CYBERTHUM PHASE B is a RERA-registered real-estate project in Gautam Budh Nagar (RERA ID UPRERAPRJ240015). Its RERA-registered completion deadline (25 Dec 2023) has passed with no occupancy certificate (OC) on record. Data as reported by UP-RERA. as reported by UPRERA
RERA status as reported: Registered.| RERA ID | UPRERAPRJ240015 |
| Applicant type | Company |
| Project category | Commercial |
| Project type | other |
| RERA status | Registered |
| Proposed start | 1 Jan 2019 |
| Project duration | 74 |
| Address | Gautam Buddha Nagar, Gautam Budh Nagar |
| RERA registered | 5 Feb 2019 |
| Promised completion | 1 Dec 2022 |
| Revised completion | 25 Dec 2023 |
| Completion certificate filed | — not on record |
| Registration fee | ₹2,39,000 |
| Configuration | Units | Carpet area |
|---|---|---|
| OTHER | 1,470 | 0–126 |
| Permit no. | Date | Valid upto | Revised end |
|---|---|---|---|
| NOIDA/MVN/2018/BP-12619/390 | 26 Dec 2018 | 25 Dec 2023 | 1 Dec 2022 |
| NOIDA/MVN/2018/BP-12619/390 | 26 Dec 2018 | 25 Dec 2023 | 25 Dec 2023 |
| Khasra | Area | Type |
|---|---|---|
| 2 SECTOR 140A | 108800 | Plot |
| Quarter | Construction | Certificates | Source |
|---|---|---|---|
| 2020-Q1 | — | CA · Arch · Eng | view ↗ |
| 2020-Q2 | — | CA · Arch · Eng | view ↗ |
| 2020-Q3 | — | CA · Arch · Eng | view ↗ |
| 2020-Q4 | — | CA · Arch · Eng | view ↗ |
| 2021-Q1 | — | CA · Arch · Eng | view ↗ |
| 2021-Q2 | — | CA · Arch · Eng | view ↗ |
| 2021-Q3 | — | CA · Arch · Eng | view ↗ |
| 2021-Q4 | — | CA · Arch · Eng | view ↗ |
| 2022-Q1 | — | CA · Arch · Eng | view ↗ |
| 2022-Q2 | — | CA · Arch · Eng | view ↗ |
| 2022-Q3 | — | CA · Arch · Eng | view ↗ |
| 2022-Q4 | — | CA · Arch · Eng | view ↗ |
| 2023-Q1 | — | CA · Arch · Eng | view ↗ |
| 2023-Q2 | — | CA · Arch · Eng | view ↗ |
| 2023-Q3 | — | CA · Arch · Eng | view ↗ |
| 2023-Q4 | — | CA · Arch · Eng | view ↗ |
| 2024-Q1 | — | CA · Arch · Eng | view ↗ |
| 2024-Q2 | — | CA · Arch · Eng | view ↗ |
| 2024-Q3 | — | CA · Arch · Eng | view ↗ |
Other projects registered in Gautam Budh Nagar.
Yes. CYBERTHUM PHASE B is registered with UPRERA under registration number UPRERAPRJ240015, registered on 5 Feb 2019. Estanzo reproduces that filing; it does not verify the work behind it.
CYBERTHUM PHASE B is 31 months past the completion date filed with UPRERA (25 Dec 2023), with no occupancy certificate on record. That is the authority's own dates subtracted — not an assessment of the builder.
CYBERTHUM PHASE B is registered in Gautam Budh Nagar, as filed with UPRERA.
Data as reported by UPRERA, last collected 4 Aug 2026. official source ↗