Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q1'25
—Q2'25
0%Q3'25
1%Q4'25
1%Q1'26
2%Q2'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ298067
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryGreater Noida Authority
Proposed start30 Mar 2025
Project duration59 months
AddressPlot No. C-01, Land-II, Integrated Sports Complex at Jaypee Greens, Sector-26 & 31, Surajpur Kasana Road, Greater Noida, Gautam Buddha Nagar, Uttar Pradesh, PIN-201310, Jaypee Greens, Sector 26 & 31, Greater Noida, Gautam Buddha Nagar, Gautam Budh Nagar
TehsilGautam Buddha Nagar
Applicant typeCompany
Applicant addressRegd. Office - 111VardhmanMayurMarketCSC, MayurViharPhase3 Gharoli, East Delhi, East Delhi, East Delhi, Delhi, India, 110096 Corporate Office- Ground Floor, Tower-A, Logix Techno Park, Sec-127, Noida, Gautam Buddha Nagar, Uttar Pradesh, PIN-201301
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    PLG/BP SM-10-JUL-2024.21921

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered16 May 2025
Original completion4 Feb 2030
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹82,500
Sanctioning authorityGreater Noida Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors— · 7 · 42 (from plan)
ConfigurationUnitsCarpet area
5 BHK—411-906
4 BHK—275-609
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
Tower-1 · 5 BHK, OTHER42—411-906
Tower-2 · OTHER, 5 BHK42—411-417
Tower-3 · OTHER, 4 BHK42—345-609
Tower-4 · OTHER, 4 BHK42—345
Tower-5 · OTHER, 4 BHK42—320
Tower-6 · 4 BHK42—340-516
Tower-7 · 4 BHK, OTHER42—275-602
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.No unit total is shown: the plan's flat-count column contradicts this project's other filings.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Shivendra Nath
License CA/2012/56592
Ground Floor, Tower- A, Logix Techno Park, Sector-127, NOIDA, Gautam Buddha Nagar.
Engineer
Ravi Shankar
H.No.- A112, Block-A, Sector-108, NOIDA, Gautam Buddha Nagar, Uttar Pradesh, PIN-201304
Contractor
Katyani Steel Works
120/5, Krishna Nagar, Safadarjung Enclave, Delhi, PIN- 110029
Sr.Development work declared to RERA
1Demarcation of Plots
The Plot No. C-1 in Land-2, integrated Sports Complex at Jaypee Greens Sector 26 and 31 , Surjpur Kasana Road, Greater Noida, U.P. had been demarcated by JAYPEE.
2Boundary Wall
Green fencing as per rule of Township.
3Road Work
Access driveway to all the towers will be provided and that driveway will be pavers M 30 grade with thickness of 65 mm and 100 mm kerb stone on sides if required. An entry of tower , there will be pattern as per design.
4Footpaths
Footpath will be provided using 40-50 mm paver wherever required.
5Water Supply Including Drinking Water Facilities
The Total domestic water demand is 770 KL, and flushing water demand is 280 KL. since this is part of the Jaypee Green Master Plan, the water supply will be received from the Jaypee Green Infra pluming plant room. This water will be stored in the fire water tank and, which shall there after be allowed to overflow and store in water tank. The raw water after treatment shall be stored in the treated water tanks. Domestic water shall thereafter be transferred by gravity to the various consumption point. Booster pump shall be installed at the roof level to feed the Top 3 floors to ensure minimum 1.5 bar pressure at the usage points. Similarly, Flushing water will be received from the Jaypee Green (Infra) STP and store in Non portable water receiving Tank. Thereafter depending on the quality water shall be treated by UF and store in Flushing Water Tank. Flushing Water and Domestic Water shall be supplied by dedicated Hydro-pneumatic System installed in the plumbing plant room respectively to feed OHT of all towers.
6Sewer System
The Centralized Sewage Treatment plant is available at master plan level. So all the blocks shall disposed by gravity system in to the first manholes around the towers, which shall be finally connected to the external sewerage system network as per the master plan. Incase of STP failure, raw water from the plumbing plant room shall be transferred to flushing water tank.
7Drain
Roof rain water shall be collected through pipes and connected to rain water storage tank for reuse and excess water overflow in the surface storm drain network, surface rain water collected through drain network which will be planned at the site level and thereafter overflow in to master plan Strom water network.
8Parks
Landscape with civil work masonry 115/230 mm and stone, paver, grass and various type of plantation , shrubs.
9Tree Planting
Tree Plantation will be as per the sanctioned Plan in which 50 percent trees will be evergreen trees.
10Design For Electric Supply Including Street Lighting
Centralized substation have been proposed for entire development at ground level. 5 no. 2000 KVA, 33/0.433 kV Oil filled Compact transformers are proposed for the entire development including External or Street lighting. In order to provide resilient power supply for the Project, 100 percent emergency power Backup is proposed through 5 No. 1500 kVA Radiator Cooled type Generator Sets.( No DG Backup for EV charging Infrastructure.). DG sets are planned in basement in double height area.
11Community Buildings
Community Building will be made as per approved Building plan and there will be Multi purpose Hall, Indoor Games, GYM, Entrance lobby etc.
12Treatment and Disposal System of Sewage and Sullage water
The Centralized Sewage Treatment plant is available at master plan level . So, all the Blocks shall be disposed by gravity system into the first main holes around the Towers, which shall be finally connected to the external sewerage system as per the master plan. Centralized sewage Treatment plant shall be consisting of a flushing water distribution ring, from which a connection shall be taken to the filled the UG Flushing Water Storage Tank. Although it is already treated water, ultra filtration will be done at the site to meet the government parameters. In case of STP Failure, row water from the pluming plant room shall be transferred to flushing water tank with dedicated transfer pumps installed in plumbing plant room.
13Solid Waste Management And Disposal System
Collection, Storage and disposal will be done manually , and disposal will be done as per norms.
14Water Conservation System
Re use STP treated water for flushing, colling tower make-up and landscaping purpose. Use of Low Flow of waterless fixtures with aerator head. Use of Sensor operated taps and Urinals and Duel Flush WCs in common Toilets. Use of Digital water Meters at each major consumption point. Use of drought resistant and native species of plants. Use of Drip irrigation of Micro Irrigation techniques for landscaping.
15Energy Management System Including Use of Renewable Energy
In compliance to ECBC norms, approx. 60 kWp Solar power needs to be generated. It is proposed to plan Solar PVs at Tower roof. Solar PV shall be provided facing south on the roof. it will be synchronized with main grid power supply for utilization within the building during the day. No net Metering with utility Grid is being envisaged.
16Fire Protection And Fire Safety System
The Fire Protection system is designated to provide Life safety of occupants by means of providing early warning for complete evacuation, activation of extinguishing system and timely information to occupants inline with part 4 of NBC 2016. The following fire fighting system have been proposed- Hydrant System Automatic Sprinkler System Fire Extinguishers. Fire Hose Reels Fire Alarm and Detection System Fire Pumps Water Storage Tanks Emergency Lighting and Signage Fore Doors and Partitions
17Social Infrastructure And Other Public Amenities Including Public Health Services
Social gathering places in the community building are being provided.
18Emergency Evacuation Services
YES, Refuge area provided at every Tower on 15th , 23rd, 31st and 39th floor in addition to Main and Fire Staircase.
19Other Miscellaneous Work
Proper Security System including Security Guards, CCTV Cameras and controlled access will be made available.
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 4 Feb 2030.

