Timeline Bar
Timeline
Registration & Cost Details
Inventory
Promoters & Contact
Contact Details
No promoter data available.
Quarterly Progress Reports
Permit & Extension History
| Permit Number | Permit Date | Valid Upto | Revised End Date | Extended Upto |
|---|---|---|---|---|
| Plotted Resi development / Plotted Housing/03218/AFDA/LD/24-25/0398/090720 | 4 Sept 2024 | 3 Sept 2029 | 30 Jun 2028 | 3 Sept 2032 |
Land Parcels
| Khasra No. | Area | Plot Type |
|---|---|---|
| 77, 78, 79, 80, 81, 82, 83, 84, 85, 86, 87, 88, 89, 90, 91, 92, 93, 94, 95, 96, 1442 VA/5, 1442 BA/1, 1442 Mi | 32415.75 | Khasra |
Frequently Asked Questions
What is the RERA registration number of The Sarayu 4?
The RERA registration number of The Sarayu 4 is UPRERAPRJ397318, as recorded on the UP-RERA portal.
What is the RERA status of The Sarayu 4?
As reported by UP-RERA, the status of The Sarayu 4 is "Registered".
Where is The Sarayu 4 located?
As reported to UP-RERA, The Sarayu 4 is located at Gata No. - 77, 78, 79, 80, 81, 82, 83, 84, 85, 86, 87, 88, 89, 90, 91, 92 , 93 , 94, 95 , 96 , 1437 VA/2 , 1442MI , 1442 VA/5 & 1442 BA/1, Ayodhya, Sadar(Faizabad), Ayodhya, Uttar Pradesh.
When will The Sarayu 4 be completed?
The latest completion date reported to UP-RERA for The Sarayu 4 is 30 Jun 2028.
Is The Sarayu 4 delayed?
Measured against the latest completion date reported to UP-RERA, The Sarayu 4 is on time.
Answers generated from this project's public UP-RERA record — data as reported by RERA.
Data as reported by RERA. View source · Scraped 3 Aug 2026