Construction progress

As filed in quarterly progress reports · % complete · latest filed Apr–Jun 2026
Quarters shown are calendar quarters. UP-RERA files them by financial year.
—Q4'24
—Q1'25
—Q2'25
33%Q3'25
38%Q4'25
59.5%Q1'26
59.5%Q2'26
—Q3'26

Basic details

The promoter’s own descriptions, published as filed. UP-RERA does not certify them.

RERA IDRERA registration numberThe unique number the authority assigns to a registration - UPRERAPRJ… for a project, UPRERAPRM… for a promoter.Read the full entry in the glossaryUPRERAPRJ107791
Project categoryResidential
Registration typeNew
RERA statusRegistered
Sanctioning authoritySanctioning authorityThe local body that approved the building and layout plans - not RERA.Read the full entry in the glossaryMuzaffarnagar Development Authority
Proposed start20 Jan 2023
Project duration69 months
AddressMuzaffarnagar, Muzaffarnagar
TehsilMuzaffarnagar
Applicant typePartnership Firm
Applicant addressVasundhara Residency, Parikarma Marg Near Shri Ram College , Muzaffarnagar- 251002
Applicant contact

Project timeline

Every dated filing on this project’s record, oldest first. A diamond is a date that was a plan, not something that happened.

  1. Building permit sanctioned

    Group Housing/00861/mzda/bp/20-21/0503/02092021

  2. Construction start, as declared

    A date on the record, not a filing — what was planned as of this entry.

  3. Registered with RERA

  4. Completion promised at registration

    A date on the record, not a filing — what was planned as of this entry.

  5. Revised completion deadline

    A date on the record, not a filing — what was planned as of this entry.

Published without a date
UPRERA lists this project as Registered. A completion certificate on the record does not change that — RERA accepts them tower by tower, and only this status says a project is complete.
Quarterly report cadence
FY 2022-23
Q1Q2Q3Q4
FY 2023-24
Q1Q2Q3Q4
FY 2024-25
Q1Q2Q3Q4
FY 2025-26
Q1Q2Q3Q4
FY 2026-27
Q1Q2Q3Q4

A filled quarter means a report reached the record. An empty one is a quarter with nothing filed — not a quarter of no work.

Registration & timeline

Dates on the registration itself, not on construction - the quarterly reports carry that.

RERA registered24 Mar 2023
Original completion18 Oct 2028
Revised completion— none granted
First completion certificate filedCompletion certificate (CC)The certificate saying a project has been built as sanctioned - not the same as permission to move in.Read the full entry in the glossary- not on record
Registration fee₹92,000
Sanctioning authorityMuzaffarnagar Development Authority

Inventory

derived from unit plan

The approved unit plan, not an availability list: nothing here says what is unsold.

Total units · towers · floors406 · 6 · 7 (units from plan)
  • 3 BHK364 90%
  • 4 BHK42 10%
ConfigurationUnitsCarpet area
4 BHK42119-120
3 BHK36470-106
Tower by tower, as filed
TowerFloorsUnitsCarpet area m²Carpet areaThe net usable floor area inside a flat - the area you could lay a carpet on.Read the full entry in the glossary
BLOCK A · 4 BHK742119-120
BLOCK B · 3 BHK798105-106
BLOCK C · 3 BHK75692-94
BLOCK D · 3 BHK75692-94
BLOCK E · 3 BHK75692-94
BLOCK F · 3 BHK79870-76
Areas are carpet area. For built-upBuilt-up areaCarpet area plus the walls and usually the balcony - a larger number, and one RERA does not define.Read the full entry in the glossary or super areaSuper areaBuilt-up area plus a share of the common space - the largest of the three numbers.Read the full entry in the glossary, check with the builder.The plan also files 944.07 m² for a 3 BHK, far outside the rest of that type, so the ranges above leave it out.

Project team & development works

Who was engaged and what was promised. No status is filed against any of it.

