GSB AND TOP OF BITUMEN LAYERS. SIZE OF ROAD 12 METER AND 9 METERS
4Footpaths
ALL FOOTHPATH IN THIS PROJECT WILL INTERLOCKING. BASE OF FOOTPATH SAME AS ROAD WORK
5Water Supply Including Drinking Water Facilities
EXISTING WATER TANK WITH SUFFICIENT CAPACITY WILL BE UTILISE FOR WATER SUPPLY ,TUBE WELL AND INSTALLATION OF PUMP WITH 100MM DIA PIPES.
6Sewer System
SEWAGE SYSTEM LAYING OF SEWER AND MANHOLE PROVIDE AND FIXING OF 150MM RCC PIPE. AND CONNECT WITH GOVERMENT SEWER PIPE LINE
7Drain
DRAIN SYSTEM LAYING OF GOVERMENT DRAIN AND MANHOLE PROVIDING AND FIXING OF 100-250 MM PIPES.
8Parks
GREEN AREA PROVIDED AS PER SANCTION MAP.AREA OF GREEN IS 885.45 SQ METER AND BOUNDARY WITH GREEN HATCHED
9Tree Planting
AT PARK AREA ALL TREE WILL BE PLANTED AT ALL SUITABLE LOCATION OF THE PROJECT AND ALONG THE GREEN AREAS.
10Design For Electric Supply Including Street Lighting
ELECTRICITY SUPPLY SHALL BE USED AS PER SANCTION LOAD AND STREET LIGHT DESIGN AS PER AUTHORITY NORMS .
11Community Buildings
AS PER SANCTION MAP
12Treatment and Disposal System of Sewage and Sullage water
S.T.P PIPES LINE SHALL BE PROVIDED . LAYING OF SEWER AND MANHOLE PROVIDE AND FIXING OF 150MM PIPES AND CONNECT WITH GOVERMENT SEWER PIPE LINES.
13Solid Waste Management And Disposal System
MANUAL COLLECTION SHALL BE PROVIDED ON PROJECT AND PROVIDING COLLECTION BOX ON SITE
14Water Conservation System
AS PER SANCTION MAP RAINWATER HARVESTING PROVING ON SITE.
15Energy Management System Including Use of Renewable Energy
AS PER UP ELECTRICITY BOARD GUIDELINES AND SHALL BE PROVIDED NECESSARY SWITCH-GEAR ETC. ALL PLOTS CONNECTION PROCESS BY ELECTRICITY BOARD .
16Fire Protection And Fire Safety System
FIRE TENDER PATH SHALL BE PROVIDED AS PER SANCTION MAP. MAIN ROAD OF PROJECT 12.0 METER , 9.0 METER AND 7.5 METER FOR FIRE TENDER PATH MOVEMENT.
17Social Infrastructure And Other Public Amenities Including Public Health Services
N/A
18Emergency Evacuation Services
FIRE TENDER ROAD SHALL BE PROVIDED AS PER SANCTION MAP . MAIN ENTRANCE 12 METER AND OTHER ROAD 9.0 METER , 7.5 METER PROVIDED.
19Other Miscellaneous Work
N/A
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 27 Feb 2030.

Sanctioned by Ghaziabad Development Authority · 7,515 sqm of land. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total.

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
GDA/LD/23-24/056428 Feb 202527 Feb 203027 Feb 203327 Feb 2030
Plans and approvals filed with RERA
DocumentFile
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
no file published
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗

Land & documents

16 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
9627514.79Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Khatauni extract · 1427-1432
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Allotment letter from the authority · 636/RC-24/03-5-24
The development authority’s letter allotting the plot - usually the step before a lease deed is executed.
PDF ↗
Registry document · 6026
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Document checklist
DocumentStatusUploaded
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New23 Oct 2025 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New30 Sept 2025 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New30 Sept 2025 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New23 Oct 2025 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New18 Sept 2025 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New18 Sept 2025 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New18 Sept 2025 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New18 Sept 2025 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New16 Sept 2025 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New30 Sept 2025 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New30 Sept 2025 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New30 Sept 2025 ↗
Agreement for sale (proforma)
The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind.
New1 Oct 2025 ↗

Quarterly progress reports

6 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

6 quarterly progress reports are on file with UPRERA, covering 2024-Q4 to 2026-Q1.

QuarterConstructionCertificates
2024-Q40%CA ↗ · Arch ↗ · Eng ↗
2025-Q10%CA ↗ · Arch ↗ · Eng ↗
2025-Q20%CA ↗ · Arch ↗ · Eng ↗
2025-Q30%CA ↗ · Arch ↗ · Eng ↗
2025-Q42.31%CA ↗ · Arch ↗ · Eng ↗
2026-Q13.34%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameAMIT KUMAR TYAGI
RolePromoter · current
RERA IDUPRERAPRM397019
PANACZPT0160F
Registered addressH.No. 113, Bonja , Ghaziabad Uttar Pradesh 201001
RERA contact
Registered since2025
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Ghaziabad

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
AMIT KUMAR TYAGI COLLECTION ACCOUNT FOR THE ESTATESBankKOTAK MAHINDRA BANK LTD.BranchKOTAK MAHINDRA BANK LTD. PANCHSHEEL PARK SAHIBABAD GHAZIABADBranch addressKOTAK MAHINDRA BANK LTD. PLOT NO. -3 PANCHSHEEL PARK SAHIBABAD GHAZIABADBranch districtGhaziabad, Uttar PradeshA/C no.IFSCKKBK0005328Branch email05328Panchsheelparksahibabadreferral@kotak.com
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
AMIT KUMAR TYAGI SEPARATE ACCOUNT FOR THE ESTATESBankKOTAK MAHINDRA BANK LTD.BranchKOTAK MAHINDRA BANK LTD. PANCHSHEEL PARK SAHIBABAD GHAZIABADBranch addressKOTAK MAHINDRA BANK LTD. PLOT NO. -3 PANCHSHEEL PARK SAHIBABAD GHAZIBAD UTTAR PRADESHBranch districtGhaziabad, Uttar PradeshA/C no.IFSCKKBK0005328
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
AMIT KUMAR TYAGI RERA TRANSACTION ACCOUNT FOR THE ESTATESBankKOTAK MAHINDRA BANK LTD.BranchKOTAK MAHINDRA BANK LTD. PANCHSHEEL PARK SAHIBABAD GHAZIABADBranch addressKOTAK MAHINDRA BANK LTD. PLOT NO. 3 PANCHSHEEL PARK SAHIBABAD GHAZIABADBranch districtGhaziabad, Uttar PradeshA/C no.IFSCKKBK0005328
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

2 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No approved unit plan is published for this project.Ask for the carpet area of the specific unit in writing, and for the approved floor plan it is measured from.
  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about THE ESTATES

Is THE ESTATES RERA registered?

Yes. THE ESTATES is registered with UPRERA under registration number UPRERAPRJ265666, registered on 27 Nov 2025. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for THE ESTATES?

The completion date filed with UPRERA is 27 Feb 2030. No completion certificate is on record yet.

Who is the builder of THE ESTATES?

AMIT KUMAR TYAGI is the promoter entity that filed THE ESTATES with UPRERA (promoter RERA ID UPRERAPRM397019). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does THE ESTATES have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is THE ESTATES located?

THE ESTATES is registered in NOOR NAGAR, Ghaziabad, as filed with UPRERA.