Registered21 Mar 2025
Today3 Aug 2026
Promised31 Mar 2028

Timeline

Promised completion31 Mar 2028
Revised completion31 Mar 2028
Actual completion
Possession delayOn time

Registration & Cost Details

Registration fee (in ₹)₹12,76,500
Project cost (in ₹ Lakhs)₹89,767 Lakhs
Project duration36 months
Project categoryResidential
LocalitySECTOR-22D, YAMUNA EXPRESSWAY,
Original start date
Proposed start date1 Apr 2025

Inventory

Total units

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9643007884
Emailrealty@atsgreens.com
Coordinator9643007884
Helpline01207111500
Address711/92, Deepali Nehru Place, South Delhi, India 110091

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2025-Q1
2025-Q22.3%
2025-Q32.3%
2025-Q420.0%
2026-Q136.0%

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
YEA/PLNG/686/202423 Sept 202422 Sept 202931 Mar 202822 Sept 2029

Land Parcels

Khasra No.AreaPlot Type
TS-02A409552.515Plot

Frequently Asked Questions

What is the RERA registration number of PROVINCE D OLYMPIA?

The RERA registration number of PROVINCE D OLYMPIA is UPRERAPRJ556048, as recorded on the UP-RERA portal.

What is the RERA status of PROVINCE D OLYMPIA?

As reported by UP-RERA, the status of PROVINCE D OLYMPIA is "Registered".

Where is PROVINCE D OLYMPIA located?

As reported to UP-RERA, PROVINCE D OLYMPIA is located at PLOT NO. TS-02A,, SECTOR-22D, YAMUNA EXPRESSWAY,, Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

When will PROVINCE D OLYMPIA be completed?

The latest completion date reported to UP-RERA for PROVINCE D OLYMPIA is 31 Mar 2028.

Is PROVINCE D OLYMPIA delayed?

Measured against the latest completion date reported to UP-RERA, PROVINCE D OLYMPIA is on time.

Answers generated from this project's public UP-RERA record — data as reported by RERA.

Data as reported by RERA. View source · Scraped 3 Aug 2026