Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ4759
Project categoryResidential
Registration typeOngoing
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryGhaziabad Development Authority
Proposed start19 Aug 2015
Original start19 Aug 2015
Project duration66 months
AddressModinagar, Ghaziabad
TehsilModinagar
Applicant typeCompany
Applicant addressAgarwal Height (Kh. No.962M Raj Nagar Ext. Ghaziabad)
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    373/ZONE-1/GH/14-15

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. to

    Extension granted

    “Six months extension in view of force majeure caused by covid-19 pandemic”

  5. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  6. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

  7. Completion certificate filed

  8. Completion certificate filed

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2020-21
Q1Q2Q3Q4
FY 2021-22
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered31 Jul 2017
Original completion19 Aug 2020
Revised completion18 Feb 2021
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary14 Jul 2022
Registration fee₹47,000
Sanctioning authorityGhaziabad Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors449 · 3 · 24 (units from plan)
Homes · commercial units440 · 9 (shops and offices filed in the same plan)
  • 2 BHK380 85%
  • 3 BHK60 13%
  • SHOP9 2%
ConfigurationUnitsCarpet area
2 BHK38049-64
3 BHK6077
SHOP915
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
A · OTHER, 2 BHK, 3 BHK, SHOP2416915-77
B · OTHER, 2 BHK2414049-64
C · OTHER, 2 BHK, 3 BHK2414049-77
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
ANUJ AGARWAL ARCHITECTS
License CA/96/19503
A-244,KAUSHAMBI,GZB.(U.P.)
Engineer
V.D. SHARMA
B-24,SEC-67,NOIDA
Sr.Development work declared to RERA
1Demarcation of Plots
Yes. Group Housing Plot already demarcated
2Boundary Wall
Yes.
3Road Work
Yes. As per Sanctioned Plans
4Footpaths
Yes. As per Sanctioned Plans
5Water Supply Including Drinking Water Facilities
Yes. As per Sanctioned Plans
6Sewer System
Yes. As per Sanctioned Plans
7Drain
Yes. As per Sanctioned Plans
8Parks
Yes. As per Sanctioned Plans
9Tree Planting
Yes. As per Sanctioned Plans
10Design For Electric Supply Including Street Lighting
Yes. As per Sanctioned Plans
11Community Buildings
Yes. Club
12Treatment and Disposal System of Sewage and Sullage water
Yes. STP
13Solid Waste Management And Disposal System
Yes.
14Water Conservation System
Yes. Rainwater will be harvested
15Energy Management System Including Use of Renewable Energy
Yes. CFL
16Fire Protection And Fire Safety System
Yes. As per Sanctioned Plans
17Social Infrastructure And Other Public Amenities Including Public Health Services
Not applicable
18Emergency Evacuation Services
Yes. As per Sanctioned Plans
19Other Miscellaneous Work
Not applicable
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Registered agents

4 agents

Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.

Sr.AgentRERA registration
1Amit sharmaUPRERAAGT12024
2GAURAV JAINUPRERAAGT11716
3Ravinder KumarUPRERAAGT13377
4TANUJ SHARMAUPRERAAGT12133
Agents as filed against this project. The grid does not say whether a registration is still valid, so no validity is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 19 Aug 2020.

Sanctioned by Ghaziabad Development Authority · 8,380 sqm of land · an approved plan of 3 blocks and 449 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
373/ZONE-1/GH/14-1519 Aug 201519 Aug 202019 Aug 202119 Aug 2020
Plans and approvals filed with RERA
DocumentFile
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
no file published
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Project approval
The approval the promoter filed as the basis for registering the project.
PDF ↗
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 1 completion extension for this project, running to 18 Feb 2021.

#Granted fromExtended uptoNote
119 Aug 202018 Feb 2021Six months extension in view of force majeure caused by covid-19 pandemic

Land & documents

15 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
962M8379.39—
962M8379.39Khasra
Registry & lease deedsRegistry / lease deedThe deed by which the land changed hands, recorded with the sub-registrar and stamped.Read the full entry in the glossary

1 registry or lease-deed filing is on this project’s record with UPRERA, dated 8 Aug 2011.

