The Flagship Phase 1

UPRERARegistered

The Flagship Phase 1 is a RERA-registered commercial project by IT INFRASTRUCTURE PARK PRIVATE LIMITED in Gautam Budh Nagar (RERA ID UPRERAPRJ184164). Registered with a completion deadline of 16 Nov 2027.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q4'24
—Q1'25
—Q2'25
59%Q3'25
63%Q4'25
74%Q1'26
81%Q2'26
—Q3'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ184164
Project categoryCommercial
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryNoida Authority
Proposed start1 Mar 2023
Project duration57 months
AddressGautam Buddha Nagar, Gautam Budh Nagar
TehsilGautam Buddha Nagar
Applicant typeCompany
Applicant addressRegistered Office Plot No. 3&4, Second Floor, Savitri Bhawan, A- Block Market, Preet Vihar, East Delhi, Delhi, PIN-110092 Corporate Office Tower A- Ground Floor , Logix Techno Park, Sector-127, NOIDA, Gautam Buddha Nagar, Uttar Pradesh, PIN-110092 Site Office Plot No. 1B, Sector 140-A, NOIDA, Distt. Gautam Buddha Nagar, Uttar Pradesh, PIN 201305
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    NOIDA/B.C./B.P.-OBPAS-7596/BP-V-1031/750

  2. Registered with RERA

  3. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2022-23
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered24 Feb 2023
Original completion16 Nov 2027
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹80,000
Sanctioning authorityNoida Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors716 · 1 · 24 (units from plan)
Homes · commercial units696 · 20 (shops and offices filed in the same plan)
  • OTHER696 97%
  • SHOP20 3%
ConfigurationUnitsCarpet area
SHOP2026-83
OTHER6967-484
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
Tower 1 · SHOP, OTHER247167-484
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Shivang Bansal
License CA/2018/96268
135 Block B, Sector 44, NOIDA, PIN-201301
Engineer
Dr. Vinod Jain - Vintech Consultants
C-35, Pamposh Enclave , G.K.1, New Delhi, PIN-110048
Contractor
Katyayani Steel Works
120/5, Krishna Nagar, Safdurganj Enclave, Delhi, PIN-110029
Sr.Development work declared to RERA
1Demarcation of Plots
The Plot No. 01B, Sector 140A, NOIDA had been demarcated by Noida Development Authority
2Boundary Wall
A boundary wall of RCC / Brick work of thickness 115 mm/ 230/150 mm and ht of 900 /1500/1800 mm with plaster and railing will be prepared, it will be as per design.
3Road Work
Access driveway to all the towers will be provided and that drive way of Pavers M 30 grade with thickness of 65 mm and 100 mm kerb stone on sides if required. At entry of tower there will be pattern as per landscape design.
4Footpaths
Footpath will be provided using 40-50 mm Paver wherever required.
5Water Supply Including Drinking Water Facilities
NOIDA Authority shall supply water for the entire society and it shall be collected in underground water tanks of 178 KL X1, 184 KL X 1 nos. Raw water and 178KL X 1 , 167 KL X1, Nos. Domestic Water Tanks and water with 65 mm dia pipes to overhead tank at respective Towers.
6Sewer System
STP of 700 KLD will be constructed using RCC and required pump room, STP treated water will be used in flushing , cooling Towers and gardening.
7Drain
Storm Water drainage system will be constructed using 400mm dia pipes as per drawings.
8Parks
Landscape with civil work masonary 115/230 mm and stone , pavers , grass, and various type of plantation shurbs
9Tree Planting
Tree Plantation will be as per sanctioned plan in which 50 percent trees will be evergreen trees.
10Design For Electric Supply Including Street Lighting
Incoming HT electrical supply will be provided by UPPCL / NPCL Via 2 Nos. 7.5 MVA Power Transformers, Substation , LT Panel and DG Sets of 5 Nos X2000 kVA and 1 No X 1010 kVA are planned as per norms. Street lighting will be done using LT supply and Power Back up as per requirement.
11Community Buildings
Not Applicable
12Treatment and Disposal System of Sewage and Sullage water
STP will be installed as per dwg , All sewerage will be treated and the treated waste water will be used for landscaping green , cooling towers and flushing system.
13Solid Waste Management And Disposal System
STP is proposed at site for the required capacity and treated water shall be used for flushing and irrigation as per latest green building practices.
14Water Conservation System
Rain water harvesting system with separate Rain water Storage tanks is being provided to conserve rain water and duel flush , Low flow Fixture and Drip / sprinklers in Green areas will also be provided.
15Energy Management System Including Use of Renewable Energy
Solar System shall be provided as per requirement.
16Fire Protection And Fire Safety System
In compliance to National Building Code of India 2016 Part IV requirement, Fire Protection and Safety System provided which consists of Underground Fire Tank - 920 m3 Each Tower having 20 m3 Fire Overhead Water Tank Main Electric Fire Hydrant and Sprinkler Pumps provided of 2850 LPM each Jockey pump for Hydrant and Sprinkler of 180 LMP each Diesel Engine Fire Pump of 2850 LPM Water Curtain Pump of 4500 M All project Sprinkler system provided in compliances to IS codes and project fire safety requirements aligned to NBC 2016 Part-IV
17Social Infrastructure And Other Public Amenities Including Public Health Services
Creche facility , Public toilets and driver toilets.
18Emergency Evacuation Services
Emergency Evacuation System ( stairways, exitways etc.) planned in compliance to National Building Code of India 2016 Part -IV . Refuge areas also provided in compliance to NBC 2016
19Other Miscellaneous Work
State of the Art Security System Access Control system and CCTV system provided for Security and controlled access in the buildings.
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 16 Nov 2027.

