Estanzo

Timeline Bar

Registered4 Apr 2024
Today29 Jul 2026
Promised28 Dec 2028

Timeline

Promised completion28 Dec 2028
Revised completion28 Dec 2028
Actual completion
Possession delayOn time

Registration & Cost Details

Registration fee (in ₹)₹2,27,500
Project cost (in ₹ Lakhs)₹75,400 Lakhs
Project duration59 months
Project categoryResidential
LocalitySector 22D
Original start date
Proposed start date1 Feb 2024

Inventory

Total units1166
Unit TypeUnitsCarpet Area (sqm)
2 BHK8083.172–113.304
3 BHK90691.963–149.083
4 BHK180157.514

Promoters & Contact

Contact Details

Applicant TypePartnership Firm
Mobile9999454799
Emailacerera@acegroupindia.com
Coordinator9899109659
Address7TH FLOOR ,PLOT NO.01/B ,SECTOR-126 ,NOIDA -201303

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2023-Q4
2024-Q1
2024-Q2
2024-Q3
2024-Q4
2025-Q1
2025-Q219.2%
2025-Q323.4%
2025-Q422.2%
2026-Q125.6%

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
YEA/Planning/06/202329 Dec 202328 Dec 202828 Dec 202828 Dec 2033

Land Parcels

Khasra No.AreaPlot Type
Plot no P5 and P6, TS-02/A, Sector 22 D Yamuna Expressway UP44440Plot

Approved Unit Plan

Unit plan rows on file324
Total flats (sum of rows)1166
BlocksTOWER A1, TOWER A2, TOWER-B1, TOWER-B2, TOWER-B3, TOWER-B4, TOWER-C1, TOWER-C2, TOWER-C3, TOWER-C4, TOWER-C5, TOWER-C6
Floor types2 BHK, 3 BHK, 4 BHK, OTHER

Individual floor/unit rows are not listed here.

Frequently Asked Questions

What is the RERA registration number of Ace Terra?

The RERA registration number of Ace Terra is UPRERAPRJ683816, as recorded on the UP-RERA portal.

What is the RERA status of Ace Terra?

As reported by UP-RERA, the status of Ace Terra is "Registered".

Where is Ace Terra located?

As reported to UP-RERA, Ace Terra is located at Plot P5 & P6, TS-02/A, Sector 22D, Yamuna Expressway, Gautam Buddha Nagar, UP, Sector 22D, Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

When will Ace Terra be completed?

The latest completion date reported to UP-RERA for Ace Terra is 28 Dec 2028.

Is Ace Terra delayed?

Measured against the latest completion date reported to UP-RERA, Ace Terra is on time.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 28 Jul 2026