Architect
Radhika Bansal
License CA/2017/88637
Muzaffarnagar
Engineer
Ashraf Ali
B-6, B-7, Aish Plaza, Madical Road, Aligarh
Contractor
Rahul Chokkar
Ghaziabad
Sr.Development work declared to RERA
1Demarcation of Plots
Group housing at plot no-194, 196, 197, 2170, 2171, 2177, agarsain marg , village- sahawal and surju, muzaffarnagar.
2Boundary Wall
2M HIGH AND 230MM THICK BRICK WORK IN COLUMN AND BEAM. AT THE CENTRE FACE OF THE BOUNDARY WALL THERE WOULD BE A LOGO OF THE PROJECT WHICH GAVE A BEAUTIFULL DESIGN TO BOUNDARY WALL
3Road Work
FROM THE MAIN ENTRANCE GATE WE HAVE 80MM THICK INTERLOCKING BRICK ROAD THROUGH OUT THE PROJECT. WHOSE WIDENESS STARTS FROM 10MTR .ALL ROAD IN THE COMPLEX WILL BE INTERLOCKING.
4Footpaths
FROM THE MAIN ENTRANCE GATE WE HAVE 60MM THICK INTERLOCKING BRICK FOOTHPATH THROUGH OUT THE PROJECT .WHOSE WIDENESS STARTS FROM 8MTR . ALL FOOTPATH IN THE COMPLEX WILL BE INTERLOCKING.
5Water Supply Including Drinking Water Facilities
WE WILL PROVIDE WATER SUPPLY FOR THE REQUIREMENT OF ALL BLOCKS THROUGH UNDERGROUND TANK WHICH WILL GETWATER SUPPLY FROM WATER SUPPLY LINES GIVEN TO US BY (RCC Tank capacity 12000 x 9= 108000 liture.)
6Sewer System
MODULAR SEERAGE SYSTEM SHALL BE PROVIDED. ALL SEWERAGE WATER SHALL BE GO TO THE STP AND OVERFLOW FROM THE STP SHALL BE CONNECT WITH THE MUNICIPAL SEWERAGE SYSTEM. WHEN COME INTO FORCE.
7Drain
STORM WATER SHALL BE PROVIDED. STORM WATER FROMROADS AND OTHER LANDSCAPE AREA SHALL BE CONNECT TO THE STORM WATER DRAIN CHANNELAND GO TO THE RAIN WATER HARVESTING PIT FOR RECHARGE THE GROUNG WATER AND OVERFLOW SHALL BE CONNECT WITH MUNICIPAL DRAIN LINE . WE PROVIDE RCC DRAIN IN WHOLE PROJECT.
8Parks
15 PERCENT park with Greenry+ Plantation
9Tree Planting
WE WILL PROVIDE MANY TYPES OF TREEALL ALONG THE BOUNDARY WALL GREEN AREAS (3 mitr distancing Tree to Tree)
10Design For Electric Supply Including Street Lighting
WE WILL DESIGN AND IMPLEMENT THE SYSTEM AS PER LOCAL ELECTRICITY BOAR AND WILL CONSIDERCENTRALIZED TRANSFORMER. HTPANEL, LT PANEL , FEEDER, PILLER AND DG BACKUP FOR COMMON SERVICES LIKE EXTERNAL LIGHTINGH, FOUNTAIN, STP PUMP ROOM ETC. WE PROVID ELECTRICITY SUPPLY THROUGH 11/10.433 KV Transformers and by DG SET Supply for backup
11Community Buildings
NOT APPLICABLE
12Treatment and Disposal System of Sewage and Sullage water
MODULAR SEWERAGE SYSTEM SHALL BE PROVIDED. ALL SEWERAGE WATER SHALL BE GO TO THE STP AND OVERFLOW FROM THE STP SHALL BE CONNECT WITH THE MUNICIPLA SEWERAGE SYSTEM, WHEN COMES INTO FORCE
13Solid Waste Management And Disposal System
Solid waste to be collected from individual flats and stored in garbage room, Recyclable shall be processed in the compost machine to make
14Water Conservation System
RAIN WATER HARVESTING PITS shall be provided for groundwater recharging and over flow to be discharged in the MUNICIPAL DRAIN TREATMENT SEWAGE
15Energy Management System Including Use of Renewable Energy
NA
16Fire Protection And Fire Safety System
SPRINKER FIRE DOORS YARD HYDRANT SMOKE DETECTERAND FIRE ALARM SYSTEM WILL BE PROVIDED AS APPLICABLE
17Social Infrastructure And Other Public Amenities Including Public Health Services
COMMON SOCIAL INFRASTRUCTURE SHALL BE PROVIDED FOR ALL THE PHASES COMBINED
18Emergency Evacuation Services
FIRE STAIRECASES SHALL BE PROVIDED AS PER THE APPROVED FIRE DRAWING FOR EXCAVATION TO OPEN AREAS
19Other Miscellaneous Work
NA
Works and their descriptions as declared to RERA. The filing carries no status or percentage per work, so none is shown

Permits & extensions

1 permit

An approval and the date it runs to - not proof the work matching it was done.

