Timeline Bar

Registered10 Jun 2023
Today4 Aug 2026
Promised16 Nov 2027

Timeline

Promised completion16 Nov 2027
Revised completion16 Nov 2027
Actual completion
Possession delayOn time

Registration & Cost Details

Registration fee (in ₹)₹65,000
Project cost (in ₹ Lakhs)₹14,460 Lakhs
Project duration54 months
Project categoryCommercial
Locality
Original start date
Proposed start date1 Jun 2023

Inventory

Total units580
Unit TypeUnitsCarpet Area (sqm)
OTHER5804.7–1670

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9599109259
Emailaccount@crcgroup.in
Coordinator9599109259
AddressRegistered Office Plot No. 3&4, Second Floor, Savitri Bhawan, A- Block Market, Preet Vihar, East Delhi, Delhi, PIN-110092 Corporate Office Tower A- Ground Floor , Logix Techno Park, Sector-127, NOIDA, Gautam Buddha Nagar, Uttar Pradesh, PIN-110092 Site Office Plot No. 1B, Sector 140-A, NOIDA, Distt. Gautam Buddha Nagar, Uttar Pradesh, PIN 201305

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2023-Q1
2023-Q2
2023-Q3
2023-Q4
2024-Q1
2024-Q2
2024-Q3
2024-Q4
2025-Q1
2025-Q258.0%
2025-Q373.0%
2025-Q482.0%
2026-Q189.0%

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
NOIDA/B.C/B.P.-OBPAS-7596/BP-V-1031/75017 Nov 202216 Nov 202716 Nov 202716 Nov 2032

Land Parcels

Khasra No.AreaPlot Type
O1B, SECTOR 140A, GAUTAM BUDDHA NAGAR, NOIDA, UP-20130545202.50Plot

Approved Unit Plan

Unit plan rows on file209
Total flats (sum of rows)580
BlocksTOWER-2
Floor typesOTHER

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of THE FLAGSHIP PHASE 2?

The RERA registration number of THE FLAGSHIP PHASE 2 is UPRERAPRJ893178, as recorded on the UP-RERA portal.

What is the RERA status of THE FLAGSHIP PHASE 2?

As reported by UP-RERA, the status of THE FLAGSHIP PHASE 2 is "Registered".

Where is THE FLAGSHIP PHASE 2 located?

As reported to UP-RERA, THE FLAGSHIP PHASE 2 is located at Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

When will THE FLAGSHIP PHASE 2 be completed?

The latest completion date reported to UP-RERA for THE FLAGSHIP PHASE 2 is 16 Nov 2027.

Is THE FLAGSHIP PHASE 2 delayed?

Measured against the latest completion date reported to UP-RERA, THE FLAGSHIP PHASE 2 is on time.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026