Timeless is a RERA-registered residential project by Aakansha Infratech in Mastemau, Lucknow (RERA ID UPRERAPRJ730763). Registered with a completion deadline of 6 Mar 2031.

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ730763
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryLucknow Development Authority
Proposed start20 Mar 2026
Project duration60 months
AddressPlot No GH-01(A) Sec-1, Pocket-2 in Pintail Park City at Village-Mastemau, Tehsil-Mohanlalganj, District-Lucknow, Mastemau, Mohanlalganj, Lucknow
TehsilMohanlalganj
Applicant typePartnership Firm
Applicant address83, Nehru Nagar, Agra-282002
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    Group Housing/18451/LDA/BP/25-26/1656/10032026

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered3 Jun 2026
Original completion6 Mar 2031
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹35,000
Sanctioning authorityLucknow Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors252 · 3 · 23 (units from plan)
ConfigurationUnitsCarpet area
3 BHK25287-90
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
TOWER-A · 3 BHK, OTHER238487-88
TOWER-B · 3 BHK, OTHER238487-88
TOWER-C · 3 BHK, OTHER238490
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Mrs. Kalyani Sharma
License CA/2016/73547
01, Bilhaur, Kanpur Nagar, U.P., 209202
Engineer
Mr. Sanjay Sharma
A-99, Shyam Nagar, Jaipur, Rajasthan, 302019
Contractor
All India Infra Build Well
Shop no 2, 2nd floor, Kaveri Center, Sanjay Place, Agra 282002
Sr.Development work declared to RERA
1Demarcation of Plots
We have one plot of size 6000 sq. mtr.having 1 main entrance gate from the 30 m wide front road.
2Boundary Wall
2 m high and 230 mm thick Brick work and rcc work in column and beam. At the center face of boundary wall there would be a Logo of the project which give a beautiful iconic design to boundary wall. Length of boundry wall will be 300 mtrs.
3Road Work
From the main entrance gate we have 80 mm thick interlocking brick /RCC road through out the project. Whose wideness starts from 10 mtr and level 450 mm fron NGL
4Footpaths
We would not provide any footpath
5Water Supply Including Drinking Water Facilities
We will provide Two nos. of pump for the requirement of blocks through underground pipelines. Water Tank Capacity- Domestic Tank-125 kl, RAW Water Tank 125 kl, Fire Water Tank (2*100 kl) 200kl , Total capacity 450 kl
6Sewer System
Modular Sewerage system shall be Provided. All Sewerage water shall be go to the STP and overflow from the STP shall be connect with the Municipal sewerage system.when come into force. STP Capacity will be 115 KLD.
7Drain
Storm water shall be Provided. Storm water from Roads and other landscape area shall be connect to the Storm water drain channel and go to the two Rain water harvesting Pit(36 cum each) for recharge the Ground water and overflow shall be connect with Municipal drain line.
8Parks
We will provide green area with the different activities and the green area will have gaming facilities for kids.
9Tree Planting
We will provide many type of trees all along the boundary wall & green area.
10Design For Electric Supply Including Street Lighting
We will design & implement the system as per local electricity Board and will consider centralized Transformer(2*630KVA), HT panel, LT Panel, Feeder Pillar and DG(125 KVA) back for common service like External lighting, Fountain, STP, Pump room etc. Transformer(2*630KVA or 3*400 kva as per lesa)
11Community Buildings
Community building will be provided as per sanctioned map
12Treatment and Disposal System of Sewage and Sullage water
Modular Sewerage system shall be Provided. All Sewerage water shall be go to the STP (115KL)and overflow from the STP shall be connect with the Municipal sewerage system.,when come into force. STP Capacity will be 115 KLD.
13Solid Waste Management And Disposal System
There are a proper garbage collection area provided for the solid waste management.
14Water Conservation System
We will suggest to individual to use low flow fixtures as well dual flush cistern and raw water harvesting system to reduce the water consumption and improve the ground water level.
15Energy Management System Including Use of Renewable Energy
We will use LED lights fitting in external area as well as solar lights. In Pump room also all the equipment shall have energy efficient motor. And we will suggest to individual also to use.
16Fire Protection And Fire Safety System
We will provide Fire Fighting facility in common areas while Individual owner can install their own system as per their and local authorities requirement.
17Social Infrastructure And Other Public Amenities Including Public Health Services
NA
18Emergency Evacuation Services
We will have staircases which will be provided with emergency exit doors and emergency exit gates
19Other Miscellaneous Work
NA
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Registered agents

6 agents

Agents the promoter filed against this project. A filing, not a recommendation, and not a statement that the registration is still valid.

