Timeline Bar
Registered15 Aug 2017
Promised12 Jun 2020
Completed8 May 2025
Timeline
Promised completion12 Jun 2020
Revised completion12 Jun 2020
Actual completion8 May 2025
Possession delay59 mo delay
Registration & Cost Details
Registration fee (in ₹)₹45,000
Project cost (in ₹ Lakhs)₹2,559 Lakhs
Project duration65 months
Project categoryResidential
Locality—
Original start date1 Aug 2015
Proposed start date1 Aug 2015
Inventory
Total units122
| Unit Type | Units | Carpet Area (sqm) |
|---|---|---|
| 2 BHK | 72 | 80.826 |
| 3 BHK | 32 | 112.877–119.845 |
| 4 BHK | 18 | 147.716 |
Promoters & Contact
Contact Details
Applicant TypeCompany
Mobile9927016371
Emailtwintoweragra@gmail.com
Coordinator9412271017
AddressShop no. 6, Block no. C15, Sanjay Place, Agra
No promoter data available.
Quarterly Progress Reports
Permit & Extension History
| Permit Number | Permit Date | Valid Upto | Revised End Date | Extended Upto |
|---|---|---|---|---|
| 1718/B.F.T./2/10-11 | 14 Jun 2012 | 14 Jun 2017 | 12 Jun 2020 | 13 Jun 2020 |
Land Parcels
| Khasra No. | Area | Plot Type |
|---|---|---|
| 159 | 7983 | — |
| 159( part) | 2661 | Khasra |
| 159( part) | 2661 | Khasra |
| 159( part) | 2661 | Khasra |
Approved Unit Plan
Unit plan rows on file40
Total flats (sum of rows)122
BlocksTwin Tower Block A, Twin Tower Block B
Floor types2 BHK, 3 BHK, 4 BHK, OTHER
Individual floor/unit rows are not listed here.
Registry & Agreement Filings
| Registry Number | Registry Date | Land Type | Area |
|---|---|---|---|
| 1511 | 17 Mar 2012 | — | — |
| 1512 | 17 Mar 2012 | — | — |
| 1513 | 17 Mar 2012 | — | — |
Frequently Asked Questions
What is the RERA registration number of Twin Tower?
The RERA registration number of Twin Tower is UPRERAPRJ11125, as recorded on the UP-RERA portal.
What is the RERA status of Twin Tower?
As reported by UP-RERA, the status of Twin Tower is "Registered".
Where is Twin Tower located?
As reported to UP-RERA, Twin Tower is located at Agra, Agra, Uttar Pradesh.
Is Twin Tower completed?
As reported to UP-RERA, Twin Tower was completed on 8 May 2025.
Is Twin Tower delayed?
Measured against the latest completion date reported to UP-RERA, Twin Tower is 59 months beyond that date.