Registry no.DateTypeArea
79358 Aug 2011self—
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Registry document · 7935
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 7935
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 7935
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 7935
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 7935
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 7935
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 7935
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 7935
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 7935
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 7935
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 7935
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 7935
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Document checklist
DocumentStatusUploaded
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New13 May 2021 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New6 Jul 2018 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New6 Jul 2018 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New6 Jul 2018 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New6 Jul 2018 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New6 Jul 2018 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New6 Jul 2018 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New6 Jul 2018 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New6 Jul 2018 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New6 Jul 2018 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
Old31 Oct 2017 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
Old31 Oct 2017 ↗

Facilities

as declared to RERA

Mostly reference numbers for filings made elsewhere, such as a fire NOC. Not live certifications, and verified by neither RERA nor Estanzo.

Drinking waterGROUND WATER
Fire safety (as filed with RERA)AS PER FIRE NORMS
Renewable energyUPPCL
Other facilitiesCLUB & GREEN AREA

The fire-safety value above is the filing reference UPRERA published for this project, not a live safety certification.

Quarterly progress reports

6 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

6 quarterly progress reports are on file with UPRERA, covering 2020-Q1 to 2021-Q3.

QuarterConstructionCertificates
2020-Q1—CA ↗ · Arch ↗ · Eng ↗
2020-Q2—CA ↗ · Arch ↗ · Eng ↗
2020-Q3—CA ↗ · Arch ↗ · Eng ↗
2020-Q4—CA ↗ · Arch ↗ · Eng ↗
2021-Q1—CA ↗ · Arch ↗ · Eng ↗
2021-Q3—CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameBankey Bihari Infrahomes Pvt. Ltd.
RolePromoter · current
RERA IDUPRERAPRM8292
PANAAECB4712F
CIN / TANU70101DL2011PTC214344
Name of chairmanSh. Rajeev Aggarwal (Director)
Registered addressAgarwal Height (Kh. No.962M Raj Nagar Ext. Ghaziabad)
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Ghaziabad

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.

AccountAs filed with RERA
Bank account as filed
bankey bihari infrahomes pvt ltdBankBANK OF BARODABranchSME BRANCHA/C no.IFSCBARB0SSIGAZ
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

Common questions about AGGARWAL HEIGHTS

Is AGGARWAL HEIGHTS RERA registered?

Yes. AGGARWAL HEIGHTS is registered with UPRERA under registration number UPRERAPRJ4759, registered on 31 Jul 2017. Estanzo reproduces that filing; it does not verify the work behind it.

Has AGGARWAL HEIGHTS been completed?

UPRERA still lists AGGARWAL HEIGHTS as Registered, so it is not shown as completed here. A completion certificate dated 14 Jul 2022 is on the record - RERA accepts these tower-wise, so one on file does not mean the whole project is complete.

Who is the builder of AGGARWAL HEIGHTS?

Bankey Bihari Infrahomes Pvt. Ltd. is the promoter entity that filed AGGARWAL HEIGHTS with UPRERA (promoter RERA ID UPRERAPRM8292). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Has UPRERA granted AGGARWAL HEIGHTS more time to complete?

UPRERA's record carries 1 completion extension for AGGARWAL HEIGHTS, the latest running to 18 Feb 2021. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does AGGARWAL HEIGHTS have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is AGGARWAL HEIGHTS located?

AGGARWAL HEIGHTS is registered in Ghaziabad, as filed with UPRERA.

What configurations are available in AGGARWAL HEIGHTS?

The unit plan filed with UPRERA lists OTHER, 2 BHK, 3 BHK and SHOP. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in AGGARWAL HEIGHTS?

The approved unit plan filed with UPRERA runs from 15 to 77 m² of carpet area (about 161 to 829 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in AGGARWAL HEIGHTS?

The approved unit plan describes 3 blocks and 449 units of which 440 are homes and 9 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is AGGARWAL HEIGHTS?

About 217 units per acre: 449 planned units across 2.07 acres (8,380 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