1 sanctioning permit is on record with UPRERA, valid to 18 Oct 2027.

Sanctioned by Muzaffarnagar Development Authority · 17,257 sqm of land · an approved plan of 6 blocks and 406 units. The plan totals are counted from what the promoter filed with RERA, not a figure the authority published as a total. See the approved unit plan

Permit no.DateValid uptoExtendable uptoRevised endDocuments filed
Group Housing/00861/mzda/bp/20-21/0503/0209202119 Oct 202218 Oct 202718 Oct 202918 Oct 2028
Plans and approvals filed with RERA
DocumentFile
Commencement certificate
The sanctioning authority’s permission to begin construction - the document that says work could lawfully start.
PDF ↗
Other plan
A plan the promoter filed that does not fall under the authority’s named headings.
PDF ↗

Land & documents

15 filings

How the promoter says it holds the land. Not a title search - nothing here confirms it is unencumbered.

KhasraKhasra numberThe number a piece of land carries in the state’s own revenue records.Read the full entry in the glossaryAreaType
194, 196, 197, 2170, 2171, 217717355Khasra
Land-title documentsLand-title documentThe paperwork showing how the promoter holds the land - a lease deed, a sale deed, an allotment letter, a khatauni extract.Read the full entry in the glossary
Registry document · 46288R
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 69408R
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 001440R
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Registry document · 47907S
The deed as registered with the sub-registrar, which is what proves the transfer took place.
PDF ↗
Lease deed · CONSORTIUM AGREEMENT
The deed by which a development authority leased the land to the promoter, with the term and the conditions on it.
PDF ↗
Khatauni extract · KHASRA 194
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · KHATAUNI 196, 197
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · KHASRA 2171
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · KHASRA 2170, 2177
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Khatauni extract · KHASRA 2170
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Allotment letter from the authority · 5033/2022
The development authority’s letter allotting the plot - usually the step before a lease deed is executed.
PDF ↗
Khatauni extract · LAND CHART DESCRIBED
An extract of the village land record showing the khasra plots and who is recorded against them.
PDF ↗
Document checklist
DocumentStatusUploaded
Encumbrance details
What the promoter declared is charged against the land - mortgages and other claims that would sit ahead of a buyer.
New12 Feb 2023 ↗
Application form (proforma)
The blank booking form the promoter filed - the terms a buyer would be asked to sign at booking.
New26 Jan 2023 ↗
Allotment letter (proforma)
The blank allotment letter on record - what the promoter said it would issue on booking.
New26 Jan 2023 ↗
Conveyance deed (proforma)
The blank deed by which title would eventually transfer to the buyer or the association.
New26 Jan 2023 ↗
Completion / occupancy certificate (proforma)
The blank form filed at registration. A proforma is a template on the record, not a certificate that has been issued.
New12 Feb 2023 ↗
Waste disposal plan
How the project proposed to handle sewage and solid waste, as filed at registration.
New12 Feb 2023 ↗
Water supply plan
How the project proposed to supply water, as filed at registration.
New12 Feb 2023 ↗
Electricity supply plan
How the project proposed to supply power, as filed at registration.
New12 Feb 2023 ↗
Development work plan
The internal development the promoter undertook to build - roads, drainage and the rest of the site works.
New26 Jan 2023 ↗
Affidavit (Form B)
The promoter’s sworn declaration to the authority at registration, including the undertaking about the project account.
New10 Feb 2023 ↗
Chartered accountant’s certificate
The CA’s certification of the money drawn from the project account against the stage of construction.
New10 Feb 2023 ↗
Architect’s certificate
The architect’s certification of the stage of construction reached - the professional basis for a quarterly percentage.
New26 Jan 2023 ↗
Engineer’s certificate
The engineer’s certification of the cost incurred on construction to date.
New26 Jan 2023 ↗
Other
A document the promoter filed under the authority’s catch-all heading; only the file itself says what it is.
New26 Jan 2023 ↗

Quarterly progress reports

15 filed reports

The promoter’s own statement, not an inspection. A blank quarter was not reported, not reported as nil.