Sr.AgentRERA registration
1GLICKMAN REALTORS PRIVATE LIMITEDUPRERAAGT25027
2MANGALGRUHUM REALTY PRIVATE LIMITEDUPRERAAGT24450
3MO SHAMSHAD KHANUPRERAAGT23717
4Narendra SinghUPRERAAGT14206
5star estateUPRERAAGT10202
6VAAP ESTATE PRIVATE LIMITEDUPRERAAGT23033
Agents as filed against this project. The grid does not say whether a registration is still valid, so no validity is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 9 Mar 2031.

Sanctioned by Lucknow Development Authority · 6,000 sqm of land · an approved plan of 3 blocks and 252 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
Group Housing/18451/LDA/BP/25-26/1656/1003202610 Mar 20269 Mar 20319 Mar 20346 Mar 2031
Plans and approvals filed with RERA
DocumentFile
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
no file published
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗

Land & documents

16 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
Plot No GH-01(A) Sec-1, Pocket-2 in Pintail Park City6000Plot
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Sale deed · Sale Deed no. 15245
The registered deed by which the promoter bought the land.
PDF ↗
Registry document · Correction Deed no. 44343
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Khatauni extract · Khatauni 1430-1435
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Registry document · Consortium no. 699
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · Consortium addendum Agreement no. 64
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Khatauni extract · Conversion of Pintail Infracon Pvt Ltd to Pintail Infracon LLP
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · Flow of Land
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · Arindam-Pintail-Name Change Certificate
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Document checklist
DocumentStatusUploaded
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
not reported—
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New6 Apr 2026 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New3 Apr 2026 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New3 Apr 2026 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New6 Apr 2026 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New3 Apr 2026 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New3 Apr 2026 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New3 Apr 2026 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New3 Apr 2026 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New3 Apr 2026 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New6 Apr 2026 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New6 Apr 2026 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New6 Apr 2026 ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
New3 Apr 2026 ↗
Agreement for sale (proforma)
The blank sale agreement filed with the authority. It is the document a buyer signs, so the clauses in it are the ones that bind.
New6 Apr 2026 ↗

Quarterly progress reports

2 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

2 quarterly progress reports are on file with UPRERA, covering 2025-Q4 to 2026-Q1.

QuarterConstructionCertificates
2025-Q40%CA ↗ · Arch ↗ · Eng ↗
2026-Q10%CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameAakansha Infratech
RolePromoter · current
RERA IDUPRERAPRM171178
PANABOFA7191B
CIN / TANAGRA15315G
Registered address83, Nehru Nagar, Agra-282002
RERA contact
Registered since2022
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.

Nearby projects

Lucknow

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
AAKANSHA INFRATECH COLLECTION ACC TIMELESSBankCanara BankBranchHazratganj, LucknowBranch addressKASMANDA HOUSE, GROUND FLOOR, PARK ROAD, HAZRATGANJ LUCKNOW - 226001 (UTTAR PRADESH)Branch districtLucknow, Uttar PradeshA/C no.IFSCCNRB0018504Branch emailcb18504@canarabank.com
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
AAKANSHA INFRATECH SEPARATE ACC TIMELESSBankCanara BankBranchHazratganj, LucknowBranch addressKASMANDA HOUSE, GROUND FLOOR, PARK ROAD, HAZRATGANJ LUCKNOW - 226001 (UTTAR PRADESH)Branch districtLucknow, Uttar PradeshA/C no.IFSCCNRB0018504
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
AAKANSHA INFRATECH TRANSACTION ACC TIMELESSBankCanara BankBranchHazratganj, LucknowBranch addressKASMANDA HOUSE, GROUND FLOOR, PARK ROAD, HAZRATGANJ LUCKNOW - 226001 (UTTAR PRADESHBranch districtLucknow, Uttar PradeshA/C no.IFSCCNRB0018504
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about Timeless

Is Timeless RERA registered?

Yes. Timeless is registered with UPRERA under registration number UPRERAPRJ730763, registered on 3 Jun 2026. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for Timeless?

The completion date filed with UPRERA is 6 Mar 2031. No completion certificate is on record yet.

Who is the builder of Timeless?

Aakansha Infratech is the promoter entity that filed Timeless with UPRERA (promoter RERA ID UPRERAPRM171178). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does Timeless have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is Timeless located?

Timeless is registered in Mastemau, Lucknow, as filed with UPRERA.

What configurations are available in Timeless?

The unit plan filed with UPRERA lists 3 BHK and OTHER. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in Timeless?

The approved unit plan filed with UPRERA runs from 87 to 90 m² of carpet area (about 934 to 973 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in Timeless?

The approved unit plan describes 3 blocks and 252 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is Timeless?

About 170 units per acre: 252 planned units across 1.48 acres (6,000 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