Vertex Luxarium Phase II is a RERA-registered real-estate project in Ghaziabad (RERA ID UPRERAPRJ583422). Its RERA-registered completion deadline (14 Oct 2025) has passed with no occupancy certificate (OC) on record. Data as reported by UP-RERA. as reported by UPRERA
RERA status as reported: Registered.| RERA ID | UPRERAPRJ583422 |
| Applicant type | Company |
| Project category | Commercial |
| Project type | other |
| RERA status | Registered |
| Proposed start | 15 Oct 2022 |
| Project duration | 48 |
| Address | Ghaziabad, Ghaziabad |
| RERA registered | 4 Nov 2022 |
| Promised completion | 14 Oct 2025 |
| Revised completion | — none granted |
| Completion certificate filed | — not on record |
| Registration fee | ₹9,700 |
| Configuration | Units | Carpet area |
|---|---|---|
| SHOP | 34 | 54–180 |
| Permit no. | Date | Valid upto | Revised end |
|---|---|---|---|
| Retail Shop/02560/GDA/BP/21-22/0027/02022022 | 7 Feb 2022 | 6 Feb 2027 | 14 Oct 2025 |
| Khasra | Area | Type |
|---|---|---|
| 1523 | 485 | Khasra |
| C1A/B | 485 | Plot |
| Quarter | Construction | Certificates | Source |
|---|---|---|---|
| 2022-Q3 | — | CA · Arch · Eng | view ↗ |
| 2022-Q4 | 17% | CA · Arch · Eng | view ↗ |
| 2023-Q1 | 17% | CA · Arch · Eng | view ↗ |
| 2023-Q2 | 19% | CA · Arch · Eng | view ↗ |
| 2023-Q3 | 21% | CA · Arch · Eng | view ↗ |
| 2023-Q4 | 23% | CA · Arch · Eng | view ↗ |
| 2024-Q1 | 24% | CA · Arch · Eng | view ↗ |
| 2024-Q2 | 24.5% | CA · Arch · Eng | view ↗ |
| 2024-Q3 | 22% | CA · Arch · Eng | view ↗ |
| 2024-Q4 | 25% | CA · Arch · Eng | view ↗ |
| 2025-Q1 | 25% | CA · Arch · Eng | view ↗ |
| 2025-Q2 | 7% | CA · Arch · Eng | view ↗ |
| 2025-Q3 | 54% | CA · Arch · Eng | view ↗ |
| 2025-Q4 | 60% | CA · Arch · Eng | view ↗ |
| 2026-Q1 | 65% | CA · Arch · Eng | view ↗ |
Other projects registered in Ghaziabad.
Yes. Vertex Luxarium Phase II is registered with UPRERA under registration number UPRERAPRJ583422, registered on 4 Nov 2022. Estanzo reproduces that filing; it does not verify the work behind it.
Vertex Luxarium Phase II is 10 months past the completion date filed with UPRERA (14 Oct 2025), with no occupancy certificate on record. That is the authority's own dates subtracted — not an assessment of the builder.
Vertex Luxarium Phase II is registered in Ghaziabad, as filed with UPRERA.
Data as reported by UPRERA, last collected 4 Aug 2026. official source ↗