15 quarterly progress reports are on file with UPRERA, covering 2022-Q4 to 2026-Q2.

QuarterConstructionCertificates
2022-Q4—CA ↗ · Arch ↗ · Eng ↗
2023-Q1—CA ↗ · Arch ↗ · Eng ↗
2023-Q2—CA ↗ · Arch ↗ · Eng ↗
2023-Q3—CA ↗ · Arch ↗ · Eng ↗
2023-Q4—CA ↗ · Arch ↗ · Eng ↗
2024-Q1—CA ↗ · Arch ↗ · Eng ↗
2024-Q2—CA ↗ · Arch ↗ · Eng ↗
2024-Q3—CA ↗ · Arch ↗ · Eng ↗
2024-Q4—CA ↗ · Arch ↗ · Eng ↗
2025-Q1—CA ↗ · Arch ↗ · Eng ↗
2025-Q233%CA ↗ · Arch ↗ · Eng ↗
2025-Q338%CA ↗ · Arch ↗ · Eng ↗
2025-Q459.5%CA ↗ · Arch ↗ · Eng ↗
2026-Q159.5%CA ↗ · Arch ↗ · Eng ↗
2026-Q2—CA ↗ · Arch ↗ · Eng ↗
This project’s record on the UPRERA portal ↗Each row is one quarterly progress reportQuarterly progress report (QPR)The return a promoter files with the authority each quarter, reporting how far the project has got.Read the full entry in the glossary as the promoter filed it. “-” means the quarter was not reported, not 0%. Construction percentages exist for filed quarters only; the most recent is 2026-Q1. A certificate opens the document filed for that quarter - the only part of a filing UPRERA publishes at an address of its own; the portal keeps the filing history itself behind the project record, under its QPR page.

Promoter (SPV) details

The legal entity carrying this project’s obligations. It may not be the brand it is marketed under.

Legal nameVASUNDHARA BUILDERS AND DEVELOPERS
RolePromoter · current
RERA IDUPRERAPRM217741
PANAARFV5722B
CIN / TANMRTV06431F
Registered addressVasundhara Residency, Parikarma Marg Near Shri Ram College , Muzaffarnagar- 251002
RERA contact
Registered since2023
The SPVSPV (special purpose vehicle)A company set up to hold and build one project, and nothing else.Read the full entry in the glossary's RERA-registered details. This is the promoterPromoterThe legal entity that registered the project with RERA and carries its obligations under the Act.Read the full entry in the glossary that filed the project, which may not be the brand it is marketed under.
Legal nameA TO Z BUILDERS AND DEVELOPERS.
RoleCo-promoter
Applicant typePartnership Firm
Address379- SOUTH CIVIL LINES , MUZAFFAR NAGAR-251002
RERA contact

Nearby projects

Muzaffarnagar

Straight-line distance between filed coordinates. Not a comparison and not a travel time.

Registered projects within 25 km, by straight-line distance from the coordinates each filed with RERA.

RERA bank accounts

verify before payment

Not confirmation that money is in these accounts, and details change - verify at the source before paying.

Under the Act’s 70% ruleThe 70% ruleThe RERA Act requires 70% of the money collected from a project’s buyers to sit in a separate bank account for that project’s land and construction cost alone.Read the full entry in the glossary, money collected from buyers is to be held in an account reserved for the project. UPRERA publishes what this promoter filed:

3 of the 3 account headings UPRERA publishes are filed for this project: collection, separate and transaction. What is filed is the account, not what is in it.

