VAIBHAV SIGNATURE

UPRERARegistered

VAIBHAV SIGNATURE is a RERA-registered commercial project by VAIBHAV INFRACITY PRIVATE LIMITED in Varanasi (RERA ID UPRERAPRJ944473). Registered with a completion deadline of 29 Feb 2024. UP-RERA flags this project "Default on QPR": it has not filed its mandatory quarterly progress report(s).

Summarize this record with:ChatGPTPerplexityClaudeGrok
RERA status as reported: Registered.

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ944473
Project categoryCommercial
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryVaranasi Development Authority
Proposed start1 Sept 2019
Project duration54 months
AddressVaranasi, Varanasi
TehsilVaranasi
Applicant typeCompany
Applicant address72- GOKUL NAGAR VARANASI
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    258/1

  2. Registered with RERA

  3. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  4. to

    Extension granted

    “Six months extension in view of force majeure caused by covid-19 pandemic”

  5. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  6. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly reports are in default on this project’s record.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered2 Jul 2019
Original completion30 Aug 2023
Revised completion29 Feb 2024
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹12,160
Sanctioning authorityVaranasi Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors18 · 1 · 5 (units from plan)
Homes · commercial units7 · 11 (shops and offices filed in the same plan)
  • SHOP11 61%
  • STUDIO7 39%
ConfigurationUnitsCarpet area
SHOP11183-216
STUDIO7172
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
VAIBHAV SIGNATURE · OTHER, SHOP, STUDIO518172-216
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
NITIN RAJ AND ASSOCIATES
License CA/2010/49248
L-6/59,SHASTRI NAGAR ,VARANASI
Engineer
SATYA RAJ SHARAN
VARANASI
Contractor
SANTOSH KUMAR SINGH
NASIRPUR,VARANASI
Sr.Development work declared to RERA
1Demarcation of Plots
DONE
2Boundary Wall
AS PER QUATERLY PLAN GIVEN
3Road Work
N.A
4Footpaths
N.A
5Water Supply Including Drinking Water Facilities
N.A
6Sewer System
N.A
7Drain
N.A
8Parks
N.A
9Tree Planting
N.A
10Design For Electric Supply Including Street Lighting
AS PER QUTERLY PLAN
11Community Buildings
N.A
12Treatment and Disposal System of Sewage and Sullage water
N.A
13Solid Waste Management And Disposal System
N.A
14Water Conservation System
N.A
15Energy Management System Including Use of Renewable Energy
N.A
16Fire Protection And Fire Safety System
AS PER QUARTERLY PLAN WILL BE DONE
17Social Infrastructure And Other Public Amenities Including Public Health Services
N.A
18Emergency Evacuation Services
WILL BE DONE AS PER CONSTRUCTION DESIGHN
19Other Miscellaneous Work
NO
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 29 Nov 2023.

Sanctioned by Varanasi Development Authority · 608 sqm of land · an approved plan of 1 block and 18 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
258/130 Nov 201829 Nov 202329 May 202430 Aug 2023
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗
Completion extensions grantedExtensionMore time granted against a project’s registered completion date, on the promoter’s application.Read the full entry in the glossary

UPRERA’s record carries 1 completion extension for this project, running to 29 Feb 2024.

#Granted fromExtended uptoNote
130 Aug 202329 Feb 2024Six months extension in view of force majeure caused by covid-19 pandemic

Land & documents

13 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Registry document · 1732/18
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Document checklist
DocumentStatusUploaded
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New20 May 2019 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New20 May 2019 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New20 May 2019 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New20 May 2019 ↗
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
New20 May 2019 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New20 May 2019 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New20 May 2019 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New20 May 2019 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New20 May 2019 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New20 May 2019 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New20 May 2019 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New20 May 2019 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New20 May 2019 ↗

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameVAIBHAV INFRACITY PRIVATE LIMITED
RolePromoter · current
RERA IDUPRERAPRM25084
PANAAFCV2667J
CIN / TANU70102UP2015PTC073880
Name of chairmanRAMESH KUMAR JAISWAL
Registered address72- GOKUL NAGAR VARANASI
RERA contact
Registered since2017
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.
Legal nameRAJ KUMAR PATEL
RoleCo-promoter
Applicant typeIndividual
AddressN-2/25-CH,SUNDERPUR,VARANASI.
RERA contact

Nearby projects

Varanasi

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

One bank account is filed for this project; UPRERA publishes no three-account breakdown for it. What is filed is the account, not what is in it.

AccountAs filed with RERA
Bank account as filed
ARVIND JAISWALBankICICI BANK LTD.BranchDLWA/C no.IFSCICIC0003512
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

nothing recorded yet

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026. Nothing has moved since. Anything that changed before that date is not on this list.

These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

3 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No khasra or plot detail is published for this project.Ask which khasra numbers the project stands on, so the plot can be matched against the deed and the revenue record.
  • No quarterly progress report is published for this project.Ask the promoter for the latest quarterly report filed and the construction percentage certified in it.
  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about VAIBHAV SIGNATURE

Is VAIBHAV SIGNATURE RERA registered?

Yes. VAIBHAV SIGNATURE is registered with UPRERA under registration number UPRERAPRJ944473, registered on 2 Jul 2019. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for VAIBHAV SIGNATURE?

The completion date filed with UPRERA is 29 Feb 2024. No completion certificate is on record yet.

Who is the builder of VAIBHAV SIGNATURE?

VAIBHAV INFRACITY PRIVATE LIMITED is the promoter entity that filed VAIBHAV SIGNATURE with UPRERA (promoter RERA ID UPRERAPRM25084). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Why does VAIBHAV SIGNATURE show "default on QPR"?

UPRERA flags this project as in default on quarterly progress reporting - the promoter has not filed one or more mandatory quarterly progress reports. The flag is the authority's, not Estanzo's.

Has UPRERA granted VAIBHAV SIGNATURE more time to complete?

UPRERA's record carries 1 completion extension for VAIBHAV SIGNATURE, the latest running to 29 Feb 2024. Applying for an extension is a step the RERA Act provides for; the filing records the dates and whatever note accompanied it, and nothing more.

Does VAIBHAV SIGNATURE have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is VAIBHAV SIGNATURE located?

VAIBHAV SIGNATURE is registered in Varanasi, as filed with UPRERA.

What configurations are available in VAIBHAV SIGNATURE?

The unit plan filed with UPRERA lists OTHER, SHOP and STUDIO. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in VAIBHAV SIGNATURE?

The approved unit plan filed with UPRERA runs from 172 to 216 m² of carpet area (about 1,851 to 2,325 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in VAIBHAV SIGNATURE?

The approved unit plan describes 1 block and 18 units of which 7 are homes and 11 are commercial units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is VAIBHAV SIGNATURE?

About 120 units per acre: 18 planned units across 0.15 acres (608 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