Estanzo

Timeline Bar

Registered3 Jun 2026
Today29 Jul 2026
Promised6 Mar 2031

Timeline

Promised completion6 Mar 2031
Revised completion6 Mar 2031
Actual completion
Possession delayOn time

Registration & Cost Details

Registration fee (in ₹)₹35,000
Project cost (in ₹ Lakhs)₹13,414 Lakhs
Project duration60 months
Project categoryResidential
LocalityMastemau
Original start date
Proposed start date20 Mar 2026

Inventory

Total units252
Unit TypeUnitsCarpet Area (sqm)
3 BHK25286.8–90.4

Promoters & Contact

Contact Details

Applicant TypePartnership Firm
Mobile9897434797
Emailexec.dir@yttgroup.co.in
Coordinator7060959088
Address83, Nehru Nagar, Agra-282002

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2025-Q40.0%
2026-Q10.0%

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
Group Housing/18451/LDA/BP/25-26/1656/1003202610 Mar 20269 Mar 20316 Mar 20319 Mar 2034

Land Parcels

Khasra No.AreaPlot Type
Plot No GH-01(A) Sec-1, Pocket-2 in Pintail Park City6000Plot

Approved Unit Plan

Unit plan rows on file132
Total flats (sum of rows)252
BlocksTOWER-A, TOWER-B, TOWER-C
Floor types3 BHK, OTHER

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of Timeless?

The RERA registration number of Timeless is UPRERAPRJ730763, as recorded on the UP-RERA portal.

What is the RERA status of Timeless?

As reported by UP-RERA, the status of Timeless is "Registered".

Where is Timeless located?

As reported to UP-RERA, Timeless is located at Plot No GH-01(A) Sec-1, Pocket-2 in Pintail Park City at Village-Mastemau, Tehsil-Mohanlalganj, District-Lucknow, Mastemau, Mohanlalganj, Lucknow, Uttar Pradesh.

When will Timeless be completed?

The latest completion date reported to UP-RERA for Timeless is 6 Mar 2031.

Is Timeless delayed?

Measured against the latest completion date reported to UP-RERA, Timeless is on time.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 28 Jul 2026