AccountAs filed with RERA
CollectionCollection accountOne of the three account types a UP-RERA project filing can carry, named “Collection” on the portal.Read the full entry in the glossary
Vasundhara Builders and Developers-Collection A/c. For Vaishali ResidencyBankPUNJAB NATIONAL BANKBranchVikas Bhawan BranchBranch addressMuzaffarnagarBranch districtMuzaffarnagar, Uttar PradeshA/C no.IFSCPUNB0684800
SeparateSeparate accountThe second of UP-RERA’s three filed account types, named “Separate” on the portal.Read the full entry in the glossary
Vasundhara Builders and Developers -Separate A/c. for Vaishali ResidencyBankPUNJAB NATIONAL BANKBranchVIKAS BHAWAN BRANCHBranch addressMUZAFFARNAGARBranch districtMuzaffarnagar, Uttar PradeshA/C no.IFSCPUNB0684800
TransactionTransaction accountThe third of UP-RERA’s three filed account types, named “Transaction” on the portal.Read the full entry in the glossary
Vasundhara Builders and Developers-Transaction A/c. For Vaishali ResidencyBankPUNJAB NATIONAL BANKBranchVIKAS BHAWAN BRANCHBranch addressMUZAFFARNAGARBranch districtMuzaffarnagar, Uttar PradeshA/C no.IFSCPUNB0684800
⚠ Verify against the official UPRERA source before any payment. Account details can change, never wire funds on this page alone.
Official RERA account page ↗

What has changed on this record

1 movement

When Estanzo first saw a difference - not proof RERA’s record changed that day.

Estanzo began recording changes to this record on 10 Aug 2026.

FieldWhat movedObserved
Quarterly progress report
2026-Q2
QPR 2026-Q2
newly filed with RERA
18 Oct 2026
These dates are Estanzo’s, not UPRERA’s. They say when Estanzo last saw a field move - not when the authority last checked it, and not when the underlying fact changed. UPRERA does not re-serve every field on every run, so a field with no movement here has not necessarily been re-confirmed.

What to verify and what to ask

1 not published

Fields UP-RERA has not published for this project. Coverage is uneven, so an absence is not evidence anything is wrong - only something this page cannot answer.

  • No fire-safety provision is published against this project’s registration.Ask which fire-safety approval the project holds or has applied for, and which authority issues it.

Common questions about VAISHALI RESIDENCY

Is VAISHALI RESIDENCY RERA registered?

Yes. VAISHALI RESIDENCY is registered with UPRERA under registration number UPRERAPRJ107791, registered on 24 Mar 2023. Estanzo reproduces that filing; it does not verify the work behind it.

When is possession due for VAISHALI RESIDENCY?

The completion date filed with UPRERA is 18 Oct 2028. No completion certificate is on record yet.

Who is the builder of VAISHALI RESIDENCY?

VASUNDHARA BUILDERS AND DEVELOPERS is the promoter entity that filed VAISHALI RESIDENCY with UPRERA (promoter RERA ID UPRERAPRM217741). RERA registers the legal entity behind a project, which may differ from the brand it is marketed under.

Does VAISHALI RESIDENCY have a RERA bank account?

Yes. The bank accounts filed with UPRERA for this project are listed on this page. Account details can change, so verify them against the official UPRERA source before making any payment.

Where is VAISHALI RESIDENCY located?

VAISHALI RESIDENCY is registered in Muzaffarnagar, as filed with UPRERA.

What configurations are available in VAISHALI RESIDENCY?

The unit plan filed with UPRERA lists 4 BHK and 3 BHK. That is the approved plan, not a live availability list - RERA does not publish what is still unsold.

What is the carpet area of flats in VAISHALI RESIDENCY?

The approved unit plan filed with UPRERA runs from 70 to 120 m² of carpet area (about 759 to 1,293 ft²). Carpet area is the net usable floor area the RERA Act defines and the only area the authority holds - a built-up or super-area figure quoted elsewhere is a larger number measured a different way.

How many towers and units are planned in VAISHALI RESIDENCY?

The approved unit plan describes 6 blocks and 406 units. UPRERA publishes no separate tower or unit count, so both are counted from that plan.

How dense is VAISHALI RESIDENCY?

About 95 units per acre: 406 planned units across 4.26 acres (17,257 m²) as filed with UPRERA. Both figures are the authority's; the division is ours.

Data as reported by UPRERA, as of 21 Oct 2026. official source ↗