Sanctioned by Greater Noida Authority · 15,432 sqm of land. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
PLG/BP SM-10-JUL-2024.219215 Feb 20254 Feb 20304 Feb 20354 Feb 2030
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗

Land & documents

18 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
C-01, Land-II, Integrated Sports Complex at Jaypee Greens , Sector 26 and 31, Surajpur Kasana Road, Greater Noida, Gautam Buddha Nagar, Uttar Pradesh, PIN- 20131015432Plot
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Lease deed · Lease Deed No. 2938-2939
The deed by which a development authority leased the land to the promoter, with the term and the conditions on it.
PDF ↗
Allotment letter from the authority · Allotment Letter No. 2000/270
The development authority’s letter allotting the plot - usually the step before a lease deed is executed.
PDF ↗
Allotment letter from the authority · Possession Letter No. 2000/275
The development authority’s letter allotting the plot - usually the step before a lease deed is executed.
PDF ↗
Allotment letter from the authority · Assignment Agreement No. 1645
The development authority’s letter allotting the plot - usually the step before a lease deed is executed.
PDF ↗
Allotment letter from the authority · Land No Dues Certificate from GNIDA
The development authority’s letter allotting the plot - usually the step before a lease deed is executed.
PDF ↗
Allotment letter from the authority · The Peridona Reply Letter to UP RERA regarding Objection Letter Dated-04.03.2025
The development authority’s letter allotting the plot - usually the step before a lease deed is executed.
PDF ↗
Document checklist
DocumentStatusUploaded
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
General body resolution
The resolution authorising an apartment owners’ association to act as the registering entity.
not reported—
Affidavit on balance development work
The promoter’s sworn statement about the development work still to be finished.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New18 Feb 2025 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New18 Feb 2025 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New18 Feb 2025 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New18 Feb 2025 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New18 Feb 2025 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New18 Feb 2025 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New18 Feb 2025 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New18 Feb 2025 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New16 Apr 2025 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New18 Apr 2025 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New18 Apr 2025 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New18 Apr 2025 ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
New16 Apr 2025 ↗
Agreement for sale (proforma)
The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind.
New18 Feb 2025 ↗

