Estanzo

Timeline Bar

Registered31 Jul 2017
Promised4 Sept 2019
Completed1 Apr 2022

Timeline

Promised completion4 Sept 2019
Revised completion4 Sept 2019
Actual completion1 Apr 2022
Possession delay31 mo delay

Registration & Cost Details

Registration fee (in ₹)₹43,520
Project cost (in ₹ Lakhs)₹1,77,000 Lakhs
Project duration80 months
Project categoryResidential
Locality
Original start date4 Jul 2014
Proposed start date4 Jul 2014

Inventory

Total units1146
Unit TypeUnitsCarpet Area (sqm)
2 BHK72070.23–79.99
3 BHK42683.24–112.41

Promoters & Contact

Contact Details

Applicant TypeCompany
Mobile9643007884
Emailrealty@atsgreens.com
Coordinator9643007884
Address711/92, Deepali Nehru Place, South Delhi, India 110091

No promoter data available.

Quarterly Progress Reports

PeriodConstruction ProgressFiled DateCertificatesSource
2020-Q184.6%
2020-Q285.4%
2020-Q386.2%
2020-Q4

Permit & Extension History

Permit NumberPermit DateValid UptoRevised End DateExtended Upto
745/PLNG/BP-08/P-0714 Nov 201313 Nov 20184 Sept 201913 Nov 2023
745/PLNG/BP-08/P-07

Revalidated: 745/PLNG/BP-08/P-07 (14 Nov 2013)

14 Nov 201313 Nov 2018

Revalidated upto: 1 Jan 1900

4 Sept 201913 Nov 2023

Land Parcels

Khasra No.AreaPlot Type
PLOT NO. P7, TS-02, SECTOR-22D, YEIDA, UP34323Plot

Approved Unit Plan

Unit plan rows on file70
Total flats (sum of rows)1146
BlocksTOWER-1, 5 & 8, TOWER-2,3,4,6 & 7
Floor types2 BHK, 3 BHK, OTHER

Individual floor/unit rows are not listed here.

Registry & Agreement Filings

Registry NumberRegistry DateLand TypeArea
1437112 Jun 2013

Frequently Asked Questions

What is the RERA registration number of ATS ALLURE?

The RERA registration number of ATS ALLURE is UPRERAPRJ918, as recorded on the UP-RERA portal.

What is the RERA status of ATS ALLURE?

As reported by UP-RERA, the status of ATS ALLURE is "Registered".

Where is ATS ALLURE located?

As reported to UP-RERA, ATS ALLURE is located at PLOT No. P7, TS-02, SECTOR-22D, YEIDA., Gautam Buddha Nagar, Gautam Budh Nagar, Uttar Pradesh.

Is ATS ALLURE completed?

As reported to UP-RERA, ATS ALLURE was completed on 1 Apr 2022.

Is ATS ALLURE delayed?

Measured against the latest completion date reported to UP-RERA, ATS ALLURE is 31 months beyond that date.

Answers generated from this project's public UP-RERA record — data as reported by RERA.