Sanctioned by Noida Authority · 6,995 sqm of land · an approved plan of 1 block and 716 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
NOIDA/B.C./B.P.-OBPAS-7596/BP-V-1031/75017 Nov 202216 Nov 202716 Nov 203216 Nov 2027
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗

Land & documents

15 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
01B, Sector 140A, NOIDA, Gautam Buddha Nagar, Uttar Pradesh, PIN-20130545202.50Plot
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Lease deed · 3997
The deed by which a development authority leased the land to the promoter, with the term and the conditions on it.
PDF ↗
Allotment letter from the authority · Affidavit Sale
The development authority’s letter allotting the plot - usually the step before a lease deed is executed.
PDF ↗
Allotment letter from the authority · Land Title Search Report
The development authority’s letter allotting the plot - usually the step before a lease deed is executed.
PDF ↗
Allotment letter from the authority · Reply Letter for Objection of The Flagship Phase 1 Project Dated 06.02.2023
The development authority’s letter allotting the plot - usually the step before a lease deed is executed.
PDF ↗
Lease deed · Sub-Lease Deed Permission letter
The deed by which a development authority leased the land to the promoter, with the term and the conditions on it.
PDF ↗
Document checklist
DocumentStatusUploaded
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New25 Jan 2023 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New25 Jan 2023 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New25 Jan 2023 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New25 Jan 2023 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New25 Jan 2023 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New25 Jan 2023 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New25 Jan 2023 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New25 Jan 2023 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New25 Jan 2023 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New25 Jan 2023 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New25 Jan 2023 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New25 Jan 2023 ↗

Quarterly progress reports

15 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

15 quarterly progress reports are on file with UPRERA, covering 2022-Q4 to 2026-Q2.

QuarterConstructionCertificates
2022-Q4—CA ↗ · Arch ↗ · Eng ↗
2023-Q1—CA ↗ · Arch ↗ · Eng ↗
2023-Q2—CA ↗ · Arch ↗ · Eng ↗
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q259%CA ↗ · Arch ↗ · Eng ↗
2025-Q363%CA ↗ · Arch ↗ · Eng ↗
2025-Q474%CA ↗ · Arch ↗ · Eng ↗
2026-Q181%CA ↗ · Arch ↗ · Eng ↗
2026-Q2—CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameIT INFRASTRUCTURE PARK PRIVATE LIMITED
RolePromoter · current
RERA IDUPRERAPRM191806
PANAAACI8782L
CIN / TANDELI06882B
Name of chairmanSatish Garg
Registered addressRegistered Office Plot No. 3&4, Second Floor, Savitri Bhawan, A- Block Market, Preet Vihar, East Delhi, Delhi, PIN-110092 Corporate Office Tower A- Ground Floor , Logix Techno Park, Sector-127, NOIDA, Gautam Buddha Nagar, Uttar Pradesh, PIN-110092 Site Office Plot No. 1B, Sector 140-A, NOIDA, Distt. Gautam Buddha Nagar, Uttar Pradesh, PIN 201305
RERA contact
Registered since2022
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Gautam Budh Nagar

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
IT Infrastructure Park Private Limited Collection Account for The Flagship Phase 1BankKotak Mahindra BankBranchSector 18, NOIDABranch addressPlot No. 31 and 32 , Block G, Sector 18, NOIDA, Gautam Buddha Nagar, Uttar Pradesh, PIN-201301Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCKKBK0000181
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
IT Infrastructure Park Private Limited Separate Bank Account for The Flagship Phase 1BankKotak Mahindra BankBranchSector18, NOIDABranch addressPlot No. 31 and 32, Block G , Sector 18, NOIDA, Gautam Buddha Nagar, Uttar Pradesh, PIN-201301Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCKKBK0000181
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
IT Infrastructure Park Private Limited RERA Transaction Account for The Flagship Phase 1BankKotak Mahindra BankBranchSector 18, NOIDABranch addressPlot No. 31 and 32, Block-G, Sector 18, NOIDA, Gautam Buddha Nagar, Uttar Pradesh, PIN-201301Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCKKBK0000181
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

1 movement

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Quarterly progress report
2026-Q2
QPR 2026-Q2
newly filed with RERA
15 Oct 2026
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about The Flagship Phase 1

Is The Flagship Phase 1 RERA registered?

Yes. The Flagship Phase 1 is registered with UPRERA under registration number UPRERAPRJ184164, registered on 24 Feb 2023. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for The Flagship Phase 1?

The completion date filed with UPRERA is 16 Nov 2027. No completion certificate is on record yet.

Who is the builder of The Flagship Phase 1?

IT INFRASTRUCTURE PARK PRIVATE LIMITED is the promoter entity that filed The Flagship Phase 1 with UPRERA (promoter RERA ID UPRERAPRM191806). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does The Flagship Phase 1 have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is The Flagship Phase 1 located?

The Flagship Phase 1 is registered in Gautam Budh Nagar, as filed with UPRERA.

What configurations are available in The Flagship Phase 1?

The unit plan filed with UPRERA lists SHOP and OTHER. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in The Flagship Phase 1?

The approved unit plan filed with UPRERA runs from 7 to 484 m² of carpet area (about 72 to 5,215 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in The Flagship Phase 1?

The approved unit plan describes 1 block and 716 units of which 696 are homes and 20 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is The Flagship Phase 1?

About 414 units per acre: 716 planned units across 1.73 acres (6,995 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