Quarterly progress reports

6 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

6 quarterly progress reports are on file with UPRERA, covering 2024-Q4 to 2026-Q1.

QuarterConstructionCertificates
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q20%CA ↗ · Arch ↗ · Eng ↗
2025-Q31%CA ↗ · Arch ↗ · Eng ↗
2025-Q41%CA ↗ · Arch ↗ · Eng ↗
2026-Q12%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameCRC Greens Private Limited
RolePromoter · current
RERA IDUPRERAPRM347558
PANAALCC5655P
CIN / TANDELC26067G
Name of chairmanSatish Garg
Registered addressRegd. Office - 111VardhmanMayurMarketCSC, MayurViharPhase3 Gharoli, East Delhi, East Delhi, East Delhi, Delhi, India, 110096 Corporate Office- Ground Floor, Tower-A, Logix Techno Park, Sec-127, Noida, Gautam Buddha Nagar, Uttar Pradesh, PIN-201301
RERA contact
Registered since2025
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.
Legal nameAdani Infrastructure Integrated Solutions Limited (formerly known as Jaiprakash Associates Limited)
RoleCo-promoter · current
RERA IDUPRERAPRM6273
Applicant typeCompany
PANAABCB1562A
CIN / TANL14106UP1995PLC019017
Name of chairmanSh. Manoj Gaur
Registered addressSector - 128, Noida - 201304, Uttar Pradesh (India)
RERA contact
Registered since2017

Nearby projects

Gautam Budh Nagar

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
CRCGPL Col A/C for The Peridona C-1 Jaypee GreensBankKotak Mahindra Bank LimitedBranchSector 18, NOIDABranch addressAnsals Fortune Arcade, Sector- 18, NOIDA, Gautam Buddha Nagar, Uttar Pradesh, PIN- 201301Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCKKBK0005033Branch emaildeepa.handa@kotak.com
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
CRCGPL Sep Bank A/C for The Peridona C-1 Jaypee GreensBankKotak Mahindra Bank LimitedBranchSector-18, NOIDABranch addressAnsals Fortune Arcade, Sector-18, NOIDA, Gautam Buddha Nagar, Uttar Pradesh, PIN-201301Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCKKBK0005033
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
CRCGPL RERA Tran A/C for The Peridona C-1 Jaypee GreensBankKotak Mahindra Bank LimitedBranchSector-18, NOIDABranch addressAnsals Fortune Arcade, Sector-18, NOIDA, Gautam Buddha Nagar, Uttar Pradesh, PIN- 201301Branch districtGautam Buddha Nagar, Uttar PradeshA/C no.IFSCKKBK0005033
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about The Peridona C-1 Jaypee Greens

Is The Peridona C-1 Jaypee Greens RERA registered?

Yes. The Peridona C-1 Jaypee Greens is registered with UPRERA under registration number UPRERAPRJ298067, registered on 16 May 2025. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for The Peridona C-1 Jaypee Greens?

The completion date filed with UPRERA is 4 Feb 2030. No completion certificate is on record yet.

Who is the builder of The Peridona C-1 Jaypee Greens?

CRC Greens Private Limited is the promoter entity that filed The Peridona C-1 Jaypee Greens with UPRERA (promoter RERA ID UPRERAPRM347558). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does The Peridona C-1 Jaypee Greens have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is The Peridona C-1 Jaypee Greens located?

The Peridona C-1 Jaypee Greens is registered in Jaypee Greens, Sector 26 & 31, Greater Noida, Gautam Budh Nagar, as filed with UPRERA.

What configurations are available in The Peridona C-1 Jaypee Greens?

The unit plan filed with UPRERA lists 5 BHK, OTHER and 4 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in The Peridona C-1 Jaypee Greens?

The approved unit plan filed with UPRERA runs from 275 to 906 m² of carpet area (about 2,962 to 9,756 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